Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD13-01688
StatusFinaled
Name THE ROBINS & MORTON GROUP
Site Address 8800 W EMERALD ST
Project NameTreasure Valley Hospital
Customer Number 
ePlanReviewYes
Description
(TREASURE VALLEY HOSPITAL – Addition) This permit is to construct a 14,320 square foot addition onto an existing single story 30,629 square foot hospital creating a new 44,949 square foot hospital. PLAN MODIFICATION 3-20-14 – Modification submitted to add a 720 square foot all aluminum patio cover for an outside eating area.**TLW** Plans approved in conjunction with BLD13-01539 for foundation and superstructure. Scope of work: construct new interior and exterior walls, installation of new plumbing, [construction of interior non-bearing walls to create additional sleeping rooms, operating rooms, and support rooms], new lighting, new accessible doors / hardware, and interior finishes. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/9/201412/10/201412/10/2014APASS
DetailsMike Jordan
Charles Phone #: ###-####. All phases completed. Ok for perm occ.
FIRE-Final Inspection12/4/201412/5/201412/5/2014APASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection12/3/201412/4/201412/4/2014APART
DetailsTroy Cobbley
Life safety will be ok to final when the project related fire sprinkler permit is finaled
BLD-Final11/5/201411/6/201411/6/2014APART
DetailsMike Jordan
Garrett Phone #: ###-####. Ok to occupy phase 3A, pre op and physicians lounge.
BLD-Ceiling Grid Inspection11/5/201411/5/201411/5/2014PPASS
DetailsMike Jordan
Garrett Phone #: ###-####
FIRE-Final Inspection10/29/201410/30/201410/30/2014APART
DetailsTroy Cobbley
Pre-op and Doctors Lounge life safety is complete
BLD-Framing/Rough-in10/22/201410/22/201410/22/2014PPASS
DetailsMike Jordan
charles Phone #: ###-####. Interior steel stud framed wall at decon 160.
BLD-Ceiling Grid Inspection10/15/201410/16/201410/16/2014APASS
DetailsMike Jordan
Charles Phone #: ###-####. Pre op D101, rms B161 , B162 Dictation C163 and breakdown B111 ok.
BLD-Final9/29/20149/30/20149/30/2014APART
DetailsMike Jordan
Garrett Phone #: ###-####. ok to occupy sterile storage, and phase 2 of lobby remodel. Also verified that exit sign has been repaired.
FIRE-Final Inspection9/29/20149/30/20149/30/2014APART
DetailsTroy Cobbley
Life safety passed in Sterile Storage
BLD-Ceiling Grid Inspection9/25/20149/26/20149/26/2014PPASS
DetailsPhil Shearer
garrett Phone #: ###-####
FIRE-Final Inspection9/16/20149/17/20149/17/2014PPART
DetailsTroy Cobbley
Remodeled portion of Main Lobby and connecting corridor life safety passed. Electritian is to repair an existing exit sign in the path of egress.
BLD-Framing/Rough-in9/17/20149/17/20149/17/2014PCANC
DetailsMike Jordan
Charles Phone #: ###-####
BLD-Framing/Rough-in9/15/20149/16/20149/16/2014PPASS
DetailsMike Jordan
Garrett Phone #: ###-####. Interior steel stud framed walls pre-op, D101, dictation C163, Annes work B161 and physicians lounge B162.
BLD-Ceiling Grid Inspection9/3/20149/4/20149/4/2014PPASS
DetailsMike Jordan
Derek Phone #: ###-####. grid ok as well as all firestopping rooms C117, C116, C110 and portion of corridor C111.
BLD-Final8/27/20148/28/20148/28/2014APART
DetailsMike Jordan
Charles Phone #: ###-####. Male and female locker rooms ok to occupy.
BLD-Final8/19/20148/20/20148/20/2014APART
DetailsMike Jordan
Charles Phone #: ###-####. Ok to occupy pacu, purchasing office B167 and General Storage B165. Male and female lockers not ready at this time.
FIRE-Final Inspection8/18/20148/19/20148/19/2014APART
DetailsTroy Cobbley
Life safety is complete in the Locker Rooms/Storage/PACU areas.
FIRE-Final Inspection8/15/20148/18/20148/18/2014AFAIL
DetailsTroy Cobbley
Life safety for new phase will be ok to final went the project related fire alarm work for this area is complete.
BLD-Ceiling Grid Inspection8/14/20148/14/20148/14/2014PPASS
DetailsMike Jordan
charles Phone #: ###-####. Male and female lockers C101 and C103.
BLD-Ceiling Grid Inspection8/11/20148/12/20148/12/2014APASS
DetailsMike Jordan
Charles Phone #: ###-####. General storage B165 and purchsing office 167 ok. All firecaulking completed and inspected.
BLD-Framing/Rough-in8/7/20148/8/20148/8/2014APASS
DetailsMike Jordan
Charles Phone #: ###-####. Interior steel stud framed walls at phase 2 of lobby remodel, work room C110 and reception C117.
BLD-Ceiling Grid Inspection8/7/20148/8/20148/8/2014APART
DetailsMike Jordan
Charles Phone #: ###-####. ceiling grid ok in general storage room B165. Didnote some penetrations not yet fire caulked. Will reinspect on monday.
BLD-Ceiling Grid Inspection7/28/20147/29/20147/29/2014APART
DetailsJim Sly
Garrett Phone #: ###-####
PAC U.......OK
BLD-Framing/Rough-in7/15/20147/16/20147/16/2014PPART
DetailsMike Jordan
Charles Phone #: ###-####. Interior steel stud framed walls at phase 2C male/female lockers and showers as well as general storage, IT and purchasing offices. Room #C100, 101, 102,103, B165, 166 and 167. Pending plumbing rough in.
BLD-Conference7/15/20147/15/20147/15/2014ADONE
DetailsMike Jordan
jobsite visit to check on progress. Contractor noted that they would be calling in for a framing inspection tomorrow in the pm.
FIRE-Final Inspection6/25/20146/26/20146/26/2014APART
DetailsTroy Cobbley
Requested paperwork signed for Charles Phone #: ###-####
BLD-Final6/25/20146/26/20146/26/2014APART
DetailsMike Jordan
Charles Phone #: ###-####. Phase 2b, north portion of lobby remodel , equipment storage rm. #103 and lab a102 ok to occupy.
FIRE-Final Inspection6/23/20146/24/20146/24/2014PPART
DetailsTroy Cobbley
life safety is complete in the Lab, Equipment Room and north half of the remodeled Lobby.
BLD-Ceiling Grid Inspection6/23/20146/23/20146/23/2014PPASS
DetailsMike Jordan
Charles Phone #: ###-####. lobby remodel.
BLD-Framing/Rough-in6/17/20146/17/20146/17/2014PPART
DetailsMike Jordan
Charles Phone #: ###-####. Interior steel stud walls phase 2 part B eqiupment storage B144 restrooms D104, D105 and North wall at room 107.
BLD-Ceiling Grid Inspection6/12/20146/12/20146/12/2014PPASS
DetailsMike Jordan
Charles Phone #: ###-####. Phase 2 equipment storage and lab rooms ok.
BLD-Framing/Rough-in5/19/20145/21/20145/21/2014APASS
DetailsMike Jordan
CHARLES Phone #: ###-####. phase 2, framing for lobby remodel ok.
BLD-Conference5/19/20145/19/20145/19/2014ADONE
DetailsMike Jordan
Framing in lobby remodel phase 2. Should be ready for formal framing inspection on wednesday.
BLD-Conference5/14/20145/14/20145/14/2014PDONE
DetailsMike Jordan
Work in progress on waiting area remodfel, phase 2.
BLD-Framing/Rough-in5/8/20145/9/20145/9/2014PPASS
DetailsMike Jordan
charles Phone #: ###-####. Phase 2 interior steel stud walls and shaft walls for storage and lab rooms ok to cover.
BLD-Conference5/7/20145/7/20145/7/2014ADONE
DetailsMike Jordan
Job site check in. Interior steel stud framing in progress. In phase 2. Per contractor should be ready for framing inspection on monday may 12th.
BLD-Conference4/30/20144/30/20144/30/2014PDONE
DetailsMike Jordan
Walk through on work in progress for phase 2.
BLD-Final4/22/20144/22/20144/22/2014PPASS
DetailsMike Jordan
Charles Phone #: ###-####. phase 1c medical records ok to occupy.
BLD-Final4/22/20144/22/20144/22/2014APART
DetailsMike Jordan
Phase 1A, O.R. and recovery rooms only ok to occupy.
FIRE-Final Inspection4/17/20144/21/20144/21/2014APART
DetailsTroy Cobbley
Remodeled area 1C, life safety is passed
BLD-Final4/17/20144/18/20144/18/2014APART
DetailsMike Jordan
O.R. addition ready for final. The O.R. addition only is ok to occupy.
BLD-Final4/17/20144/17/20144/17/2014PCANC
DetailsMike Jordan
moved to am. Life safety for the or addition has passed, but was entered in error under bld14-00903. I have contacted troy c. and left a message for him.
FIRE-Final Inspection4/16/20144/17/20144/17/2014APART
DetailsTroy Cobbley
Life safety passed in the new OR area. See the city approved plans for marked location
BLD-Final4/17/20144/17/20144/17/2014PNR
DetailsMike Jordan
Mark-patio cover in back Phone #: ###-####. This in regards to the patio cover that has been added to scope of work. Patio cover is complete, but the sprinkler system has not yey been extended in to the covered patio area.
BLD-Final4/16/20144/17/20144/17/2014ACANC
DetailsMike Jordan
Charles Phone #: ###-####. Moved to pm pending fire alarm.
BLD-Conference4/16/20144/16/20144/16/2014PDONE
DetailsMike Jordan
FIRE-Final Inspection4/15/20144/16/20144/16/2014PFAIL
DetailsTroy Cobbley
Life safety for the new OR area will be ok to pass when the project related fire alarm system for this area has been inspected and passed as well.
BLD-Final4/15/20144/15/20144/15/2014PPART
DetailsMike Jordan
Charles Phone #: ###-####. Phase 1a patient addition only ok to occupy.
BLD-Footing4/14/20144/15/20144/15/2014APASS
DetailsMike Jordan
SHawn Phone #: ###-####. footings for new patio cocer.
BLD-Conference4/8/20144/9/20144/9/2014ACANC
DetailsMike Jordan
BLD-Ceiling Grid Inspection4/8/20144/9/20144/9/2014APASS
DetailsMike Jordan
grid in cafeteria ok.
BLD-Ceiling Grid Inspection4/4/20144/7/20144/7/2014APASS
DetailsTom Arcoraci
Charles Phone #: ###-####
BLD-Conference4/2/20144/2/20144/2/2014PDONE
DetailsMike Jordan
Walk through at OR addition. Inspected in progress work of ceiling grid install and firecaulking.
BLD-Conference4/2/20144/2/20144/2/2014ACANC
DetailsMike Jordan
Moved to pm.
BLD-Ceiling Grid Inspection3/31/20144/1/20144/1/2014APASS
DetailsMike Jordan
charles Phone #: ###-####. Areas A and B ok to cover.
FIRE-Final Inspection3/28/20143/31/20143/31/2014APART
DetailsTroy Cobbley
New Patient Wing Life safety complete.
BLD-Framing/Rough-in3/31/20143/31/20143/31/2014APART
DetailsMike Jordan
Soffit in cafeteria. Steel stud framing for soffit in cafeteria ok. Partial walk through on ceiling grid and fire caulking at Areas A and B. Aslo inspected doors and door frames in 1 hr. corridor at patient addition.
BLD-Framing/Rough-in3/26/20143/27/20143/27/2014AFAIL
DetailsTom Arcoraci
Charles Miller ###-#### unable to locate superintendent on site no ans on phone
BLD-Ceiling Grid Inspection3/24/20143/25/20143/25/2014APASS
DetailsMike Jordan
garret Phone #: ###-####. Framing for hardlid in OR# 6 ok to cover.
BLD-Ceiling Grid Inspection3/20/20143/21/20143/21/2014APASS
DetailsMike Jordan
Charles Phone #: ###-####. Ceiling grid ok to cover.
BLD-Framing/Rough-in3/19/20143/20/20143/20/2014APART
DetailsMike Jordan
CHARLES Phone #: ###-####. hardlid for OR# 5 ok to sheet rock. Ceiling grid in patient addition ok. Noted some penetrations not yet firecaulked. Will reinspect tomorrow.
BLD-Conference3/18/20143/19/20143/19/2014ADONE
DetailsMike Jordan
Walked job and discussed the addition of a possible patio cover.
BLD-Framing/Rough-in3/17/20143/18/20143/18/2014APASS
DetailsMike Jordan
Charles Miller Phone #: ###-####. Interior steel stud framed 1hr. Fire barrier wall at gridline 11 between grids C to D.8, seperation between Suite C and Suite B.
BLD-Framing/Rough-in3/14/20143/17/20143/17/2014APASS
DetailsMike Jordan
charles Phone #: ###-####. Hrdlids ok to cover in OR#4. Soffits for nurses station D116 and D110.
BLD-Framing/Rough-in3/13/20143/13/20143/13/2014PPART
DetailsMike Jordan
charles Phone #: ###-####. Hardlid for OR#4. Pending electrical rough in.
BLD-Conference3/11/20143/12/20143/12/2014ADONE
DetailsMike Jordan
BLD-Framing/Rough-in3/12/20143/12/20143/12/2014APASS
DetailsMike Jordan
Interior steel studs for fire barrier walls in exisiting building at for medical records room C109, corridor C105, and offices C106,C107 and C110.
BLD-Framing/Rough-in3/7/20143/7/20143/7/2014PPASS
DetailsMike Jordan
Garrett Phone #: ###-####. Interior steel stud firebarrier wall at gridline 8 between grids B to D.(compartment wall for suite C)
BLD-Conference3/4/20143/5/20143/5/2014ADONE
DetailsMike Jordan
Walk through with tim Woodard, plan reviewer for project.
BLD-Conference3/4/20143/4/20143/4/2014PCANC
DetailsMike Jordan
BLD-Framing/Rough-in3/4/20143/4/20143/4/2014PPASS
DetailsMike Jordan
Interior steel stud walls for soiled laundry and wash room at siute B.
BLD-Conference2/26/20142/26/20142/26/2014PPASS
DetailsMike Jordan
Walk through on patient addition to inspect partial ceiling grid and firestopping. Aslo wlak through on work in progress in area B.
BLD-Conference2/18/20142/19/20142/19/2014PPASS
DetailsMike Jordan
Patient addition walk through, inspected membrane and through penetration firecaulikng.
BLD-Energy code compliance2/19/20142/19/20142/19/2014PPASS
DetailsMike Jordan
Exterior walls at OR addtion.
BLD-Conference2/18/20142/19/20142/19/2014ACANC
DetailsMike Jordan
Moved to PM.
BLD-Framing/Rough-in2/18/20142/18/20142/18/2014PPASS
DetailsMike Jordan
Charles Miller Phone #: ###-####. Interior steel stud framed walls for the remainder of suite B. (area C).
BLD-Conference2/18/20142/18/20142/18/2014ACANC
DetailsMike Jordan
BLD-Conference2/12/20142/13/20142/13/2014PDONE
DetailsMike Jordan
Went over UL assemblies with general contractor and firestop contractor and resolved issues regarding membrane protection for med gas and through penetrations for insulated steel pipe.
BLD-Conference2/11/20142/12/20142/12/2014PCANC
DetailsMike Jordan
BLD-Conference2/11/20142/12/20142/12/2014APART
DetailsMike Jordan
Reviewed fire stopping submittals. PArtial walk through at patient addition to inspect firestopping. Will need to provide details for opening protection for med and oxygen gas in firebarrier wall at gridline 8. Aslo need to discuss UL for cleanouts.
BLD-Framing/Rough-in2/12/20142/12/20142/12/2014PPASS
DetailsMike Jordan
Charles Phone #: ###-####. Interior walls at suite C ok. Compartment wall (fire Barrier) om gridline C ok to rock from 11ft. elevation to top of deck. Interior walls on siute B at gridlines 9.7 to 13 from AA to C. Also verified putty pads on fire barrier wall on gridline 8.
BLD-Framing/Rough-in2/7/20142/10/20142/10/2014PPASS
DetailsMike Jordan
charles Miller Phone #: ###-####. interior steel stud walls in suite C at gridlines 8 to 9.7 and AA to c.
BLD-Conference2/3/20142/5/20142/5/2014ACANC
DetailsMike Jordan
BLD-Conference2/5/20142/5/20142/5/2014PDONE
DetailsMike Jordan
Discussed UL approved details for firestopping and area suites.
BLD-Final1/31/20142/3/20142/4/2014PPART
DetailsMike Jordan
garrett or ###-#### Phone #: ###-####. Partial final only for the phase 1 partB admin. offices only ok to occupy. All other trades and life safety have signed off in this area.
BLD-Conference2/3/20142/5/20142/3/2014PCANC
DetailsMike Jordan
garrett or ###-#### Phone #: ###-####
BLD-Framing/Rough-in2/3/20142/3/20142/3/2014PPART
DetailsMike Jordan
garrett or ###-#### Phone #: ###-####. Interior steel stud walls at sterile passage corridorB138, ok to rock from 11ft. elevation to top of wall. West exterior wall from grid line AA betweeen greids 8.7 to 13 ok to cover, ok to cover electrical room B123.
FIRE-Final Inspection1/31/20142/3/20142/3/2014APASS
DetailsTroy Cobbley
Life safety for Phase 1B is passed. See the life safey plan sheet for area high lighted and signed.
BLD-Final1/31/20141/31/20141/31/2014PNR
DetailsMike Jordan
charles Phone #: ###-####. Needs fire/life/safety.
BLD-Conference1/29/20141/29/20141/29/2014PCANC
DetailsMike Jordan
BLD-Conference1/29/20141/29/20141/29/2014APART
DetailsMike Jordan
Work in progress on Phase 1 part A, inspected door frames in corridor. Partial framing in phase 1 part B, noted that electrical Isolation boxes inproperly wrapped at rated corridor. Also reviewed special inspection reports to date. Pre walk through on Admin area remodel prior to temp. final on friday.
BLD-Ceiling Grid Inspection1/6/20141/6/20141/6/2014PPASS
DetailsMike Jordan
charles Phone #: ###-####. Ceiling grid inspection for phase 1B remodel ok.
BLD-Framing/Rough-in12/18/201312/19/201312/19/2013APART
DetailsMike Jordan
CHARLES Phone #: ###-####. Top of wall for firewalls @ corridor on grids H and H.3 from 1 to 3.9 for phase 1 patient addition, pending electrical inspection. Steel stud framing for exterior walls at phase 1 part B. Also noted steel track at phase 1 patient addition has been shot down per the approved engineering.
BLD-Framing/Rough-in11/26/201311/26/201311/26/2013PPART
DetailsMike Jordan
Charles Phone #: ###-####. Exterior steel stud framed walls for phase 1 partA patient addition at gridlines 1 to 4 and on gridlines G to J. All work per the contractors egineering. Will get copy to have scanned into case. Noted that contractor is lacking shot spacing on the bottom track connection to concrete. Will reinspect on next inspection. ok to cover exterior only.
BLD-Framing/Rough-in11/1/201311/4/201311/4/2013APASS
DetailsMike Jordan
Interior steel stud walls at phase 1, part B. Gridlines 4 to 5.7 and grid lines C to E (Admin offices) ok to cover.
BLD-Other10/24/201310/25/201310/25/2013PPASS
DetailsMike Jordan
Rebar - Charles Phone #: ###-####. Footings and interior column pad footings at part B.
BLD-Framing/Rough-in11/1/201311/1/2013 P 
DetailsMike Jordan
Charles Phone #: ###-####