Permit Information
Permit NumberBLD12-03121
StatusFinaled
Name BENITON CONSTRUCTION
Site Address 12127 W FRANKLIN RD
Project NameMaverik store #470
Customer Number 
ePlanReviewYes
Description
MAVERIK STORE #470 - To construct a new 4,600 square foot, one story, convenience store with a 7,070 sq. ft. metal canopy over 10 fuel dispensing stations and two 150 sq. ft. metal trellis roof structures, as well as, other related site improvements. Permit to construct a new Maverick fuel station with convenience market. The four (4) underground fuel storage tanks will require a separate Fire Department permit. A separate operational permit will be required by Boise Fire Department for the fueling operation. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/29/20144/29/20144/29/2014APASS
DetailsDave Hannah
Please call at least 30 mins in advance-Brice ###-####
FIRE-Final Inspection4/29/20144/29/20144/29/2014APASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection4/25/20144/25/20144/25/2014PPASS
DetailsTroy Cobbley
life safety passed
BLD-Aging Inspection1/23/20141/23/20141/28/2014 CANC
DetailsJim Sly
BLD-Conference1/28/20141/28/20141/28/2014PDONE
DetailsJim Sly
BLD-Final10/25/201310/25/201310/25/2013PPART
DetailsJim Sly
Ryan Phone #: ###-####
OK for Temp Occ. OK for perm Occ when Fire Perms.
FIRE-Final Inspection10/23/201310/24/201310/24/2013PPART
DetailsTroy Cobbley
A temporary occupancy is being given until the fire dept approves the height of the islands
FIRE-Final Inspection10/22/201310/23/201310/23/2013AFAIL
DetailsTroy Cobbley
Provide final approval from the fire dept for the storage tanks, provide sticker and indicator at the main exit, disable lock on the cooler door and repair the main exit discharge light
BLD-Final10/4/201310/7/201310/7/2013APASS
DetailsJim Sly
Ceiling cover insepction please-Ryan Phone #: ###-####
BLD-Energy code compliance8/23/20138/23/20138/23/2013PPASS
DetailsJim Sly
ryan Phone #: ###-####
BLD-Framing/Rough-in8/12/20138/12/20138/12/2013PPART
DetailsJim Sly
ryan Phone #: ###-####
Exterior shear fastening......OK.
BLD-Energy code compliance8/6/20138/7/20138/8/2013APART
DetailsDave Hannah
ryan Phone #: ###-#### ext walls thae coolers are built next to and the elec room ok to cover also oked the shear wall hold downs in the walls.
BLD-Framing/Rough-in8/1/20138/1/20138/1/2013PPART
DetailsJim Sly
Ryan Phone #: ###-####
OK to cover walls behind Freezers.
BLD-Energy code compliance6/26/20136/27/20136/27/2013APART
DetailsJim Sly
Ryan Phone #: ###-####
Foundation insulation OK.
BLD-Foundation6/21/20136/24/20136/24/2013APASS
DetailsJim Sly
ryan Phone #: ###-####
Main Bldg .......OK pending MTI special insp,tests and approvals.
BLD-Concrete6/17/20136/18/20136/18/2013APART
DetailsJim Sly
Ryan Phone #: ###-####
Footing for Main Bldg. OK pending MTI special insp, tests and approvals. NOTE....Verified rebar for UFER ground tied to horizontal rebar, running full length around bldg perimeter.
BLD-Footing6/11/20136/12/20136/12/2013PPART
DetailsJim Sly
Ryan Smith Phone #: ###-####
10 large footing pads for Canopy OK pending MTI special inspection, tests and approvals.
BLD-Conference12/10/201212/10/201212/10/2012PCANC
DetailsJim Sly
BLD-Conference12/10/201212/10/201212/10/2012PCANC
DetailsJim Sly