Permit Information
Permit NumberBLD13-03551
StatusFinaled
Name PARADIGM CONSTRUCTION COMPANY LLC
Site Address 8637 W PINE VALLEY LN
Project Name 
Customer Number 
ePlanReviewNo
Description
Permit for the construction of a new 1340 sq. ft., 3 story (first story 228 sq. ft, second story 552 sq. ft., third story 560 sq. ft.) Townhouse with 3 bedrooms, 2.5 bathrooms, approximately 90 sq. ft. of covered patio/porch and a 379 sq. ft. attached garage per the approved plans, Rescheck, plan review report and any notations. Approval based on previous approval of this design. R-2D zoning and setbacks per planning. ajs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/23/20152/23/20152/23/2015PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Brian Stark
DOC - Permit Finaled2/23/20152/23/20152/23/2015PPASS
DetailsMike Jordan
BLD-Blower Door Test Results2/23/20152/23/20152/23/2015PDONE
DetailsMike Jordan
5.6
BLD-Final2/18/20152/19/20152/18/2015ACANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Brian Stark Inspection cancelled from web by: Brian Stark
BLD-Energy code compliance10/7/201410/8/201410/8/2014APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Brian Stark
BLD-Framing/Rough-in10/3/201410/3/201410/3/2014PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Brian Stark
BLD-Wall Bracing8/25/20148/26/20148/26/2014APASS
DetailsMike Jordan
2nd floor shear Phone #: ###-#### Inspection requested via web by Brian Stark
BLD-Wall cover8/25/20148/25/20148/25/2014PPASS
DetailsMike Jordan
Firewall Phone #: ###-#### Inspection requested via web by Brian Stark. 2nd. floor 2hr. wall ok.
BLD-Wall cover8/8/20148/8/20148/8/2014PPASS
DetailsMike Jordan
firewall Phone #: ###-#### Inspection requested via web by Brian Stark
BLD-Wall cover8/5/20148/6/20148/6/2014APASS
DetailsMike Jordan
Firewall Phone #: ###-#### Inspection requested via web by Brian Stark. 1st. floor ok.
BLD-Footing6/13/20146/13/20146/13/2014APASS
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by James Larkin. Interior thickend footing.
BLD-Energy code compliance5/19/20145/19/20145/19/2014PDONE
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by James Larkin
BLD-Energy code compliance5/15/20145/16/20145/16/2014PPASS
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by James Larkin. rigid insulation at stemwall under slab on grade.
BLD-Foundation5/13/20145/15/20145/15/2014PPART
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by James Larkin
BLD-Footing5/13/20145/14/20145/14/2014PPASS
DetailsMike Jordan
Hopefully they are ready Phone #: ###-#### >> Inspection requested via web by James Larkin
BLD-Foundation5/13/20145/14/20145/14/2014PCANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by James Larkin
BLD-Foundation5/13/20145/14/20145/14/2014PCANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by James Larkin
BLD-Footing5/13/20145/13/20145/13/2014PNR
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by James Larkin