BLD-Final | 10/8/2014 | 10/9/2014 | 10/9/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
DOC - Permit Finaled | 10/9/2014 | 10/9/2014 | 10/9/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 10/9/2014 | 10/9/2014 | 10/9/2014 | A | DONE |
Mike Jordan
|
|
|
6
|
BLD-Wall cover | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Wall cover | 6/2/2014 | 6/3/2014 | 6/3/2014 | P | FAIL |
Mike Jordan
|
|
|
Fire and sheetrock shear fastening Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Energy code compliance | 5/20/2014 | 5/22/2014 | 5/22/2014 | P | PASS |
Mike Jordan
|
|
|
BLD-COM/RES INSPECTOR
|
BLD-Framing/Rough-in | 5/22/2014 | 5/22/2014 | 5/22/2014 | P | PASS |
Mike Jordan
|
|
|
BLD-COM/RES INSPECTOR
|
BLD-Framing/Rough-in | 5/19/2014 | 5/20/2014 | 5/20/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark. Needs to provide bearing under 3ply LVL in garage. ok to insulate.
|
BLD-Wall Bracing | 4/4/2014 | 4/7/2014 | 4/7/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 3/25/2014 | 3/26/2014 | 3/26/2014 | A | PART |
Jim Sly
|
|
|
Upper floor shear nailing. Brian will not be present. Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Footing | 3/20/2014 | 3/21/2014 | 3/21/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin. interior thickend footings.
|
BLD-Energy code compliance | 2/13/2014 | 2/13/2014 | 2/13/2014 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Foundation | 2/6/2014 | 2/6/2014 | 2/6/2014 | P | PASS |
Mike Jordan
|
|
|
Heron Phone #: ###-####
|
BLD-Footing | 2/3/2014 | 2/3/2014 | 2/3/2014 | P | PASS |
Mike Jordan
|
|
|
Heron Phone #: ###-####
|