BLD-Aging Inspection | 3/16/2016 | 3/16/2016 | 3/16/2016 | | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 3/16/2016 | 3/16/2016 | 3/16/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 1/4/2016 | 1/4/2016 | 1/4/2016 | | PASS |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 10/15/2015 | 10/15/2015 | 10/15/2015 | | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 8/3/2015 | 8/3/2015 | 8/3/2015 | P | PART |
Phil Shearer
|
|
|
OK for temp occupancy.
|
FIRE-Final Inspection | 7/23/2015 | 7/24/2015 | 7/24/2015 | A | PASS |
Troy Cobbley
|
|
|
Life Safety Passed
|
BLD-Energy code compliance | 5/21/2015 | 5/22/2015 | 5/22/2015 | A | PASS |
Jim Sly
|
|
|
energy inspection Phone #: ###-#### Inspection requested via web by Mel Rawlinson
|
BLD-Framing/Rough-in | 5/19/2015 | 5/20/2015 | 5/20/2015 | A | PASS |
Mike Jordan
|
|
|
rough frame inspection Phone #: ###-#### Inspection requested via web by Mel Rawlinson
|
BLD-Wall Bracing | 4/22/2015 | 4/22/2015 | 4/22/2015 | P | PASS |
Mike Jordan
|
|
|
exterior shear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
|
BLD-Wall Bracing | 3/30/2015 | 3/30/2015 | 3/30/2015 | P | PASS |
Mike Jordan
|
|
|
Tyler// 1st floor interior sheer Phone #: ###-####
|
BLD-Foundation | 3/24/2015 | 3/24/2015 | 3/24/2015 | P | PASS |
Mike Jordan
|
|
|
Shane-flat work rebar Phone #: ###-####. Interior column pad footings and thickend footings under slab on grade.
|
BLD-Energy code compliance | 3/10/2015 | 3/10/2015 | 3/10/2015 | A | PASS |
Mike Jordan
|
|
|
Vicky Phone #: ###-####. rigid insulation on interior side of foundation wall under SOG.
|
BLD-Foundation | 3/4/2015 | 3/4/2015 | 3/4/2015 | P | PASS |
Dave Hannah
|
|
|
WALL // Manuel Phone #: ###-####
|
BLD-Footing | 3/3/2015 | 3/3/2015 | 3/3/2015 | P | PASS |
Jim Sly
|
|
|
Manuel Phone #: ###-####
|