BLD-Final | 10/1/2013 | 10/2/2013 | 10/2/2013 | A | PASS |
Tony Young
|
|
|
All roofs are complete. There are 24 total roofs replaced. All roofs with comp shingles. Thank you Phone #: ###-#### >> Inspection requested via web by Michael La Pointe
|
DOC - Permit Finaled | 10/2/2013 | 10/2/2013 | 10/2/2013 | P | PASS |
Tony Young
|
|
|
all appear to be done
|
BLD-Conference | 10/1/2013 | 10/1/2013 | 10/1/2013 | P | PASS |
Tony Young
|
|
|
All roofs are complete. There are 24 total roofs replaced. All roofs with comp shingles. Thank you Phone #: ###-#### >> Inspection requested via web by Michael La Pointe,, looks complete
|
BLD-Conference | 8/26/2013 | 8/26/2013 | 8/26/2013 | P | CANC |
Jim Sly
|
|
|
2 of the buildings will be ready for inspection today. please call me and let me know if you would like to file an inspection report each day. we will be working on this project for the next 4 weeks. Thank you. Phone #: ###-#### >> Inspection requested via web by Michael La Pointe
WIP
|