Permit Information
Permit NumberBLD14-01823
StatusFinaled
Name ESI
Site Address 521 E PARKCENTER BLVD
Project NameThe District at Parkcenter
Customer NumberBLD14-01818 FOR DRAWNGS
ePlanReviewYes
Description
(THE DISTRICT AT PARKCENTER - COTTAGE BUILDING B - #2) (7-1-16 PLAN MODIFICATION TO RE-DESIGN THE STRUCTURAL SYSTEM FROM THE FOUNDATION UP. REVISED STRUCTURAL DRAWINGS ARE FILED UNDER BLD14-01823 IN EPLANREVIEW.) (The drawings are filed under permit BLD14-01818 in ePlanReview) To construct a 10 dwelling unit two story apartment building with six units having their own garage (i.e. 6 garages). Four dwelling units will not have garages. The total floor area of this building is about 12,497 square feet (8,089 square feet 1st story and 4,408 square feet 2nd story). All ground floor units within Cottage Building B - #1 and Cottage Building B - #2 are required to comply as Type B dwelling units. Two ground floor units within Cottage Building A - #2 are required to comply as Type A dwelling units. Work is to include interior nonbearing walls, 1-hr bearing walls, 1-hr roof-ceiling assemblies, 1-hr floor-ceiling assemblies, 1-hr dwelling unit separations, attic insulation, interior doors, exterior windows and doors, insulated exterior walls, “Hardi-board” exterior siding, exterior manufactured stone wainscot, composition roof shingles, common stairways within a 1-hr corridor open to the outside, private interior stairways, garages, garage overhead doors, millwork, and finishes. Structural work includes concrete footings, concrete stem walls, concrete floor slabs on grade with thickened footings at interior bearing walls, wood floor trusses, wood roof trusses, wood columns, wood beams, and shear walls. Special inspection is required for soils, concrete, and wood. The designs for the roof trusses and floor trusses are deferred submittal items. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13R as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/27/20171/30/20171/30/2017PPASS
DetailsJim Storey
cory Phone #: ###-####
FIRE-Final Inspection1/30/20171/30/20171/30/2017APASS
DetailsJim Page
Final life fire safety inspection passed/complete
BLD-Aging Inspection12/13/201612/13/201612/13/2016 PASS
DetailsJim Storey
BLD-Final10/13/201610/14/201610/14/2016APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Corey Hockersmith temp ok c/n posted
BLD-Final10/11/201610/13/201610/13/2016PDEFR
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Corey Hockersmith
FIRE-Final Inspection10/11/201610/13/201610/13/2016APART
DetailsJim Page
Partial final life fire safety complete, final fire sprinkler inspection is complete, final fire alarm inspection is complete, fire extinguishers are in place with current inspection tags. Building fire sub-panel reports to clubhouse main fire panel, life fire safety will be a partial pass until clubhouse is done and the inspection is finaled/passed.
BLD-Wall cover7/18/20167/19/20167/19/2016APASS
DetailsJim Storey
Bathroom ceiling inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith
BLD-Ceiling Grid Inspection7/14/20167/18/20167/18/2016PDEFR
DetailsJim Storey
Bathroom ceiling inspection Phone #: ###-#### Inspection requested via web by Corey Hockersmith . out of time
BLD-Ceiling Grid Inspection6/20/20166/21/20166/21/2016PPASS
DetailsJim Storey
RC1 Channel Phone #: ###-####
BLD-Framing/Rough-in6/20/20166/20/20166/20/2016PPASS
DetailsJim Storey
Cory Phone #: ###-####
BLD-Framing/Rough-in6/15/20166/15/20166/15/2016PPART
DetailsJim Storey
###-#### JT c/n posted ok to insulate
BLD-Wall Bracing3/31/20164/1/20164/1/2016APASS
DetailsJim Storey
Shear roof & wall inspection - Corey Phone #: ###-####
BLD-Foundation9/28/20159/29/20159/29/2015APASS
DetailsJim Storey
Concrete to be onsite at 1:30 Phone #: ###-#### Inspection requested via web by Corey Hockersmith placed w/si
BLD-Footing9/23/20159/24/20159/24/2015APASS
DetailsJim Storey
2:30 Pour Phone #: ###-#### Inspection requested via web by Corey Hockersmith