BLD-Final | 4/23/2013 | 4/23/2013 | 4/23/2013 | P | PASS |
Jim Sly
|
|
|
dan Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 4/22/2013 | 4/23/2013 | 4/23/2013 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 4/22/2013 | 4/22/2013 | 4/22/2013 | P | FAIL |
Troy Cobbley
|
|
|
Will be ok to final life safety when the project related fire sprinkler permit is complete.
|
FIRE-Final Inspection | 4/5/2013 | 4/5/2013 | 4/5/2013 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given until the fire sprinkler permit is inspected and finaled.
|
BLD-Final | 4/5/2013 | 4/5/2013 | 4/5/2013 | P | CANC |
Jim Sly
|
|
|
OK for Temp occ. OK to perm when Fire perms.
|
BLD-Final | 4/3/2013 | 4/3/2013 | 4/3/2013 | P | NR |
Jim Sly
|
|
|
doug Phone #: ###-#### Called Doug....left V/M....Need Temp or Perm Occ approval from fire insp. prior to calling for Struct. insp.
|
BLD-Final | 4/2/2013 | 4/3/2013 | 4/3/2013 | A | CANC |
Jim Sly
|
|
|
call 1/2 hr ahead to meet//Dan Phone #: ###-#### Called Dan left V/M......Need Fire final.
|
FIRE-Final Inspection | 4/2/2013 | 4/2/2013 | 4/2/2013 | P | FAIL |
Troy Cobbley
|
|
|
Two pendant heads are overspaced off of the north wall in the Retail area. A temporary occupancy will be ok when the sprinkler contractor has submitted for approval.
|