BLD-Final | 11/27/2013 | 11/27/2013 | 11/27/2013 | P | PASS |
Mike Jordan
|
|
|
final called in with fire Phone #: ###-#### >> Inspection requested via web by nate hutton
|
DOC - Permit Finaled | 11/27/2013 | 11/27/2013 | 11/27/2013 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 11/25/2013 | 11/26/2013 | 11/27/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed per Craig
|
FIRE-Final Inspection | 11/27/2013 | 11/27/2013 | 11/27/2013 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety passed
|
BLD-Final | 11/25/2013 | 11/26/2013 | 11/26/2013 | P | NR |
Mike Jordan
|
|
|
please call Deven at ###-####- Fire final also called in for PM inspection on Tuesday. Thank you Mike- Nate-ESI Phone #: ###-#### >> Inspection requested via web by nate hutton. Needs fire/life/safety inspection. not yet completed as of 4:00pm.
|
BLD-Final | 11/21/2013 | 11/22/2013 | 11/22/2013 | P | NR |
Mike Jordan
|
|
|
Please call Matt about 30 minutes before you get to the mall. Thanks Phone #: ###-#### >> Inspection requested via web by Matt Perry. Needs fire/life/safety.
|
BLD-Framing/Rough-in | 11/7/2013 | 11/8/2013 | 11/8/2013 | P | PASS |
Mike Jordan
|
|
|
Framing for 1hr. exit corridor.
|
BLD-Framing/Rough-in | 11/6/2013 | 11/7/2013 | 11/7/2013 | P | PASS |
Mike Jordan
|
|
|
Please call about 30 minutes prior and I will meet you there. Thanks Phone #: ###-#### >> Inspection requested via web by Matt Perry
|
BLD-Conference | 11/4/2013 | 11/5/2013 | 11/5/2013 | A | PART |
Mike Jordan
|
|
|
Please call. Changed number to Matt Perry for contact. Just let me know about 30 minutes prior. Thanks Phone #: ###-#### >> Inspection requested via web by Matt Perry. Needs to provide the approved set of plans. ok to start sheet rock on storage demissing wall and up top at discussed areas. will reschedule inspection for tomorrow and provide the approved plans.
|
BLD-Framing/Rough-in | 11/4/2013 | 11/4/2013 | 11/4/2013 | P | FAIL |
Mike Jordan
|
|
|
Please call Mike Oborn prior to arrival. He is the contractor for all the framing. Thanks Phone #: ###-#### >> Inspection requested via web by Matt Perry. No approved plans on site. Called Mike twice prior to arrival, no answer and could not leave message, voice mailbox full. Will need to reschedule.
|
FIRE-Final Inspection | 10/17/2013 | 10/21/2013 | 10/21/2013 | A | FAIL |
Troy Cobbley
|
|
|
Project not ready for a final inspection. Matt just wanted a conference on the "art of shaving" tenant space.
|