BLD-Final | 4/4/2013 | 4/4/2013 | 4/4/2013 | P | PASS |
Mike Jordan
|
|
|
Ok for perm occ.
|
BLD-Final | 4/3/2013 | 4/4/2013 | 4/4/2013 | P | PART |
Mike Jordan
|
|
|
Would like to schedule building final for 4:00 p.m. on Thursday, April 4th..contact John ###-#### if you have any questions Phone #: ###-#### >> Inspection requested via web by Paul Saucerman. Will be ok for perm. occ once plumbing signs perm.
|
FIRE-Final Inspection | 4/3/2013 | 4/4/2013 | 4/4/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Conference | 3/20/2013 | 3/21/2013 | 3/21/2013 | A | DONE |
Troy Cobbley
|
|
|
Went over life safety requirements withJohn Saucerman Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/13/2013 | 3/14/2013 | 3/14/2013 | A | PART |
Mike Jordan
|
|
|
Ceiling grid inspection / electrical to submit for inspection tomorrow a.m. too / site representative - John ###-#### Phone #: ###-#### >> Inspection requested via web by Paul Saucerman. Ceiling grid ok pending electrical and mech. r.i. inspection.
|
BLD-Ceiling Grid Inspection | 3/12/2013 | 3/13/2013 | 3/13/2013 | P | CANC |
Mike Jordan
|
|
|
Ceiling grid inspection / please schedule for after 2:00 p.m. / site superintendent - John ###-#### Phone #: ###-#### >> Inspection requested via web by Paul Saucerman Inspection cancelled from web by: Paul Saucerman
|
BLD-Framing/Rough-in | 2/20/2013 | 2/21/2013 | 2/21/2013 | A | PASS |
Mike Jordan
|
|
|
Framing rough-in inspection / electrical and plumbing should be completed on 2/20/13. Call John (###-####) at the site if you have any questions. Phone #: ###-#### >> Inspection requested via web by Paul Saucerman
|