Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD14-00819
StatusFinaled
Name MCCARTER-MOORHOUSE LLC
Site Address 1508 S CLOVERDALE RD
Project NameThe Boise Tech Mall
Customer Number 
ePlanReviewYes
Description
Boise Tech Mall - To construct a new 11,860 square foot, three story, wood framed office and retail building and related site improvements. This building is fully fire sprinkled. The sprinklers are used for substitution for one-hour fire-resistive construction. 1st FL: 3,900 sq. ft., 2nd FL: 3,995 sq. ft., 3rd FL: 3,965 sq. ft. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/12/201412/15/201412/15/2014APASS
DetailsMike Jordan
Final Inspection

Thank you, Dave ###-#### Phone #: ###-#### Inspection requested via web by David Moorhouse. Ok for perm occ.
FIRE-Final Inspection12/12/201412/15/201412/12/2014ACANC
DetailsTroy Cobbley
Final Inspection Please

Thanks, Dave 9###-#### Phone #: ###-#### >> Inspection requested via web by David Moorhouse Inspection cancelled from web by: David Moorhouse
FIRE-Final Inspection12/11/201412/12/201412/12/2014PPASS
DetailsTroy Cobbley
Fire life safety passed
FIRE-Conference11/3/201411/4/201411/4/2014ADONE
DetailsTroy Cobbley
Inspection under stairs on both ends passed and can be covered.
BLD-Other10/28/201410/28/201410/28/2014APASS
DetailsMike Jordan
PLease inspect 1st layer of 2nd floor ceiling sheetrock. Please come as early as possible.

Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
FIRE-Conference10/24/201410/24/201410/24/2014APASS
DetailsTroy Cobbley
North and south stairwell insulation is complete and piping can be covered. Second floor insulation is complete and sprinkler piping can be covered.
BLD-Conference10/23/201410/23/201410/23/2014PPASS
DetailsDave Hannah
Please 2nd floor insulation

Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
BLD-Energy code compliance10/23/201410/23/201410/23/2014PPASS
DetailsDave Hannah
Please 2nd floor insulation

Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
BLD-Energy code compliance10/20/201410/20/201410/20/2014PPASS
DetailsMike Jordan
Requesting a 3rd Floor Energy Code Compliance.
2nd Floor Framing
1st Floor Structural post 1hr protection. Will have data on site for product used.
Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. ok to sheet rock 3rd. floor.
BLD-Conference10/14/201410/15/201410/15/2014PPASS
DetailsMike Jordan
Please inspect fire caulking on third floor to approve for insulation.

Thanks,

Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. All fire stopping is completed at the 3rd floor. Framing repairs in progress. Ok to insulate 3rd floor only.
BLD-Framing/Rough-in10/10/201410/10/201410/10/2014PFAIL
DetailsMike Jordan
Please inspect the 3rd floor framing

Thanks Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. Correction notice posted.
BLD-Energy code compliance10/9/201410/10/201410/10/2014PPASS
DetailsMike Jordan
Please contact Vicky to ensure access and can meet on site ###-####. Set for PM to ensure insulation is complete. Also will have plans for the 2nd floor TI on site.

Thanks Dave ###-#### Phone #: ###-#### Inspection requested via web by David Moorhouse. Ok to sheet rock first floor only, except for columns and underneath stair treads.
BLD-Energy code compliance10/10/201410/10/201410/10/2014ACANC
DetailsMike Jordan
. Moved to pm.
BLD-Energy code compliance10/8/201410/9/201410/10/2014PPART
DetailsMike Jordan
Would like an energy code inspection for pm for 1st level. Please call Vicky at ###-#### with questions or concerns or Dave ###-####. For access call either numbers

Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. 1st. floor energy code ok. Needs fire inspection and will need tenant improvement plans prior to cover.
BLD-Conference10/5/201410/6/201410/6/2014PPASS
DetailsMike Jordan
Framing re-inspection 1st Floor.

Call if locked up for the key code. ###-#### ###-####

Thanks,

Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. All framing issues hace been resolved. Ok to insulate 1st. floor only.
BLD-Framing/Rough-in10/2/201410/3/201410/3/2014AFAIL
DetailsMike Jordan
Fireblock at electrical panel fur out at ceiling-NW corner. Foam seal around plumbing penetrartions at both restroomsabove furdown ceilings at OSB. Provide a 3rd stud at the simpson hdu8 hold downs on west wall as per detail 8 on SD1.0, also nail all double and triple studs 16D nails at 8"o.c. staggered at all hold down locations. Install full height LSL blocking with A35's at front and back popouts. Provide All backing for ADA components in restrooms. ok to insulate 1st. floor only, this framing inspection is for the first floor only. Also need a fire inspection after insulation, prior to energy code. Will Also need the city approved TI plans prior to sheet rock, due to occupancy change on 2nd. floor (A-2), changing to a seperated use. Additional fire rated construction for 1st floor will need to be verified. Correction notice posted. ok to insulate 1st. floor only.
BLD-Conference10/2/201410/2/201410/2/2014PPART
DetailsMike Jordan
1st floor framing inspection prior to insulation.

Thank you,
Phone #: ###-#### Inspection requested via web by David Moorhouse. Partial, schedule for the am, out of time.
BLD-Conference10/1/201410/2/201410/2/2014ACANC
DetailsDave Hannah
Would like a First floor framing inspection. Requesting inspection for approval to insulate.

Thank you, Phone #: ###-#### >> Inspection requested via web by David Moorhouse Inspection cancelled from web by: David Moorhouse
BLD-Wall Bracing9/5/20149/5/20149/5/2014ADONE
DetailsDave Hannah
Please inspect mechanical Fasteners especially in South Stairwell before shear to be installed.

Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
BLD-Wall Bracing9/5/20149/5/20149/5/2014PPART
DetailsDave Hannah
Please inspect mechanical Fasteners especially in South Stairwell before shear to be installed.

Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse hold downs ok ok to insulate ext soffits
BLD-Conference9/3/20149/4/20149/5/2014PPART
DetailsDave Hannah
Please inspect mechanical Fasteners especially in South Stairwell before shear to be installed.

Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
BLD-Conference8/28/20148/29/20148/29/2014APART
DetailsJim Storey
We need an inspection of hold downs on first floor stair wall, so we can install shear after inspection.

Thanks,

Dave Moorhouse Phone #: ###-#### Inspection requested via web by David Moorhouse south stair hold downs ok to cover // north hold short.
BLD-Wall Bracing8/24/20148/25/20148/25/2014APASS
DetailsMike Jordan
Exterior Shear inspection is being requested. I was told that a partial inspection of certain floors was complete. I will be on site in the morning and can be reached by phone. Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. All exterior walls ok for cover, roof ok for cover.
BLD-Conference8/15/20148/18/20148/18/2014APASS
DetailsDave Hannah
Requesting a shear inspection. Exterior and a stair way.

Thank you

Dave Phone #: ###-#### >> Inspection requested via web by David Moorhouse ok to cover ground level ext walls and inside stair tower second floor.
BLD-Conference8/12/20148/13/20148/13/2014ACANC
DetailsMike Jordan
Requesting a 3rd story shear wall inspection as soon as you can AM Wednesday August 13th. Inspector requested to see walls before they are stood. Thank you. Phone #: ###-#### Inspection requested via web by David Moorhouse
BLD-Wall Bracing8/13/20148/13/20148/13/2014APASS
DetailsMike Jordan
Requesting a 3rd story shear wall inspection as soon as you can AM Wednesday August 13th. Inspector requested to see walls before they are stood. Thank you. Phone #: ###-#### . Inspection requested via web by DavidMoorhouse. 3rd floor exterior shear walls ok.
BLD-Wall Bracing7/30/20147/31/20147/31/2014APASS
DetailsPhil Shearer
Dave-in stairwell Phone #: ###-####
1st floor interior stair way shear walls only
BLD-Foundation7/2/20147/2/20147/2/2014PPASS
DetailsMike Jordan
Pat Phone #: ###-####
BLD-Footing6/26/20146/26/20146/26/2014PDEFR
DetailsMike Jordan
Chris Phone #: ###-####. Special inspection this morning. Will review report.