BLD-Final | 7/23/2014 | 7/23/2014 | 7/23/2014 | A | PASS |
Jim Sly
|
|
|
if possible 10:30 to 12:00 Phone #: ###-#### Inspection requested via web by phil doble
|
DOC - Permit Finaled | 7/23/2014 | 7/23/2014 | 7/23/2014 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 7/23/2014 | 7/23/2014 | 7/23/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 7/17/2014 | 7/17/2014 | 7/17/2014 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by phil doble
|
BLD-Wall cover | 6/19/2014 | 6/20/2014 | 6/20/2014 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble
|
BLD-Ceiling Grid Inspection | 5/6/2014 | 5/6/2014 | 5/6/2014 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble
|
FIRE-Sprinkler Rough-in | 4/30/2014 | 4/30/2014 | 4/30/2014 | P | PART |
Forrest France
|
|
|
Okay to cover overhead fire sprinkler work completed to date as marked on approved plans including endo #4.
|
BLD-Wall cover | 4/15/2014 | 4/15/2014 | 4/15/2014 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble
|
BLD-Final | 3/25/2014 | 3/26/2014 | 3/26/2014 | A | PART |
Dave Hannah
|
|
|
temp occ. Phone #: ###-#### >> Inspection requested via web by phil doble ok to move into phase one
|
BLD-Ceiling Grid Inspection | 2/28/2014 | 2/28/2014 | 2/28/2014 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble
|
BLD-Ceiling Grid Inspection | 2/6/2014 | 2/7/2014 | 2/7/2014 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble
|
BLD-Wall cover | 1/21/2014 | 1/21/2014 | 1/21/2014 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble
|
BLD-Wall cover | 1/6/2014 | 1/7/2014 | 1/7/2014 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by phil doble ok to cover walls 1st phase
|