DOC - Permit Finaled | 11/4/2014 | 11/4/2014 | 11/4/2014 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 11/4/2014 | 11/4/2014 | 11/4/2014 | P | PASS |
Tony Young
|
|
|
2.72
|
BLD-Final | 11/4/2014 | 11/4/2014 | 11/4/2014 | P | PASS |
Tony Young
|
|
|
blower test 2.72
|
BLD-Conference | 9/19/2014 | 9/19/2014 | 9/19/2014 | P | PART |
Mike Jordan
|
|
|
Call 30 min prior Phone #: ###-#### Inspection requested via web by Chris Laraway. Needs blower door test. Noted window by back door is not tempered. Window will be blocked off until new window arrives, one week. CO was issued.
|
BLD-Energy code compliance | 7/16/2014 | 7/17/2014 | 7/17/2014 | A | PASS |
Tony Young
|
|
|
Call Matt 1/2 hour before inspection if possible. 208.922.0695 Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD-Framing/Rough-in | 7/14/2014 | 7/14/2014 | 7/14/2014 | P | PASS |
Tony Young
|
|
|
Call 30 minutes prior to meet on site. Phone #: ###-#### Inspection requested via web by Chris Laraway,, ok to insulate
|
BLD-Framing/Rough-in | 7/11/2014 | 7/14/2014 | 7/14/2014 | A | PASS |
Tony Young
|
|
|
Call 30 minutes prior to meet on site. Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD-Wall Bracing | 7/1/2014 | 7/2/2014 | 7/2/2014 | P | PASS |
Tony Young
|
|
|
House has already passed shear wall insp. we need inspection on the shop behind. Phone #: ###-#### >> Inspection requested via web by Chris Laraway,, wip,, ok
|
BLD-Wall Bracing | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PART |
Tony Young
|
|
|
Matt Phone #: ###-####,, exterior ok
|
BLD-Footing | 4/25/2014 | 4/28/2014 | 4/28/2014 | P | PART |
Tony Young
|
|
|
Pat Phone #: ###-####,, work in progress,,, builder needs to change the plans if he is not using rebar in the house footings
|