BLD-Final | 8/24/2015 | 8/25/2015 | 8/25/2015 | A | PART |
Jim Storey
|
|
|
Brett Phone #: ###-####
|
FIRE-Final Inspection | 8/24/2015 | 8/24/2015 | 8/24/2015 | P | CANC |
Thomas Walsh
|
|
|
TCO for this parking garage was granted with the provisions for a temporary waal to separate from the adjacent portion of the building still under construction. Final signoff of this permit is pending completion of the adjacent space and removal of this temporary wall.
|
BLD-Aging Inspection | 8/12/2015 | 8/12/2015 | 8/12/2015 | | NR |
Jim Storey
|
|
|
|
BLD-Final | 6/12/2015 | 6/17/2015 | 6/17/2015 | A | PART |
Jim Storey
|
|
|
JC Phone #: ###-####
|
FIRE-Final Inspection | 6/12/2015 | 6/15/2015 | 6/15/2015 | A | PEND |
Thomas Walsh
|
|
|
Final Fire/Life Safety inspection of the garage area for TCO clearance. Exit signs and emergency lighting tested OK (off generator). Fire sprinklers and fire alarm systems have also been finaled for this area. Fire Exttinguishers - OK Evac plans are temporary and permanent signs are being supplied by the owners. Knox box is installed and FD has been called to lock keys into it. Fire Lane marking sign has been installed. Only outstanding items to be addressed this week are, clean up fire pump room and secure doors, provide temporary address on the monument signs until permanant signs are installed,
|
BLD-Final | 6/12/2015 | 6/15/2015 | 6/15/2015 | A | CANC |
Jim Storey
|
|
|
Jesus Phone #: ###-####
|
BLD-Final | 6/12/2015 | 6/15/2015 | 6/15/2015 | A | CANC |
Bob Archibald
|
|
|
JC Phone #: ###-####
|
BLD-Final | 6/11/2015 | 6/12/2015 | 6/12/2015 | P | NR |
Tony Young
|
|
|
JC Phone #: ###-####,, conference only,, need trades 1st,, walk through only
|
BLD-Final | 6/9/2015 | 6/10/2015 | 6/10/2015 | P | NR |
Jim Storey
|
|
|
John Phone #: ###-####
|
FIRE-Conference | 5/9/2014 | 5/9/2014 | 5/9/2014 | A | DONE |
Forrest France
|
|
|
|
BLD-Other | 5/8/2014 | 5/8/2014 | 5/8/2014 | P | PASS |
Jim Storey
|
|
|
slab on deck rebar // JC Phone #: ###-#### rebar ok
|
BLD-Concrete | 3/14/2014 | 3/17/2014 | 3/17/2014 | A | PART |
Jim Storey
|
|
|
j.c. Phone #: ###-####
|
BLD-Other | 3/6/2014 | 3/7/2014 | 3/7/2014 | P | PART |
Jim Storey
|
|
|
basement walls and interior colum pads, concrete on Saturday // JC Phone #: ###-#### si to insp. work in progress.
|
BLD-Footing | 2/28/2014 | 3/3/2014 | 3/3/2014 | A | PASS |
Jim Storey
|
|
|
JC (concrete at noon) Phone #: ###-####
|
BLD-Footing | 2/11/2014 | 2/12/2014 | 2/12/2014 | A | PASS |
Jim Storey
|
|
|
JC Phone #: ###-####
|
BLD-Foundation | 1/16/2014 | 1/17/2014 | 1/17/2014 | A | PASS |
Jim Storey
|
|
|
JC Phone #: ###-#### rfi to follow 16" vert to match wall.
|
BLD-Footing | 1/10/2014 | 1/14/2014 | 1/14/2014 | P | NR |
Jim Storey
|
|
|
Rebar around 2 - Jc Phone #: ###-####
|
BLD-Footing | 1/9/2014 | 1/10/2014 | 1/10/2014 | P | DEFR |
Jim Storey
|
|
|
Rebar around 2 - Jc Phone #: ###-####
|