Permit Information
Permit NumberBLD12-03002
StatusIssued
Name VAN AUKER CONSTRUCTION
Site Address 618 N ALLUMBAUGH ST
Project NameDARIGOLD-WHEY TANK ADDITION
Customer Number 
ePlanReviewNo
Description
(DARIGOLD INC - WHEY STORAGE TANK) Permit is to construct a new 180 sq. ft. hallway addition and install two exterior whey tanks and one interior tank. Work to include: construct two new concrete pads for the new whey tanks, construct new foundation and 8" insulated CMU walls for the new access, construct and provide new concrete stairs, install new stainless steel pipe handrails, installation of new doors, installation of new emergency egress lighting, and installation of one new floor drain. All work per the approved plans, engineering, attached plan review report, and applicable codes. "This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department." **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/6/20133/8/20133/8/2013APASS
DetailsTom Arcoraci
Mike Phone #: ###-#### no card on site
FIRE-Final Inspection2/28/20133/1/20133/1/2013APART
DetailsTroy Cobbley
A temporary occupancy was given with scott arellano's permission. The existing fire alarm system needs to be extended into this new corridor. During my walk through of the existing building I found what appears to be non-compliant audio/visual portion of a fire alarm system. I found some rooms with smoke detectors, some at what appear to be fire doors. I also found strobes overspaced in one room and another with a ceiling mounted horn. I spoke to the superintendant, Ron, about contacting tim woodard in plan review to get the fire dept. involved with this.
BLD-Final2/28/20132/28/20132/28/2013PNR
DetailsTom Arcoraci
BLD-Final2/27/20132/28/20132/28/2013ANR
DetailsTom Arcoraci
Ron Phone #: ###-####
BLD-Framing/Rough-in12/31/20121/2/20131/2/2013APASS
DetailsJim Storey
RON Phone #: ###-####
BLD-Other12/21/201212/26/201212/26/2012APASS
DetailsJim Storey
ron Phone #: ###-#### rebar ok topped out.
BLD-Other12/20/201212/21/201212/21/2012APASS
DetailsJim Storey
rebar insp//Ron Phone #: ###-####
BLD-Foundation12/19/201212/20/201212/20/2012APART
DetailsMike Jordan
CMU inspection please-Pouring grout at 10:00--Ron Phone #: ###-####. ok pend.specia;l inspection.
BLD-Framing/Rough-in12/13/201212/14/201212/14/2012APART
DetailsJim Sly
Ronald-right before lunch if possible please Phone #: ###-####
Roof framing and decking around tank # 867.....OK
BLD-Foundation12/10/201212/10/201212/10/2012PPART
DetailsTony Young
Ron Phone #: ###-####,, pad for tank,, ok,, per plan,, also footings for short wall on west side of tanks and docks,, all pending special inspection reports,, blankets on site for cold weather
BLD-Foundation12/6/201212/7/201212/7/2012APASS
DetailsJim Storey
Ron Phone #: ###-####
BLD-Foundation11/30/201211/30/201211/30/2012PPASS
DetailsTom Arcoraci
Ron_Please call prior to inspection Phone #: ###-####