Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD13-01783
StatusFinaled
Name ESI
Site Address 800 W MAIN ST Unit: 1600
Project Name8TH & MAIN STE 1600
Customer NumberREF BLD13-01691
ePlanReviewNo
Description
(HOLLAND & HART – 8th & Main Building – Suite # 1600) This building is sprinklered to comply as a high-rise building. Permit is to build out for the first time the entire 16,828 square foot 16th floor (Shell and Core done under BLD12-01991) as offices. Work is to include: [construction of interior none bearing walls to create; 36 offices, 8 open office areas, 7 small storage areas, a conference room (under 400 sq. ft), a coffee / break room, a large research area, and three copy/print areas], installation of a new lighting, installation of new plumbing, installation of new mechanical, and new interior finishes. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. NOTE: Reference ePlanReview case BLD13-01691 for review. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection2/10/20142/11/20142/11/2014APASS
DetailsForrest France
Fire life safety inspection passed after corrections and adjustments made while on site.
BLD-Final2/10/20142/11/20142/11/2014APASS
DetailsDave Hannah
Final inspection request of H&H 16th Floor. Adam will walk with you for this inspection. Thanks. AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Conference2/4/20142/5/20142/5/2014APEND
DetailsDave Hannah
Meet and walk H&H floors for egress signage compliance. Contact Adam or Murph. Thanks. AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Ceiling Grid Inspection1/17/20141/21/20141/21/2014PPART
DetailsJim Sly
Ceiling inspection, 16th floor Holland and Hart. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
Install Perimeter only.....OK.
BLD-Ceiling Grid Inspection1/7/20141/8/20141/9/2014PPART
DetailsDave Hannah
Ceiling grid inspection requested by Murph, PM, 16th Floor H&H. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to place bourder tiles in
BLD-Ceiling Grid Inspection12/27/201312/30/201312/31/2013PPART
DetailsDave Hannah
Ceiling inspection, 16th Floor Holland and Hart, requested for PM Monday, by Murph. Thanks, AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson hard lids both sides of elevator lobby ok to cover
BLD-Framing/Rough-in10/31/201310/31/201311/1/2013PPASS
DetailsDave Hannah
Framing inspection request from John Woods. Thanks. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in10/30/201310/30/201310/31/2013PPART
DetailsDave Hannah
Requested inspection of 16th Floor East, coordinate specific needs with Murph, ESI, ###-####. Thank you. Adam ###-#### Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover all but break room wall
BLD-Framing/Rough-in10/24/201310/24/201310/24/2013APART
DetailsDave Hannah
Inspection scheduled via John Woods. Adam is off site this morning, contact John for inspection needs. Thanks. Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover rooms 1627-34 1601-10 1652-56
BLD-Framing/Rough-in10/1/201310/1/201310/3/2013PPART
DetailsDave Hannah
H&H 16th Floor Framing. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover rooms 1###-#### and rooms 1###-####