BLD-Final | 12/12/2014 | 12/15/2014 | 12/15/2014 | A | PASS |
Mike Jordan
|
|
|
Final Inspection
Thank you, Dave ###-#### Phone #: ###-#### Inspection requested via web by David Moorhouse. Ok for perm occ.
|
FIRE-Final Inspection | 12/12/2014 | 12/15/2014 | 12/12/2014 | A | CANC |
Troy Cobbley
|
|
|
Final Inspection Please
Thanks, Dave 9###-#### Phone #: ###-#### >> Inspection requested via web by David Moorhouse Inspection cancelled from web by: David Moorhouse
|
FIRE-Final Inspection | 12/11/2014 | 12/12/2014 | 12/12/2014 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety passed
|
FIRE-Conference | 11/3/2014 | 11/4/2014 | 11/4/2014 | A | DONE |
Troy Cobbley
|
|
|
Inspection under stairs on both ends passed and can be covered.
|
BLD-Other | 10/28/2014 | 10/28/2014 | 10/28/2014 | A | PASS |
Mike Jordan
|
|
|
PLease inspect 1st layer of 2nd floor ceiling sheetrock. Please come as early as possible.
Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
|
FIRE-Conference | 10/24/2014 | 10/24/2014 | 10/24/2014 | A | PASS |
Troy Cobbley
|
|
|
North and south stairwell insulation is complete and piping can be covered. Second floor insulation is complete and sprinkler piping can be covered.
|
BLD-Conference | 10/23/2014 | 10/23/2014 | 10/23/2014 | P | PASS |
Dave Hannah
|
|
|
Please 2nd floor insulation
Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
|
BLD-Energy code compliance | 10/23/2014 | 10/23/2014 | 10/23/2014 | P | PASS |
Dave Hannah
|
|
|
Please 2nd floor insulation
Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
|
BLD-Energy code compliance | 10/20/2014 | 10/20/2014 | 10/20/2014 | P | PASS |
Mike Jordan
|
|
|
Requesting a 3rd Floor Energy Code Compliance. 2nd Floor Framing 1st Floor Structural post 1hr protection. Will have data on site for product used. Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. ok to sheet rock 3rd. floor.
|
BLD-Conference | 10/14/2014 | 10/15/2014 | 10/15/2014 | P | PASS |
Mike Jordan
|
|
|
Please inspect fire caulking on third floor to approve for insulation.
Thanks,
Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. All fire stopping is completed at the 3rd floor. Framing repairs in progress. Ok to insulate 3rd floor only.
|
BLD-Framing/Rough-in | 10/10/2014 | 10/10/2014 | 10/10/2014 | P | FAIL |
Mike Jordan
|
|
|
Please inspect the 3rd floor framing
Thanks Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. Correction notice posted.
|
BLD-Energy code compliance | 10/9/2014 | 10/10/2014 | 10/10/2014 | P | PASS |
Mike Jordan
|
|
|
Please contact Vicky to ensure access and can meet on site ###-####. Set for PM to ensure insulation is complete. Also will have plans for the 2nd floor TI on site.
Thanks Dave ###-#### Phone #: ###-#### Inspection requested via web by David Moorhouse. Ok to sheet rock first floor only, except for columns and underneath stair treads.
|
BLD-Energy code compliance | 10/10/2014 | 10/10/2014 | 10/10/2014 | A | CANC |
Mike Jordan
|
|
|
. Moved to pm.
|
BLD-Energy code compliance | 10/8/2014 | 10/9/2014 | 10/10/2014 | P | PART |
Mike Jordan
|
|
|
Would like an energy code inspection for pm for 1st level. Please call Vicky at ###-#### with questions or concerns or Dave ###-####. For access call either numbers
Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. 1st. floor energy code ok. Needs fire inspection and will need tenant improvement plans prior to cover.
|
BLD-Conference | 10/5/2014 | 10/6/2014 | 10/6/2014 | P | PASS |
Mike Jordan
|
|
|
Framing re-inspection 1st Floor.
Call if locked up for the key code. ###-#### ###-####
Thanks,
Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. All framing issues hace been resolved. Ok to insulate 1st. floor only.
|
BLD-Framing/Rough-in | 10/2/2014 | 10/3/2014 | 10/3/2014 | A | FAIL |
Mike Jordan
|
|
|
Fireblock at electrical panel fur out at ceiling-NW corner. Foam seal around plumbing penetrartions at both restroomsabove furdown ceilings at OSB. Provide a 3rd stud at the simpson hdu8 hold downs on west wall as per detail 8 on SD1.0, also nail all double and triple studs 16D nails at 8"o.c. staggered at all hold down locations. Install full height LSL blocking with A35's at front and back popouts. Provide All backing for ADA components in restrooms. ok to insulate 1st. floor only, this framing inspection is for the first floor only. Also need a fire inspection after insulation, prior to energy code. Will Also need the city approved TI plans prior to sheet rock, due to occupancy change on 2nd. floor (A-2), changing to a seperated use. Additional fire rated construction for 1st floor will need to be verified. Correction notice posted. ok to insulate 1st. floor only.
|
BLD-Conference | 10/2/2014 | 10/2/2014 | 10/2/2014 | P | PART |
Mike Jordan
|
|
|
1st floor framing inspection prior to insulation.
Thank you, Phone #: ###-#### Inspection requested via web by David Moorhouse. Partial, schedule for the am, out of time.
|
BLD-Conference | 10/1/2014 | 10/2/2014 | 10/2/2014 | A | CANC |
Dave Hannah
|
|
|
Would like a First floor framing inspection. Requesting inspection for approval to insulate.
Thank you, Phone #: ###-#### >> Inspection requested via web by David Moorhouse Inspection cancelled from web by: David Moorhouse
|
BLD-Wall Bracing | 9/5/2014 | 9/5/2014 | 9/5/2014 | A | DONE |
Dave Hannah
|
|
|
Please inspect mechanical Fasteners especially in South Stairwell before shear to be installed.
Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
|
BLD-Wall Bracing | 9/5/2014 | 9/5/2014 | 9/5/2014 | P | PART |
Dave Hannah
|
|
|
Please inspect mechanical Fasteners especially in South Stairwell before shear to be installed.
Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse hold downs ok ok to insulate ext soffits
|
BLD-Conference | 9/3/2014 | 9/4/2014 | 9/5/2014 | P | PART |
Dave Hannah
|
|
|
Please inspect mechanical Fasteners especially in South Stairwell before shear to be installed.
Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
|
BLD-Conference | 8/28/2014 | 8/29/2014 | 8/29/2014 | A | PART |
Jim Storey
|
|
|
We need an inspection of hold downs on first floor stair wall, so we can install shear after inspection.
Thanks,
Dave Moorhouse Phone #: ###-#### Inspection requested via web by David Moorhouse south stair hold downs ok to cover // north hold short.
|
BLD-Wall Bracing | 8/24/2014 | 8/25/2014 | 8/25/2014 | A | PASS |
Mike Jordan
|
|
|
Exterior Shear inspection is being requested. I was told that a partial inspection of certain floors was complete. I will be on site in the morning and can be reached by phone. Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. All exterior walls ok for cover, roof ok for cover.
|
BLD-Conference | 8/15/2014 | 8/18/2014 | 8/18/2014 | A | PASS |
Dave Hannah
|
|
|
Requesting a shear inspection. Exterior and a stair way.
Thank you
Dave Phone #: ###-#### >> Inspection requested via web by David Moorhouse ok to cover ground level ext walls and inside stair tower second floor.
|
BLD-Conference | 8/12/2014 | 8/13/2014 | 8/13/2014 | A | CANC |
Mike Jordan
|
|
|
Requesting a 3rd story shear wall inspection as soon as you can AM Wednesday August 13th. Inspector requested to see walls before they are stood. Thank you. Phone #: ###-#### Inspection requested via web by David Moorhouse
|
BLD-Wall Bracing | 8/13/2014 | 8/13/2014 | 8/13/2014 | A | PASS |
Mike Jordan
|
|
|
Requesting a 3rd story shear wall inspection as soon as you can AM Wednesday August 13th. Inspector requested to see walls before they are stood. Thank you. Phone #: ###-#### . Inspection requested via web by DavidMoorhouse. 3rd floor exterior shear walls ok.
|
BLD-Wall Bracing | 7/30/2014 | 7/31/2014 | 7/31/2014 | A | PASS |
Phil Shearer
|
|
|
Dave-in stairwell Phone #: ###-#### 1st floor interior stair way shear walls only
|
BLD-Foundation | 7/2/2014 | 7/2/2014 | 7/2/2014 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Footing | 6/26/2014 | 6/26/2014 | 6/26/2014 | P | DEFR |
Mike Jordan
|
|
|
Chris Phone #: ###-####. Special inspection this morning. Will review report.
|