Permit Information
Permit NumberBLD14-01045
StatusIssued
Name C2 CONSTRUCTION
Site Address 715 S CAPITOL BLVD
Project NameBoise Public Library 1st Floor
Customer Number 
ePlanReviewYes
Description
(BOISE MAIN PUBLIC LIBRARY - NORTHWEST CORNER OF 1ST STORY) Fire sprinklers used to substitute for 1-hr construction. To remodel an existing 4,003 square foot employee work area located within the Northwest corner of the 1st story in the Boise Main Public Library. Work is to include 2 restrooms accessible to the disabled, interior nonbearing walls, suspended gypsum board ceilings, suspended acoustical ceilings, new exterior windows, new exterior brick, new interior doors and windows, millwork, and finishes. A new 18” x 18” opening will be cut in the existing exterior wall for an outside air duct. A new 24” x 18” opening will be cut in the existing exterior wall for an exhaust duct. Adequate headers are required to support the weight of the walls located above the openings. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/28/201412/1/201412/1/2014PPASS
DetailsJim Sly
Miguel 794- 4062
OK for Perm Occ.
BLD-Final11/26/201411/28/201411/28/2014APEND
DetailsJim Sly
call before to meet // Miguel Phone #: ###-####
Need zoning final
FIRE-Final Inspection11/28/201411/28/201411/28/2014APASS
DetailsForrest France
Fire life safety inspection passed provided door hardware at the SW exit is reversed to allow free egress as discussed- to be finished prior to structural final for verification at that time.
BLD-Final11/20/201411/21/201411/22/2014PNR
DetailsDave Hannah
Miguel Phone #: ###-####
FIRE-Sprinkler Rough-in11/17/201411/17/201411/17/2014APART
DetailsForrest France
Overhead fire sprinkler work approved for cover at the remodel area.
BLD-Ceiling Grid Inspection11/6/201411/6/201411/7/2014PPASS
DetailsDave Hannah
Miguel Phone #: ###-####
BLD-Framing/Rough-in10/20/201410/21/201410/22/2014PPART
DetailsDave Hannah
Phone #: ###-#### windows and soffits 1st floor offices ok to cover
BLD-Framing/Rough-in9/10/20149/10/20149/10/2014PCANC
DetailsMike Jordan
BLD-Framing/Rough-in9/9/20149/10/20149/10/2014APASS
DetailsMike Jordan
Miguel Phone #: ###-####
BLD-Framing/Rough-in9/5/20149/8/20149/9/2014APART
DetailsDave Hannah
Miguel Phone #: ###-#### ok to cover hard lids in restrooms
BLD-Framing/Rough-in8/28/20148/29/20148/29/2014APART
DetailsJim Storey
Miguel Phone #: ###-#### restroom and office walls only ok to cover.