BLD-Final | 9/9/2013 | 9/9/2013 | 9/9/2013 | P | PASS |
Mike Jordan
|
|
|
Hi Mike can we make this late afternoon I have final fire this pm Please call me 20 min before Thanks Dan ###-####n Phone #: ###-#### >> Inspection requested via web by Dan Elser. Ok for perm occ;.
|
FIRE-Final Inspection | 9/9/2013 | 9/9/2013 | 9/9/2013 | P | PASS |
Forrest France
|
|
|
Noted correction items verified for completion. Fire life safety finaled.
|
FIRE-Final Inspection | 9/6/2013 | 9/6/2013 | 9/6/2013 | A | FAIL |
Troy Cobbley
|
|
|
Remove the thumbturn lock at the main exit, provide canopies for the pendant sprinkler heads, remove tape from uprights in stock room. aquire a racking permit for the storage racks that exceed 8'.
|
BLD-Conference | 8/22/2013 | 8/23/2013 | 8/23/2013 | A | DONE |
Mike Jordan
|
|
|
Hi Mike Have a couple of questions please call before Thanks Dan Phone #: ###-#### >> Inspection requested via web by Dan Elser
|
BLD-Ceiling Grid Inspection | 8/15/2013 | 8/15/2013 | 8/15/2013 | P | PASS |
Mike Jordan
|
|
|
Hi Mike need inspection for ceiling grid electrical and fire have inspected .Thanks dan Phone #: ###-#### >> Inspection requested via web by Dan Elser
|
BLD-Conference | 8/12/2013 | 8/12/2013 | 8/12/2013 | P | DONE |
Mike Jordan
|
|
|
hi mike could you come by today the tenant would like to make a couple changes . Please call me @ ###-#### prior to coming by so I can make sure that i am there. Thanks Dan Phone #: ###-#### >> Inspection requested via web by Dan Elser. Spoke to contractor on moving one of the required exits at storefront closer to the main exit. Building is fully fire sprinklered, moving exit falls within the one third minimum distance exits need to be seperated.
|
BLD-Conference | 7/22/2013 | 7/22/2013 | 7/22/2013 | P | PASS |
Mike Jordan
|
|
|
framing inspection Please call Dan @ ###-#### before inspection Thanks Phone #: ###-#### >> Inspection requested via web by Dan Elser. Interior steel stud framed walls only. ok.
|