Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD12-03195
StatusFinaled
Name STEED CONSTRUCTION
Site Address 6224 W STATE ST
Project NameHendricks Vet Hospital
Customer Number 
ePlanReviewYes
Description
Hendricks Veterinary Hospital - To demolish and remove an existing 3,125 square foot veterinary office building and construct a new 3,525 square foot, one story, wood framed veterinary hospital and related site improvements. The new building will contain a waiting area, exam rooms, treatment and surgery areas, a feline boarding area and dog kennel area, as well as, office and lab areas. This building is not fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/25/201311/25/201311/25/2013PPASS
DetailsTony Young
Rick Phone #: ###-####,, ok for a c of o
BLD-Final10/17/201310/29/201310/29/2013APEND
DetailsTony Young
call before // Tim Phone #: ###-####,, still needs a landing
BLD-Final10/14/201310/15/201310/17/2013APART
DetailsTony Young
call before // Tim Phone #: ###-####,, temp occ.
BLD-Final10/14/201310/14/201310/15/2013PPEND
DetailsTony Young
call before // Tim Phone #: ###-####
BLD-Final10/9/201310/10/201310/14/2013APART
DetailsTony Young
call before // Tim Phone #: ###-####,, ok pending others,, needs a landing on rear door,, will pour concrete
FIRE-Final Inspection10/11/201310/11/201310/11/2013PPASS
DetailsTroy Cobbley
life safety passed
BLD-Conference10/9/201310/9/201310/9/2013PPART
DetailsTony Young
call before // Tim Phone #: ###-####,, walk through
FIRE-Final Inspection10/8/201310/8/201310/8/2013PPART
DetailsTroy Cobbley
A temporary occupancy is given with scotts permission until fire dept access signage is provided.
BLD-Energy code compliance9/4/20139/5/20139/5/2013ADONE
DetailsTony Young
gary Phone #: ###-####
BLD-Energy code compliance9/4/20139/4/20139/4/2013PPASS
DetailsTony Young
gary Phone #: ###-####
BLD-Energy code compliance9/3/20139/4/20139/4/2013APASS
DetailsTony Young
late morning - Rick Phone #: ###-####
BLD-Energy code compliance8/30/20139/3/20139/3/2013ACANC
DetailsTony Young
Phone #: ###-####,, nr
BLD-Framing/Rough-in8/30/20138/30/20138/30/2013PPART
DetailsTony Young
Tim; Phone #: ###-####,, need point load studs,, straps,, ok to insulate
BLD-Other6/17/20136/19/20136/19/2013APASS
DetailsTony Young
exterior wall shear nailing inspection, for cover.
Steed Supt. Gary Band ###-####
Framing Cont. Will Schiebe ###-#### Phone #: ###-#### >> Inspection requested via web by Gary Band,, ext shear ok
BLD-Conference6/4/20136/5/20136/5/2013APEND
DetailsTony Young
Framing contractor William Scheibe would like to discuss connection requirements and shear.
Rescheduled for a.m..
Ph #''s William Scheibe---- ###-####
Gary Band (steed)- ###-#### Phone #: ###-#### >> Inspection requested via web by Gary Band,, will get architect to answer ?s
BLD-Conference6/4/20136/4/20136/4/2013PCANC
DetailsTony Young
structural wood framers have several questions regarding allowable connections and shear construction
Steed Supt. Gary Band@ ###-#### or framing contractor, William Scheibe ###-#### Phone #: ###-#### >> Inspection requested via web by Gary Band Inspection cancelled from web by: Gary Band