BLD-Final | 4/29/2014 | 4/29/2014 | 4/29/2014 | A | PASS |
Dave Hannah
|
|
|
Please call at least 30 mins in advance-Brice ###-####
|
FIRE-Final Inspection | 4/29/2014 | 4/29/2014 | 4/29/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 4/25/2014 | 4/25/2014 | 4/25/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Aging Inspection | 1/23/2014 | 1/23/2014 | 1/28/2014 | | CANC |
Jim Sly
|
|
|
|
BLD-Conference | 1/28/2014 | 1/28/2014 | 1/28/2014 | P | DONE |
Jim Sly
|
|
|
|
BLD-Final | 10/25/2013 | 10/25/2013 | 10/25/2013 | P | PART |
Jim Sly
|
|
|
Ryan Phone #: ###-#### OK for Temp Occ. OK for perm Occ when Fire Perms.
|
FIRE-Final Inspection | 10/23/2013 | 10/24/2013 | 10/24/2013 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given until the fire dept approves the height of the islands
|
FIRE-Final Inspection | 10/22/2013 | 10/23/2013 | 10/23/2013 | A | FAIL |
Troy Cobbley
|
|
|
Provide final approval from the fire dept for the storage tanks, provide sticker and indicator at the main exit, disable lock on the cooler door and repair the main exit discharge light
|
BLD-Final | 10/4/2013 | 10/7/2013 | 10/7/2013 | A | PASS |
Jim Sly
|
|
|
Ceiling cover insepction please-Ryan Phone #: ###-####
|
BLD-Energy code compliance | 8/23/2013 | 8/23/2013 | 8/23/2013 | P | PASS |
Jim Sly
|
|
|
ryan Phone #: ###-####
|
BLD-Framing/Rough-in | 8/12/2013 | 8/12/2013 | 8/12/2013 | P | PART |
Jim Sly
|
|
|
ryan Phone #: ###-#### Exterior shear fastening......OK.
|
BLD-Energy code compliance | 8/6/2013 | 8/7/2013 | 8/8/2013 | A | PART |
Dave Hannah
|
|
|
ryan Phone #: ###-#### ext walls thae coolers are built next to and the elec room ok to cover also oked the shear wall hold downs in the walls.
|
BLD-Framing/Rough-in | 8/1/2013 | 8/1/2013 | 8/1/2013 | P | PART |
Jim Sly
|
|
|
Ryan Phone #: ###-#### OK to cover walls behind Freezers.
|
BLD-Energy code compliance | 6/26/2013 | 6/27/2013 | 6/27/2013 | A | PART |
Jim Sly
|
|
|
Ryan Phone #: ###-#### Foundation insulation OK.
|
BLD-Foundation | 6/21/2013 | 6/24/2013 | 6/24/2013 | A | PASS |
Jim Sly
|
|
|
ryan Phone #: ###-#### Main Bldg .......OK pending MTI special insp,tests and approvals.
|
BLD-Concrete | 6/17/2013 | 6/18/2013 | 6/18/2013 | A | PART |
Jim Sly
|
|
|
Ryan Phone #: ###-#### Footing for Main Bldg. OK pending MTI special insp, tests and approvals. NOTE....Verified rebar for UFER ground tied to horizontal rebar, running full length around bldg perimeter.
|
BLD-Footing | 6/11/2013 | 6/12/2013 | 6/12/2013 | P | PART |
Jim Sly
|
|
|
Ryan Smith Phone #: ###-#### 10 large footing pads for Canopy OK pending MTI special inspection, tests and approvals.
|
BLD-Conference | 12/10/2012 | 12/10/2012 | 12/10/2012 | P | CANC |
Jim Sly
|
|
|
|
BLD-Conference | 12/10/2012 | 12/10/2012 | 12/10/2012 | P | CANC |
Jim Sly
|
|
|
|