BLD-Final | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. All phases completed. Ok for perm occ.
|
FIRE-Final Inspection | 12/4/2014 | 12/5/2014 | 12/5/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 12/3/2014 | 12/4/2014 | 12/4/2014 | A | PART |
Troy Cobbley
|
|
|
Life safety will be ok to final when the project related fire sprinkler permit is finaled
|
BLD-Final | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | PART |
Mike Jordan
|
|
|
Garrett Phone #: ###-####. Ok to occupy phase 3A, pre op and physicians lounge.
|
BLD-Ceiling Grid Inspection | 11/5/2014 | 11/5/2014 | 11/5/2014 | P | PASS |
Mike Jordan
|
|
|
Garrett Phone #: ###-####
|
FIRE-Final Inspection | 10/29/2014 | 10/30/2014 | 10/30/2014 | A | PART |
Troy Cobbley
|
|
|
Pre-op and Doctors Lounge life safety is complete
|
BLD-Framing/Rough-in | 10/22/2014 | 10/22/2014 | 10/22/2014 | P | PASS |
Mike Jordan
|
|
|
charles Phone #: ###-####. Interior steel stud framed wall at decon 160.
|
BLD-Ceiling Grid Inspection | 10/15/2014 | 10/16/2014 | 10/16/2014 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Pre op D101, rms B161 , B162 Dictation C163 and breakdown B111 ok.
|
BLD-Final | 9/29/2014 | 9/30/2014 | 9/30/2014 | A | PART |
Mike Jordan
|
|
|
Garrett Phone #: ###-####. ok to occupy sterile storage, and phase 2 of lobby remodel. Also verified that exit sign has been repaired.
|
FIRE-Final Inspection | 9/29/2014 | 9/30/2014 | 9/30/2014 | A | PART |
Troy Cobbley
|
|
|
Life safety passed in Sterile Storage
|
BLD-Ceiling Grid Inspection | 9/25/2014 | 9/26/2014 | 9/26/2014 | P | PASS |
Phil Shearer
|
|
|
garrett Phone #: ###-####
|
FIRE-Final Inspection | 9/16/2014 | 9/17/2014 | 9/17/2014 | P | PART |
Troy Cobbley
|
|
|
Remodeled portion of Main Lobby and connecting corridor life safety passed. Electritian is to repair an existing exit sign in the path of egress.
|
BLD-Framing/Rough-in | 9/17/2014 | 9/17/2014 | 9/17/2014 | P | CANC |
Mike Jordan
|
|
|
Charles Phone #: ###-####
|
BLD-Framing/Rough-in | 9/15/2014 | 9/16/2014 | 9/16/2014 | P | PASS |
Mike Jordan
|
|
|
Garrett Phone #: ###-####. Interior steel stud framed walls pre-op, D101, dictation C163, Annes work B161 and physicians lounge B162.
|
BLD-Ceiling Grid Inspection | 9/3/2014 | 9/4/2014 | 9/4/2014 | P | PASS |
Mike Jordan
|
|
|
Derek Phone #: ###-####. grid ok as well as all firestopping rooms C117, C116, C110 and portion of corridor C111.
|
BLD-Final | 8/27/2014 | 8/28/2014 | 8/28/2014 | A | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Male and female locker rooms ok to occupy.
|
BLD-Final | 8/19/2014 | 8/20/2014 | 8/20/2014 | A | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Ok to occupy pacu, purchasing office B167 and General Storage B165. Male and female lockers not ready at this time.
|
FIRE-Final Inspection | 8/18/2014 | 8/19/2014 | 8/19/2014 | A | PART |
Troy Cobbley
|
|
|
Life safety is complete in the Locker Rooms/Storage/PACU areas.
|
FIRE-Final Inspection | 8/15/2014 | 8/18/2014 | 8/18/2014 | A | FAIL |
Troy Cobbley
|
|
|
Life safety for new phase will be ok to final went the project related fire alarm work for this area is complete.
|
BLD-Ceiling Grid Inspection | 8/14/2014 | 8/14/2014 | 8/14/2014 | P | PASS |
Mike Jordan
|
|
|
charles Phone #: ###-####. Male and female lockers C101 and C103.
|
BLD-Ceiling Grid Inspection | 8/11/2014 | 8/12/2014 | 8/12/2014 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. General storage B165 and purchsing office 167 ok. All firecaulking completed and inspected.
|
BLD-Framing/Rough-in | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Interior steel stud framed walls at phase 2 of lobby remodel, work room C110 and reception C117.
|
BLD-Ceiling Grid Inspection | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. ceiling grid ok in general storage room B165. Didnote some penetrations not yet fire caulked. Will reinspect on monday.
|
BLD-Ceiling Grid Inspection | 7/28/2014 | 7/29/2014 | 7/29/2014 | A | PART |
Jim Sly
|
|
|
Garrett Phone #: ###-#### PAC U.......OK
|
BLD-Framing/Rough-in | 7/15/2014 | 7/16/2014 | 7/16/2014 | P | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Interior steel stud framed walls at phase 2C male/female lockers and showers as well as general storage, IT and purchasing offices. Room #C100, 101, 102,103, B165, 166 and 167. Pending plumbing rough in.
|
BLD-Conference | 7/15/2014 | 7/15/2014 | 7/15/2014 | A | DONE |
Mike Jordan
|
|
|
jobsite visit to check on progress. Contractor noted that they would be calling in for a framing inspection tomorrow in the pm.
|
FIRE-Final Inspection | 6/25/2014 | 6/26/2014 | 6/26/2014 | A | PART |
Troy Cobbley
|
|
|
Requested paperwork signed for Charles Phone #: ###-####
|
BLD-Final | 6/25/2014 | 6/26/2014 | 6/26/2014 | A | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Phase 2b, north portion of lobby remodel , equipment storage rm. #103 and lab a102 ok to occupy.
|
FIRE-Final Inspection | 6/23/2014 | 6/24/2014 | 6/24/2014 | P | PART |
Troy Cobbley
|
|
|
life safety is complete in the Lab, Equipment Room and north half of the remodeled Lobby.
|
BLD-Ceiling Grid Inspection | 6/23/2014 | 6/23/2014 | 6/23/2014 | P | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. lobby remodel.
|
BLD-Framing/Rough-in | 6/17/2014 | 6/17/2014 | 6/17/2014 | P | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Interior steel stud walls phase 2 part B eqiupment storage B144 restrooms D104, D105 and North wall at room 107.
|
BLD-Ceiling Grid Inspection | 6/12/2014 | 6/12/2014 | 6/12/2014 | P | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Phase 2 equipment storage and lab rooms ok.
|
BLD-Framing/Rough-in | 5/19/2014 | 5/21/2014 | 5/21/2014 | A | PASS |
Mike Jordan
|
|
|
CHARLES Phone #: ###-####. phase 2, framing for lobby remodel ok.
|
BLD-Conference | 5/19/2014 | 5/19/2014 | 5/19/2014 | A | DONE |
Mike Jordan
|
|
|
Framing in lobby remodel phase 2. Should be ready for formal framing inspection on wednesday.
|
BLD-Conference | 5/14/2014 | 5/14/2014 | 5/14/2014 | P | DONE |
Mike Jordan
|
|
|
Work in progress on waiting area remodfel, phase 2.
|
BLD-Framing/Rough-in | 5/8/2014 | 5/9/2014 | 5/9/2014 | P | PASS |
Mike Jordan
|
|
|
charles Phone #: ###-####. Phase 2 interior steel stud walls and shaft walls for storage and lab rooms ok to cover.
|
BLD-Conference | 5/7/2014 | 5/7/2014 | 5/7/2014 | A | DONE |
Mike Jordan
|
|
|
Job site check in. Interior steel stud framing in progress. In phase 2. Per contractor should be ready for framing inspection on monday may 12th.
|
BLD-Conference | 4/30/2014 | 4/30/2014 | 4/30/2014 | P | DONE |
Mike Jordan
|
|
|
Walk through on work in progress for phase 2.
|
BLD-Final | 4/22/2014 | 4/22/2014 | 4/22/2014 | P | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. phase 1c medical records ok to occupy.
|
BLD-Final | 4/22/2014 | 4/22/2014 | 4/22/2014 | A | PART |
Mike Jordan
|
|
|
Phase 1A, O.R. and recovery rooms only ok to occupy.
|
FIRE-Final Inspection | 4/17/2014 | 4/21/2014 | 4/21/2014 | A | PART |
Troy Cobbley
|
|
|
Remodeled area 1C, life safety is passed
|
BLD-Final | 4/17/2014 | 4/18/2014 | 4/18/2014 | A | PART |
Mike Jordan
|
|
|
O.R. addition ready for final. The O.R. addition only is ok to occupy.
|
BLD-Final | 4/17/2014 | 4/17/2014 | 4/17/2014 | P | CANC |
Mike Jordan
|
|
|
moved to am. Life safety for the or addition has passed, but was entered in error under bld14-00903. I have contacted troy c. and left a message for him.
|
FIRE-Final Inspection | 4/16/2014 | 4/17/2014 | 4/17/2014 | A | PART |
Troy Cobbley
|
|
|
Life safety passed in the new OR area. See the city approved plans for marked location
|
BLD-Final | 4/17/2014 | 4/17/2014 | 4/17/2014 | P | NR |
Mike Jordan
|
|
|
Mark-patio cover in back Phone #: ###-####. This in regards to the patio cover that has been added to scope of work. Patio cover is complete, but the sprinkler system has not yey been extended in to the covered patio area.
|
BLD-Final | 4/16/2014 | 4/17/2014 | 4/17/2014 | A | CANC |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Moved to pm pending fire alarm.
|
BLD-Conference | 4/16/2014 | 4/16/2014 | 4/16/2014 | P | DONE |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 4/15/2014 | 4/16/2014 | 4/16/2014 | P | FAIL |
Troy Cobbley
|
|
|
Life safety for the new OR area will be ok to pass when the project related fire alarm system for this area has been inspected and passed as well.
|
BLD-Final | 4/15/2014 | 4/15/2014 | 4/15/2014 | P | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Phase 1a patient addition only ok to occupy.
|
BLD-Footing | 4/14/2014 | 4/15/2014 | 4/15/2014 | A | PASS |
Mike Jordan
|
|
|
SHawn Phone #: ###-####. footings for new patio cocer.
|
BLD-Conference | 4/8/2014 | 4/9/2014 | 4/9/2014 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Ceiling Grid Inspection | 4/8/2014 | 4/9/2014 | 4/9/2014 | A | PASS |
Mike Jordan
|
|
|
grid in cafeteria ok.
|
BLD-Ceiling Grid Inspection | 4/4/2014 | 4/7/2014 | 4/7/2014 | A | PASS |
Tom Arcoraci
|
|
|
Charles Phone #: ###-####
|
BLD-Conference | 4/2/2014 | 4/2/2014 | 4/2/2014 | P | DONE |
Mike Jordan
|
|
|
Walk through at OR addition. Inspected in progress work of ceiling grid install and firecaulking.
|
BLD-Conference | 4/2/2014 | 4/2/2014 | 4/2/2014 | A | CANC |
Mike Jordan
|
|
|
Moved to pm.
|
BLD-Ceiling Grid Inspection | 3/31/2014 | 4/1/2014 | 4/1/2014 | A | PASS |
Mike Jordan
|
|
|
charles Phone #: ###-####. Areas A and B ok to cover.
|
FIRE-Final Inspection | 3/28/2014 | 3/31/2014 | 3/31/2014 | A | PART |
Troy Cobbley
|
|
|
New Patient Wing Life safety complete.
|
BLD-Framing/Rough-in | 3/31/2014 | 3/31/2014 | 3/31/2014 | A | PART |
Mike Jordan
|
|
|
Soffit in cafeteria. Steel stud framing for soffit in cafeteria ok. Partial walk through on ceiling grid and fire caulking at Areas A and B. Aslo inspected doors and door frames in 1 hr. corridor at patient addition.
|
BLD-Framing/Rough-in | 3/26/2014 | 3/27/2014 | 3/27/2014 | A | FAIL |
Tom Arcoraci
|
|
|
Charles Miller ###-#### unable to locate superintendent on site no ans on phone
|
BLD-Ceiling Grid Inspection | 3/24/2014 | 3/25/2014 | 3/25/2014 | A | PASS |
Mike Jordan
|
|
|
garret Phone #: ###-####. Framing for hardlid in OR# 6 ok to cover.
|
BLD-Ceiling Grid Inspection | 3/20/2014 | 3/21/2014 | 3/21/2014 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Ceiling grid ok to cover.
|
BLD-Framing/Rough-in | 3/19/2014 | 3/20/2014 | 3/20/2014 | A | PART |
Mike Jordan
|
|
|
CHARLES Phone #: ###-####. hardlid for OR# 5 ok to sheet rock. Ceiling grid in patient addition ok. Noted some penetrations not yet firecaulked. Will reinspect tomorrow.
|
BLD-Conference | 3/18/2014 | 3/19/2014 | 3/19/2014 | A | DONE |
Mike Jordan
|
|
|
Walked job and discussed the addition of a possible patio cover.
|
BLD-Framing/Rough-in | 3/17/2014 | 3/18/2014 | 3/18/2014 | A | PASS |
Mike Jordan
|
|
|
Charles Miller Phone #: ###-####. Interior steel stud framed 1hr. Fire barrier wall at gridline 11 between grids C to D.8, seperation between Suite C and Suite B.
|
BLD-Framing/Rough-in | 3/14/2014 | 3/17/2014 | 3/17/2014 | A | PASS |
Mike Jordan
|
|
|
charles Phone #: ###-####. Hrdlids ok to cover in OR#4. Soffits for nurses station D116 and D110.
|
BLD-Framing/Rough-in | 3/13/2014 | 3/13/2014 | 3/13/2014 | P | PART |
Mike Jordan
|
|
|
charles Phone #: ###-####. Hardlid for OR#4. Pending electrical rough in.
|
BLD-Conference | 3/11/2014 | 3/12/2014 | 3/12/2014 | A | DONE |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 3/12/2014 | 3/12/2014 | 3/12/2014 | A | PASS |
Mike Jordan
|
|
|
Interior steel studs for fire barrier walls in exisiting building at for medical records room C109, corridor C105, and offices C106,C107 and C110.
|
BLD-Framing/Rough-in | 3/7/2014 | 3/7/2014 | 3/7/2014 | P | PASS |
Mike Jordan
|
|
|
Garrett Phone #: ###-####. Interior steel stud firebarrier wall at gridline 8 between grids B to D.(compartment wall for suite C)
|
BLD-Conference | 3/4/2014 | 3/5/2014 | 3/5/2014 | A | DONE |
Mike Jordan
|
|
|
Walk through with tim Woodard, plan reviewer for project.
|
BLD-Conference | 3/4/2014 | 3/4/2014 | 3/4/2014 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 3/4/2014 | 3/4/2014 | 3/4/2014 | P | PASS |
Mike Jordan
|
|
|
Interior steel stud walls for soiled laundry and wash room at siute B.
|
BLD-Conference | 2/26/2014 | 2/26/2014 | 2/26/2014 | P | PASS |
Mike Jordan
|
|
|
Walk through on patient addition to inspect partial ceiling grid and firestopping. Aslo wlak through on work in progress in area B.
|
BLD-Conference | 2/18/2014 | 2/19/2014 | 2/19/2014 | P | PASS |
Mike Jordan
|
|
|
Patient addition walk through, inspected membrane and through penetration firecaulikng.
|
BLD-Energy code compliance | 2/19/2014 | 2/19/2014 | 2/19/2014 | P | PASS |
Mike Jordan
|
|
|
Exterior walls at OR addtion.
|
BLD-Conference | 2/18/2014 | 2/19/2014 | 2/19/2014 | A | CANC |
Mike Jordan
|
|
|
Moved to PM.
|
BLD-Framing/Rough-in | 2/18/2014 | 2/18/2014 | 2/18/2014 | P | PASS |
Mike Jordan
|
|
|
Charles Miller Phone #: ###-####. Interior steel stud framed walls for the remainder of suite B. (area C).
|
BLD-Conference | 2/18/2014 | 2/18/2014 | 2/18/2014 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 2/12/2014 | 2/13/2014 | 2/13/2014 | P | DONE |
Mike Jordan
|
|
|
Went over UL assemblies with general contractor and firestop contractor and resolved issues regarding membrane protection for med gas and through penetrations for insulated steel pipe.
|
BLD-Conference | 2/11/2014 | 2/12/2014 | 2/12/2014 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 2/11/2014 | 2/12/2014 | 2/12/2014 | A | PART |
Mike Jordan
|
|
|
Reviewed fire stopping submittals. PArtial walk through at patient addition to inspect firestopping. Will need to provide details for opening protection for med and oxygen gas in firebarrier wall at gridline 8. Aslo need to discuss UL for cleanouts.
|
BLD-Framing/Rough-in | 2/12/2014 | 2/12/2014 | 2/12/2014 | P | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Interior walls at suite C ok. Compartment wall (fire Barrier) om gridline C ok to rock from 11ft. elevation to top of deck. Interior walls on siute B at gridlines 9.7 to 13 from AA to C. Also verified putty pads on fire barrier wall on gridline 8.
|
BLD-Framing/Rough-in | 2/7/2014 | 2/10/2014 | 2/10/2014 | P | PASS |
Mike Jordan
|
|
|
charles Miller Phone #: ###-####. interior steel stud walls in suite C at gridlines 8 to 9.7 and AA to c.
|
BLD-Conference | 2/3/2014 | 2/5/2014 | 2/5/2014 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 2/5/2014 | 2/5/2014 | 2/5/2014 | P | DONE |
Mike Jordan
|
|
|
Discussed UL approved details for firestopping and area suites.
|
BLD-Final | 1/31/2014 | 2/3/2014 | 2/4/2014 | P | PART |
Mike Jordan
|
|
|
garrett or ###-#### Phone #: ###-####. Partial final only for the phase 1 partB admin. offices only ok to occupy. All other trades and life safety have signed off in this area.
|
BLD-Conference | 2/3/2014 | 2/5/2014 | 2/3/2014 | P | CANC |
Mike Jordan
|
|
|
garrett or ###-#### Phone #: ###-####
|
BLD-Framing/Rough-in | 2/3/2014 | 2/3/2014 | 2/3/2014 | P | PART |
Mike Jordan
|
|
|
garrett or ###-#### Phone #: ###-####. Interior steel stud walls at sterile passage corridorB138, ok to rock from 11ft. elevation to top of wall. West exterior wall from grid line AA betweeen greids 8.7 to 13 ok to cover, ok to cover electrical room B123.
|
FIRE-Final Inspection | 1/31/2014 | 2/3/2014 | 2/3/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety for Phase 1B is passed. See the life safey plan sheet for area high lighted and signed.
|
BLD-Final | 1/31/2014 | 1/31/2014 | 1/31/2014 | P | NR |
Mike Jordan
|
|
|
charles Phone #: ###-####. Needs fire/life/safety.
|
BLD-Conference | 1/29/2014 | 1/29/2014 | 1/29/2014 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 1/29/2014 | 1/29/2014 | 1/29/2014 | A | PART |
Mike Jordan
|
|
|
Work in progress on Phase 1 part A, inspected door frames in corridor. Partial framing in phase 1 part B, noted that electrical Isolation boxes inproperly wrapped at rated corridor. Also reviewed special inspection reports to date. Pre walk through on Admin area remodel prior to temp. final on friday.
|
BLD-Ceiling Grid Inspection | 1/6/2014 | 1/6/2014 | 1/6/2014 | P | PASS |
Mike Jordan
|
|
|
charles Phone #: ###-####. Ceiling grid inspection for phase 1B remodel ok.
|
BLD-Framing/Rough-in | 12/18/2013 | 12/19/2013 | 12/19/2013 | A | PART |
Mike Jordan
|
|
|
CHARLES Phone #: ###-####. Top of wall for firewalls @ corridor on grids H and H.3 from 1 to 3.9 for phase 1 patient addition, pending electrical inspection. Steel stud framing for exterior walls at phase 1 part B. Also noted steel track at phase 1 patient addition has been shot down per the approved engineering.
|
BLD-Framing/Rough-in | 11/26/2013 | 11/26/2013 | 11/26/2013 | P | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Exterior steel stud framed walls for phase 1 partA patient addition at gridlines 1 to 4 and on gridlines G to J. All work per the contractors egineering. Will get copy to have scanned into case. Noted that contractor is lacking shot spacing on the bottom track connection to concrete. Will reinspect on next inspection. ok to cover exterior only.
|
BLD-Framing/Rough-in | 11/1/2013 | 11/4/2013 | 11/4/2013 | A | PASS |
Mike Jordan
|
|
|
Interior steel stud walls at phase 1, part B. Gridlines 4 to 5.7 and grid lines C to E (Admin offices) ok to cover.
|
BLD-Other | 10/24/2013 | 10/25/2013 | 10/25/2013 | P | PASS |
Mike Jordan
|
|
|
Rebar - Charles Phone #: ###-####. Footings and interior column pad footings at part B.
|
BLD-Framing/Rough-in | 11/1/2013 | 11/1/2013 | | P | |
Mike Jordan
|
|
|
Charles Phone #: ###-####
|