BLD-Final | 8/8/2014 | 8/11/2014 | 8/11/2014 | A | PASS |
Phil Shearer
|
|
|
Call Ross. Final letter for special inspections (Strata) is available at the job site. Mike wants to pick it up on Monday. Thank you! Phone #: ###-#### Inspection requested via web by Jakie Phelps
|
DOC - Permit Finaled | 8/11/2014 | 8/11/2014 | 8/11/2014 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Ceiling Grid Inspection | 8/6/2014 | 8/7/2014 | 8/7/2014 | A | CANC |
Mike Jordan
|
|
|
Ross Phone #: ###-####
|
BLD-Final | 8/7/2014 | 8/7/2014 | 8/7/2014 | A | PART |
Mike Jordan
|
|
|
Ross Phone #: ###-####. Need final letter from special inspection. ok for temp occ.
|
FIRE-Final Inspection | 8/5/2014 | 8/6/2014 | 8/6/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
BLD-Final | 8/1/2014 | 8/6/2014 | 8/5/2014 | P | CANC |
Phil Shearer
|
|
|
ross
|
FIRE-Final Inspection | 8/1/2014 | 8/5/2014 | 8/5/2014 | P | FAIL |
Troy Cobbley
|
|
|
Could not perform life safety inspection due to project related fire alarm permit. Electrician wanted to work on fire alarm and could not do the exit signs and emergency lights
|
Code Occupancy Approval | | | 7/31/2014 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 7/23/2014 | 7/24/2014 | 7/24/2014 | A | PASS |
Mike Jordan
|
|
|
Ross- Phone #: ###-####
|
BLD-Energy code compliance | 6/18/2014 | 6/18/2014 | 6/18/2014 | P | PASS |
Tom Arcoraci
|
|
|
Ross Phone #: ###-####
|
BLD-Framing/Rough-in | 5/21/2014 | 5/22/2014 | 5/22/2014 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall Bracing | 5/21/2014 | 5/21/2014 | 5/21/2014 | P | PASS |
Tom Arcoraci
|
|
|
Ross Phone #: ###-####
|
BLD-Framing/Rough-in | 5/14/2014 | 5/15/2014 | 5/15/2014 | A | PART |
Jim Storey
|
|
|
Ross Phone #: ###-#### si welding ok/ screw wall bracing ok north/south walls
|
BLD-Concrete | 5/7/2014 | 5/8/2014 | 5/8/2014 | P | PASS |
Tom Arcoraci
|
|
|
ross - 2:00 pm - masonary inspection Phone #: ###-####
|
BLD-Other | 5/7/2014 | 5/7/2014 | 5/7/2014 | P | PART |
Tom Arcoraci
|
|
|
Masonary around 3 - Ross Phone #: ###-#### pending spec insp
|
BLD-Foundation | 4/21/2014 | 4/22/2014 | 4/22/2014 | P | PASS |
Tom Arcoraci
|
|
|
Rebar also///Dan- would like beween 12:00 & 1:00 Phone #: ###-####
|
BLD-Footing | 4/16/2014 | 4/17/2014 | 4/17/2014 | P | PART |
Mike Jordan
|
|
|
Dan Phone #: ###-####. perimeter and interior footings for new east wing, work in progress. Will have special inspection.
|