BLD-Final | 10/20/2015 | 10/20/2015 | 10/20/2015 | A | PASS |
Jim Storey
|
|
|
perm occ ok
|
BLD-Final | 8/26/2015 | 8/27/2015 | 8/27/2015 | A | PASS |
Jim Storey
|
|
|
Level 5 inspection for Temp C of O, all other inspections are complete. Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Final | 8/24/2015 | 8/25/2015 | 8/25/2015 | P | NR |
Jim Storey
|
|
|
Level 5 final for C of O Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Final | 8/18/2015 | 8/19/2015 | 8/19/2015 | A | PASS |
Jim Storey
|
|
|
Final walk on rooms 360, 460,, 356, 456, 350, 450 at 10 am Phone #: ###-#### Inspection requested via web by Mike Wilson pending 5th floor as directed.
|
BLD-Final | 8/17/2015 | 8/18/2015 | 8/18/2015 | P | NR |
Jim Storey
|
|
|
finish the building walk on items to complete for Temp sign off 1 pm Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Ceiling Grid Inspection | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PASS |
Jim Storey
|
|
|
Fire caulking inspection on level 2 South elevator lobby, level 3 Center lobby and level 4 Center lobby Phone #: ###-#### Inspection requested via web by Mike Wilson
|
FIRE-Final Inspection | 8/4/2015 | 8/4/2015 | 8/4/2015 | P | PASS |
Thomas Walsh
|
|
|
Fire life safety inspection of new apartment building, including test of exit signs and emergency lighting units throughout the building. Several EM lights need to be repaired/replaced. Also need additionl exit signs in south corridor (all floors) to clearly indicate the direction of egress to the southeast exit stair. EVAC plans need to be installed. Fire Exting. OK ****AS PER sja FINAL PASSED****
|
BLD-Wall cover | 7/31/2015 | 7/31/2015 | 7/31/2015 | P | PART |
Jim Sly
|
|
|
level 5 fire caulking in the drop ceiling area around sprinkler pipe Phone #: ###-#### Inspection requested via web by Mike Wilson OK
|
BLD-Ceiling Grid Inspection | 7/28/2015 | 7/29/2015 | 7/29/2015 | A | PASS |
Jim Storey
|
|
|
Level 2 and 3 hallway inspection for cover Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Ceiling Grid Inspection | 7/27/2015 | 7/28/2015 | 7/28/2015 | P | PART |
Jim Storey
|
|
|
Level 2 and 3 hallway inspection for cover Phone #: ###-#### Inspection requested via web by Mike Wilson firestopping required
|
FIRE-Conference | 7/15/2015 | 7/15/2015 | 7/15/2015 | P | DONE |
Thomas Walsh
|
|
|
Meeting to discuss corridor ceiling heights in several areas, including the provisions needed for exposing CPVC sprinkler pipe and the location of exit signage below drop ceilings in these corridors, including code requirements for min. ceiling heights below the drop ceiling. Meeting notes suggested that the CVPC pipe will probably be made to be concealed, but that some steel dry pipe system piping may be exposed in some areas. Exit signs may have to be offset from plan locations, but this should acceptable if they meet the min. celing heights as per Bldg Code. and clearly show the direction of exit travel. If CVPC pipe has to run exposed, the sprinkler contractor (Shilo) was informed that this will take a plan modification submittal to the plan checker to ensure that this meets manufacturer's specifications.
|
BLD-Wall cover | 7/3/2015 | 7/6/2015 | 7/6/2015 | A | PART |
Jim Storey
|
|
|
Level 5 shafts fire caulking inspection for cover Phone #: ###-#### Inspection requested via web by Mike Wilson corridor ok / shafts ok per list.
|
BLD-Wall cover | 7/1/2015 | 7/1/2015 | 7/1/2015 | P | PART |
Jim Storey
|
|
|
10 shaft on level 5 for cover Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Wall cover | 6/25/2015 | 6/26/2015 | 6/26/2015 | P | NR |
Jim Storey
|
|
|
level 5 shafts for cover Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Energy code compliance | 6/10/2015 | 6/11/2015 | 6/12/2015 | P | PASS |
Dave Hannah
|
|
|
Level 5 East perimeter wall energy code Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Energy code compliance | 6/1/2015 | 6/3/2015 | 6/3/2015 | P | PASS |
Jim Storey
|
|
|
level 4 East Perimeter wall energy code Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Framing/Rough-in | 5/21/2015 | 5/22/2015 | 5/22/2015 | A | PASS |
Jim Storey
|
|
|
Level 4 East unit framing and stair well A for cover Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Energy code compliance | 5/12/2015 | 5/13/2015 | 5/13/2015 | P | PASS |
Jim Storey
|
|
|
Level 3 East exterior wall foam and insulation inspection for cover Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Wall cover | 5/11/2015 | 5/12/2015 | 5/12/2015 | A | PASS |
Jim Storey
|
|
|
The rest of units on level 2 east drop down ceiling fire caulking inspection for cover Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Wall cover | 5/5/2015 | 5/6/2015 | 5/6/2015 | P | PASS |
Jim Storey
|
|
|
Level 2 East drop ceiling framing in units for cover, level 3 East wood framing unit framing for cover Inspection requested via web by Mike Wilson drops ok pending fire as noted/ 303 and 304 beam support justafacation. all the rest of framing ok.
|
BLD-Framing/Rough-in | 4/28/2015 | 4/29/2015 | 4/29/2015 | P | PASS |
Jim Storey
|
|
|
Elevator #1 shaft framing for cover, South elevation shear nailing Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Energy code compliance | 4/22/2015 | 4/23/2015 | 4/23/2015 | A | PASS |
Jim Storey
|
|
|
level 2 shower pan grouting in PT deck, Exterior insulation in perimeter walls Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Energy code compliance | 4/20/2015 | 4/21/2015 | 4/21/2015 | A | PASS |
Jim Storey
|
|
|
Level 2 East exterior wall inspection for drywall Phone #: ###-#### Inspection requested via web by Mike Wilson up to 214 ok/ 4th floor coridor ok to pre gyp
|
BLD-Framing/Rough-in | 4/20/2015 | 4/21/2015 | 4/21/2015 | A | PART |
Jim Storey
|
|
|
Elevator shaft #2 framing inspection for drywall cover Phone #: ###-#### Inspection requested via web by Mike Wilson all but east/north corner gyp. missing
|
BLD-Framing/Rough-in | 4/14/2015 | 4/14/2015 | 4/14/2015 | P | PASS |
Jim Storey
|
|
|
roof deck nw andne ok 2nd floor rooms framing ok212 thur 221
|
BLD-Framing/Rough-in | 4/9/2015 | 4/10/2015 | 4/10/2015 | P | PASS |
Jim Storey
|
|
|
Level 2 East unit 207 to 212 ceilings for Drywall cover, Level 2 east exterior wall sealant, East exterior elevation sheathing nail inspection. Roof Truss engineering Phone #: ###-#### Inspection requested via web by Mike Wilson east truss ok/ east wall exterior ok/
|
BLD-Framing/Rough-in | 4/7/2015 | 4/8/2015 | 4/8/2015 | P | CANC |
Jim Storey
|
|
|
Next 6 unit ceiling framing for cover, Level 2 exterior wall envelope, East exterior Nailing inspection, Phone #: ###-#### >> Inspection requested via web by Mike Wilson Inspection cancelled from web by: Mike Wilson
|
BLD-Framing/Rough-in | 4/2/2015 | 4/3/2015 | 4/3/2015 | P | PASS |
Jim Storey
|
|
|
First 6 Units Ceiling inspections for Insulation inspection East Wing Phone #: ###-#### Inspection requested via web by Mike Wilson 2nd floor 202 thru 207 frame ok ok to insulate.
|
BLD-Framing/Rough-in | 3/30/2015 | 3/31/2015 | 3/31/2015 | P | PASS |
Jim Storey
|
|
|
More East side Roof nailing and Level 4 corridor framing inspection for cover Phone #: ###-#### Inspection requested via web by Mike Wilson
|
BLD-Framing/Rough-in | 3/19/2015 | 3/20/2015 | 3/20/2015 | P | PASS |
Jim Storey
|
|
|
Northeast exterior building nailing for building wrap install, East Roof nailing inspection for Roofing install Phone #: ###-#### Inspection requested via web by Mike Wilson k line wall and roof ok to cover
|
BLD-Wall cover | 2/25/2015 | 2/26/2015 | 2/26/2015 | A | PASS |
Jim Storey
|
|
|
Level 2 east hallway wall inspection and Exterior sheathing nailing inspection at the CMU wall only Phone #: ###-#### Inspection requested via web by Mike Wilson ok to pre rock corridor at ceilling and 24 inches down walls
|