BLD-Final | 9/18/2013 | 9/19/2013 | 9/19/2013 | P | PASS |
Dave Hannah
|
|
|
john Phone #: ###-####
|
FIRE-Final Inspection | 9/16/2013 | 9/17/2013 | 9/17/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
BLD-Ceiling Grid Inspection | 9/12/2013 | 9/13/2013 | 9/13/2013 | A | PASS |
Dave Hannah
|
|
|
john Phone #: ###-####
|
BLD-Framing/Rough-in | 8/29/2013 | 8/29/2013 | 8/29/2013 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-#### tempered markings are on glass they are under molding
|
BLD-Final | 8/21/2013 | 8/22/2013 | 8/28/2013 | P | PART |
Dave Hannah
|
|
|
phase 1 only - jeffrey Phone #: ###-#### ok to move into phase one need to have find tempering markings on glass walls
|
FIRE-Final Inspection | 8/21/2013 | 8/22/2013 | 8/22/2013 | A | PART |
Forrest France
|
|
|
Fire life safety okayed for "phase one" of the remodel work to date.
|
BLD-Ceiling Grid Inspection | 8/19/2013 | 8/19/2013 | 8/19/2013 | P | PASS |
Dave Hannah
|
|
|
john Phone #: ###-####
|
BLD-Conference | 7/22/2013 | 7/23/2013 | 7/23/2013 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### 17 th and mec deck
|
BLD-Framing/Rough-in | 7/19/2013 | 7/19/2013 | 7/19/2013 | P | PART |
Tony Young
|
|
|
John Phone #: ###-####,, walls ok
|