BLD-Final | 4/9/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
BLD-Aging Inspection | 4/9/2015 | 4/9/2015 | 4/9/2015 | | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 1/27/2015 | 1/28/2015 | 1/28/2015 | A | PART |
Mike Jordan
|
|
|
Tyler Phone #: ###-####. ok for temp occ. Will be ok for perm occ. once zoning sign perm.
|
BLD-Final | 1/26/2015 | 1/26/2015 | 1/26/2015 | P | NR |
Mike Jordan
|
|
|
Tyler Phone #: ###-####
|
BLD-Final | 1/15/2015 | 1/15/2015 | 1/15/2015 | P | CANC |
Mike Jordan
|
|
|
Tyler Phone #: ###-####
|
BLD-Final | 1/8/2015 | 1/9/2015 | 1/9/2015 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand. Still working on ADA componets on type A unit.
|
FIRE-Final Inspection | 1/8/2015 | 1/9/2015 | 1/9/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Energy code compliance | 11/17/2014 | 11/18/2014 | 11/18/2014 | A | PASS |
Mike Jordan
|
|
|
TYLER Phone #: ###-####
|
BLD-Framing/Rough-in | 11/14/2014 | 11/14/2014 | 11/14/2014 | P | PASS |
Phil Shearer
|
|
|
tyler Phone #: ###-####
|
BLD-Energy code compliance | 11/14/2014 | 11/14/2014 | 11/14/2014 | P | CANC |
Mike Jordan
|
|
|
tyler Phone #: ###-#### Inspection cancelled from web by: Darin Thornton
|
BLD-Wall Bracing | 9/24/2014 | 9/24/2014 | 9/24/2014 | P | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####. floor to floor straps ok.
|
BLD-Wall Bracing | 9/17/2014 | 9/18/2014 | 9/18/2014 | A | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####. 2nd. floor interior shear walls ok.
|
BLD-Wall Bracing | 9/16/2014 | 9/16/2014 | 9/16/2014 | P | PASS |
Mike Jordan
|
|
|
Exterior shear walls, 2nd. floor ok.
|
BLD-Wall Bracing | 9/15/2014 | 9/16/2014 | 9/16/2014 | A | PART |
Mike Jordan
|
|
|
Richard Phone #: ###-####. 2nd. floor exterior walls. work in progress.
|
BLD-Wall Bracing | 9/15/2014 | 9/15/2014 | 9/15/2014 | P | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####. 2nd. floor straps ok.
|
BLD-Wall Bracing | 9/12/2014 | 9/12/2014 | 9/12/2014 | P | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####. 1st. floor exterior walls ok.
|
BLD-Wall Bracing | 9/9/2014 | 9/9/2014 | 9/9/2014 | P | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####. 1st. floor interior shear walls ok.
|
BLD-Footing | 7/23/2014 | 7/24/2014 | 7/24/2014 | P | PASS |
Mike Jordan
|
|
|
Shane Phone #: ###-####. Interior thickend footings.
|
BLD-Energy code compliance | 7/17/2014 | 7/17/2014 | 7/17/2014 | P | PASS |
Mike Jordan
|
|
|
foundation insulation - ashley Phone #: ###-####
|
BLD-Foundation | 7/14/2014 | 7/15/2014 | 7/15/2014 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Footing | 7/11/2014 | 7/14/2014 | 7/14/2014 | A | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|