BLD-Final | 4/8/2015 | 4/9/2015 | 4/9/2015 | A | PASS |
Mike Jordan
|
|
|
Jeremy Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 1/9/2015 | 1/9/2015 | 1/9/2015 | A | PART |
Mike Jordan
|
|
|
Pat Phone #: ###-####. ok for perm occ.
|
BLD-Final | 1/8/2015 | 1/8/2015 | 1/9/2015 | P | CANC |
Dave Hannah
|
|
|
Pat Phone #: ###-#### out of time resecduled
|
FIRE-Final Inspection | 1/8/2015 | 1/8/2015 | 1/8/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 1/6/2015 | 1/7/2015 | 1/7/2015 | A | FAIL |
Troy Cobbley
|
|
|
Need project related fire alarm and fire sprinkler permits finaled. Smoke alarm in 201 was repaired and tested ok.
|
FIRE-Final Inspection | 1/5/2015 | 1/6/2015 | 1/6/2015 | P | FAIL |
Troy Cobbley
|
|
|
Project related fire alarm and fire sprinkler permits are not ready. I noted that a smoke alarm in #201 did not sound the other smoke alarms when activated.
|
BLD-Other | 11/7/2014 | 11/10/2014 | 11/10/2014 | A | PASS |
Phil Shearer
|
|
|
Pat-rc channel Phone #: ###-####
|
BLD-Energy code compliance | 11/6/2014 | 11/7/2014 | 11/7/2014 | P | PASS |
Mike Jordan
|
|
|
Pat-please do as late as possible Phone #: ###-####
|
BLD-Framing/Rough-in | 11/6/2014 | 11/6/2014 | 11/6/2014 | P | PART |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Pending mech. rough in inspection. Complete airseal upstairs at linesets and dryer ducts. Firestop penetrations in draft stop in attic, firestop 3inch ducts at top plates downstairs and straP TOP PLATES AT THOSE LOCATIONS.
|
BLD-Wall Bracing | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Foundation | 9/3/2014 | 9/3/2014 | 9/3/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Foundation | 9/2/2014 | 9/3/2014 | 9/3/2014 | A | NR |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 8/29/2014 | 9/2/2014 | 9/2/2014 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####
|