BLD-Framing/Rough-in | 4/22/2013 | 4/22/2013 | 4/22/2013 | P | PASS |
Mike Jordan
|
|
|
late pm//Jim Phone #: 559-. All framing issues resolved.
|
BLD-Energy code compliance | 4/22/2013 | 4/22/2013 | 4/22/2013 | P | PASS |
Mike Jordan
|
|
|
late pm//Jim Phone #: ###-####
|
BLD-Conference | 4/10/2013 | 4/11/2013 | 4/11/2013 | A | DONE |
Mike Jordan
|
|
|
meet at 9//Jim Phone #: ###-####. Went over all framing issues with contractor and issued a correction notice.
|
BLD-Framing/Rough-in | 4/10/2013 | 4/10/2013 | 4/10/2013 | P | PART |
Mike Jordan
|
|
|
Jim please call for access (3rd floor) Phone #: ###-####. Nail off all hangars, complete all fire blocking, complete airseal package and provide truss engineering. Called contractor and will meet on site tomorrow in the am.
|