Information based on query as of Sunday, June 16, 2024.
Permit Information
Permit NumberBLD13-03461
StatusFinaled
Name MARATHON RESOURCES INC
Site Address 1109 W MYRTLE ST Unit: 100
Project NameLiberty Dialysis Boise
Customer Number 
ePlanReviewYes
Description
(LIBERTY DIALYSIS BOISE - Pioneer Plaza - 1st Floor) To remodel a 7,697 square foot portion of the 1st story of this existing 3 story building into an out-patient dialysis facility. Work to include: removal of selective existing interior walls and new construction of interior non-bearing walls to create: a main dialysis treatment room, exam room, home training rooms, offices, employee areas, and water treatment room; interior finishes in compliance with chapter 8 of the 2009 IBC; separate the water treatment, supply storage, and med waste rooms with a 1 hour fire barrier per incidental use separation requirements; install new lighting, emergency lighting and illuminated exit signs; plumbing, mechanical, and electrical systems. All work shall comply with the approved drawings, the plan review report, and all applicable codes. A new Certificate of Occupancy with the new occupant load total is required to be obtained after all work has been inspected and approved and prior to tenant occupying this space. NOTE: This building is fully sprinkled for substitution of 1- hour fire-resistive construction. This building also has an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/2/20146/2/20146/3/2014PPASS
DetailsDave Hannah
John Phone #: ###-####
FIRE-Final Inspection6/2/20146/2/20146/2/2014APASS
DetailsForrest France
Fire life safety inspection passed. One missing exit sign installed while on site.
BLD-Final5/29/20145/30/20146/2/2014PNR
DetailsDave Hannah
John Phone #: ###-####
BLD-Ceiling Grid Inspection5/12/20145/13/20145/13/2014APASS
DetailsDave Hannah
john Phone #: ###-####
BLD-Ceiling Grid Inspection4/30/20145/1/20145/1/2014PPART
DetailsMike Jordan
John Phone #: ###-####. Ceiling grid in all areas except dialysis room. Pending trade rough in inspections.
BLD-Other4/4/20144/7/20144/7/2014APART
DetailsDave Hannah
Concrete - John Phone #: ###-####
BLD-Framing/Rough-in3/27/20143/28/20143/29/2014PPASS
DetailsDave Hannah
John Phone #: ###-####
BLD-Framing/Rough-in3/26/20143/26/20143/27/2014PPART
DetailsDave Hannah
john Phone #: ###-#### ok to cover east half
BLD-Energy code compliance3/24/20143/25/20143/25/2014APASS
DetailsDave Hannah
John Phone #: ###-####
BLD-Energy code compliance3/20/20143/21/20143/24/2014PFAIL
DetailsDave Hannah
john Phone #: ###-#### insulation needs to be fixed so it dont fall back int the windows
BLD-Framing/Rough-in3/18/20143/19/20143/20/2014APART
DetailsDave Hannah
John Phone #: ###-#### ok to cover wall below windows and one side walls on south east corner
BLD-Footing3/5/20143/6/20143/6/2014PPASS
DetailsDave Hannah
John Phone #: ###-####