BLD-Final | 1/16/2014 | 1/17/2014 | 1/17/2014 | P | PASS |
Jim Sly
|
|
|
Clarence Phone #: ###-####
|
DOC - Permit Finaled | 1/17/2014 | 1/17/2014 | 1/17/2014 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 1/10/2014 | 1/13/2014 | 1/13/2014 | A | NR |
Mike Jordan
|
|
|
Clarence Phone #: ###-####. Need plumbing final, raise handrail on basement stairs to meet the 34 to 38 inch requirement.
|
BLD-Energy code compliance | 11/5/2013 | 11/7/2013 | 11/7/2013 | A | PASS |
Mike Jordan
|
|
|
Clarence Phone #: ###-####
|
BLD-Other | 11/4/2013 | 11/4/2013 | 11/4/2013 | P | PASS |
Mike Jordan
|
|
|
clarence Phone #: ###-####. OK to insulate.
|
BLD-Framing/Rough-in | 10/25/2013 | 10/30/2013 | 10/30/2013 | P | PART |
Mike Jordan
|
|
|
Clarence Phone #: ###-####. Complete airseal. Go back to plan review ti have scope of work updated. This is a whole house remodel, all sheet rock and insulation has been removed from house except for master bedroom.
|