BLD-Aging Inspection | 3/10/2016 | 3/10/2016 | 3/10/2016 | | PASS |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 12/31/2015 | 12/31/2015 | 12/31/2015 | | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 9/4/2015 | 9/4/2015 | 9/4/2015 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand. Wil be ok for perm occ. once zoning and oublic works signs perm.
|
BLD-Final | 9/1/2015 | 9/1/2015 | 9/1/2015 | P | NR |
Mike Jordan
|
|
|
come as late morning as you can still waiting for MEP Phone #: ###-#### Inspection requested via web by Tyler Hildebrand.
|
FIRE-Final Inspection | 8/26/2015 | 8/27/2015 | 8/27/2015 | A | PASS |
Troy Cobbley
|
|
|
Life Safety Passed
|
BLD-Energy code compliance | 6/22/2015 | 6/23/2015 | 6/23/2015 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
|
BLD-Framing/Rough-in | 6/23/2015 | 6/23/2015 | 6/23/2015 | A | CANC |
Dave Hannah
|
|
|
rough framing Phone #: ###-#### >> Inspection requested via web by Mel Rawlinson Inspection cancelled from web by: Mel Rawlinson
|
BLD-Framing/Rough-in | 6/22/2015 | 6/22/2015 | 6/23/2015 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
|
BLD-Wall Bracing | 5/19/2015 | 5/19/2015 | 5/19/2015 | P | PASS |
Mike Jordan
|
|
|
exterior shear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
|
BLD-Conference | 4/27/2015 | 4/28/2015 | 4/28/2015 | A | NR |
Mike Jordan
|
|
|
exterior shear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
|
BLD-Conference | 4/9/2015 | 4/10/2015 | 4/10/2015 | A | PASS |
Mike Jordan
|
|
|
interior shear 2nd floor Phone #: ###-#### Inspection requested via web by Mel Rawlinson
|
BLD-Wall Bracing | 4/1/2015 | 4/2/2015 | 4/2/2015 | A | PASS |
Phil Shearer
|
|
|
1st floor sheer
|
BLD-Wall Bracing | 4/1/2015 | 4/1/2015 | 4/1/2015 | P | NR |
Mike Jordan
|
|
|
FIRST FLOOR INTERIOR SHEAR Phone #: ###-#### Inspection requested via web by Mel Rawlinson
|
BLD-Foundation | 3/24/2015 | 3/24/2015 | 3/24/2015 | P | PASS |
Mike Jordan
|
|
|
Shane-flat work rebar Phone #: ###-####. Interior column pad footings and thickend footings under slab on grade.
|
BLD-Energy code compliance | 3/12/2015 | 3/12/2015 | 3/12/2015 | P | PASS |
Mike Jordan
|
|
|
Vicki Phone #: ###-####. rigid insulation under sog.
|
BLD-Foundation | 3/10/2015 | 3/10/2015 | 3/10/2015 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Foundation | 3/10/2015 | 3/10/2015 | 3/10/2015 | A | CANC |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Footing | 3/10/2015 | 3/10/2015 | 3/10/2015 | A | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|