BLD-Final | 6/5/2014 | 6/6/2014 | 6/5/2014 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 3/19/2014 | 3/19/2014 | 3/19/2014 | P | PASS |
Mike Jordan
|
|
|
late afternoon - Fred Phone #: ###-####. Ok for temp occ. Will be ok for perm occ. once zoning signs perm.
|
FIRE-Final Inspection | 3/19/2014 | 3/19/2014 | 3/19/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Wall cover | 12/2/2013 | 12/3/2013 | 12/3/2013 | A | PASS |
Mike Jordan
|
|
|
1st. floor, remainder of center units ok to tape.
|
BLD-Wall cover | 12/2/2013 | 12/2/2013 | 12/2/2013 | P | PART |
Mike Jordan
|
|
|
1st. floor, east central units ok to tape.
|
BLD-Wall cover | 11/27/2013 | 12/2/2013 | 12/2/2013 | A | PART |
Mike Jordan
|
|
|
Center Units first floor Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Work in progress, 1st. floor, center units.
|
BLD-Wall cover | 11/20/2013 | 11/20/2013 | 11/20/2013 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. 1st floor, base layer on ceilings ok.
|
BLD-Energy code compliance | 11/15/2013 | 11/15/2013 | 11/15/2013 | A | PASS |
Mike Jordan
|
|
|
Wall insulation Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
FIRE-Sprinkler Rough-in | 11/13/2013 | 11/13/2013 | 11/13/2013 | P | PASS |
Troy Cobbley
|
|
|
Tenting inspection passed
|
FIRE-Sprinkler Rough-in | 11/11/2013 | 11/12/2013 | 11/12/2013 | P | FAIL |
Troy Cobbley
|
|
|
Tenting inspection failed due to many problem areas. I left a voice message for Mike. Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Framing/Rough-in | 11/11/2013 | 11/12/2013 | 11/12/2013 | A | PART |
Mike Jordan
|
|
|
fire caulking / framing Phone #: ###-#### >> Inspection requested via web by Mike McHargue. ok to insulate. Pendinf electrical rough in inspection and firesprinkler tenting.
|
BLD-Energy code compliance | 11/11/2013 | 11/12/2013 | 11/12/2013 | A | PART |
Mike Jordan
|
|
|
Air Sill Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Air seal ok.
|
BLD-Conference | 10/30/2013 | 10/30/2013 | 10/30/2013 | A | DONE |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 10/15/2013 | 10/16/2013 | 10/16/2013 | A | PASS |
Mike Jordan
|
|
|
Hold downs blding 12, two no north end, two on south end. Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Missing and or loose holdowns installed and tightend.
|
BLD-Wall Bracing | 10/14/2013 | 10/15/2013 | 10/15/2013 | A | NR |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 10/14/2013 | 10/14/2013 | 10/14/2013 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Wall Bracing | 10/11/2013 | 10/14/2013 | 10/14/2013 | A | FAIL |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 10/9/2013 | 10/9/2013 | 10/9/2013 | P | FAIL |
Mike Jordan
|
|
|
North end hold downs re inspect Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Holdowns still missing or not yet installed.
|
BLD-Wall Bracing | 9/24/2013 | 9/24/2013 | 9/24/2013 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Exterior shear nailing ok, 1st. and 2nd. floors.
|
BLD-Concrete | 8/15/2013 | 8/15/2013 | 8/15/2013 | P | PASS |
Mike Jordan
|
|
|
North slab on grade thicken footings building 12 Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Concrete | 8/14/2013 | 8/15/2013 | 8/15/2013 | A | CANC |
Mike Jordan
|
|
|
North end building 12 slab thickend footing Phone #: ###-#### >> Inspection requested via web by Mike McHargue Inspection cancelled from web by: Mike McHargue
|
BLD-Concrete | 8/13/2013 | 8/13/2013 | 8/13/2013 | P | PART |
Mike Jordan
|
|
|
South slab on grade thickened footings Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 8/2/2013 | 8/2/2013 | 8/2/2013 | P | PASS |
Mike Jordan
|
|
|
North end foundation insulation inspection Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 7/31/2013 | 7/31/2013 | 7/31/2013 | P | PASS |
Mike Jordan
|
|
|
Foundation Insulation south end of building 12. Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Foundation | 7/30/2013 | 7/31/2013 | 7/31/2013 | A | PASS |
Mike Jordan
|
|
|
North half of building 12. John with foundations will call. Ready now. Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Foundation | 7/29/2013 | 7/29/2013 | 7/29/2013 | P | PART |
Mike Jordan
|
|
|
Blding 12 south end stemwall inspection. Ready for a 1PM pour. John with foundations will call. Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Stemwall and column pedestals, south half only.
|
BLD-Footing | 7/24/2013 | 7/24/2013 | 7/24/2013 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 7/24/2013 | 7/24/2013 | 7/24/2013 | A | NR |
Mike Jordan
|
|
|
Bld 12 footing rebar inspection. John with Foundations LLC will call to confirm time should be mid morning. Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Moved to pm.
|