Permit Information
Permit NumberBLD13-03600
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 12141 W OVERLAND RD
Project NameCantabria Development
Customer Number 
ePlanReviewNo
Description
(CANTABRIA DEVELOPMENT - BLDG 21) - To construct a new 3,668 sq. ft., two story, Four unit, apartment building. Units 'A' have one bedroom, one den, and two bathrooms. Units 'B' have two bedrooms, and two bathrooms. All 4 dwelling units have their own independent exit. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partition separations are required between dwelling units. This building is required to be fire sprinklered. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. DRH13-00337 Per Planning and Zoning. See BLD13-03579 for building plan review report. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection3/14/20163/14/20163/14/2016 PASS
DetailsMike Jordan
BLD-Aging Inspection1/12/20161/12/20161/13/2016 PASS
DetailsMike Jordan
BLD-Aging Inspection11/12/201511/12/201511/12/2015 PASS
DetailsMike Jordan
BLD-Final8/31/20158/31/20158/31/2015PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand. Will be ok for perm occ. once zoning signs perm
FIRE-Final Inspection8/26/20158/27/20158/27/2015APASS
DetailsTroy Cobbley
Life Safety Passed
BLD-Energy code compliance7/8/20157/8/20157/8/2015PPASS
DetailsMike Jordan
BLD-Energy code compliance7/7/20157/8/20157/8/2015ANR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
BLD-Framing/Rough-in7/7/20157/7/20157/7/2015PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
BLD-Energy code compliance7/6/20157/6/20157/6/2015PCANC
DetailsPhil Shearer
Having insulation scheduled to be done by noon, sheetrock to be dropped by 2. If you can be here between 12-and 2 Id appreciate that. Thanks Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
BLD-Framing/Rough-in7/6/20157/6/20157/6/2015PNR
DetailsPhil Shearer
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
BLD-Framing/Rough-in7/6/20157/7/20157/6/2015PCANC
DetailsMike Jordan
Having insulation scheduled to be done by noon, sheetrock to be dropped by 2. If you can be here between 12-and 2 Id appreciate that. Thanks Phone #: ###-#### >> Inspection requested via web by Tyler Hildebrand Inspection cancelled from web by: Tyler Hildebrand
BLD-Wall Bracing5/5/20155/5/20155/5/2015PPASS
DetailsMike Jordan
exterior shear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Wall Bracing4/16/20154/16/20154/16/2015PPASS
DetailsMike Jordan
2nd floor interior shear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Wall Bracing4/9/20154/10/20154/10/2015APASS
DetailsMike Jordan
interior shear 1st floor Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Energy code compliance3/26/20153/27/20153/27/2015APASS
DetailsMike Jordan
Insulation// Rob Phone #: ###-####
BLD-Foundation3/24/20153/25/20153/25/2015APASS
DetailsMike Jordan
Manuel Phone #: ###-####
BLD-Footing3/23/20153/23/20153/23/2015PPASS
DetailsMike Jordan
Manuel Phone #: ###-####