BLD-Final | 5/21/2015 | 5/22/2015 | 5/22/2015 | P | PASS |
Jim Sly
|
|
|
Curtis Phone #: ###-####
|
FIRE-Final Inspection | 5/22/2015 | 5/22/2015 | 5/22/2015 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Framing/Rough-in | 4/23/2015 | 4/23/2015 | 4/23/2015 | P | PASS |
Mike Jordan
|
|
|
Curtis Phone #: ###-####. Went over masonry wall infill details with masonry contractor and general contractor.
|
BLD-Footing | 1/7/2015 | 1/8/2015 | 1/8/2015 | P | PASS |
Dave Hannah
|
|
|
Masonary wall rebar/grout-Top out- MTI scheduled to be on site,Grout scheduled for 12pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 1/5/2015 | 1/6/2015 | 1/6/2015 | A | PASS |
Dave Hannah
|
|
|
Partial Masonary wall grout,MTI scheduled to be onsie 10 am grout time Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/29/2014 | 12/30/2014 | 12/30/2014 | A | CANC |
Dave Hannah
|
|
|
Partial Masonary wall rebar and grout.MTI scheduled to be on site Grout planned for 10 am Phone #: ###-#### >> Inspection requested via web by Murph Naughtin Inspection cancelled from web by: Murph Naughtin
|
BLD-Foundation | 12/23/2014 | 12/24/2014 | 12/24/2014 | A | PEND |
Dave Hannah
|
|
|
Partial Masonary wall grout/rebar,MTI scheduled to be onside 11am grout Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/23/2014 | 12/23/2014 | 12/24/2014 | P | PART |
Dave Hannah
|
|
|
Partial Masonary grout/rebar MTI to be onsite, Grout scheduled for 2:30 pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/22/2014 | 12/22/2014 | 12/22/2014 | P | PART |
Dave Hannah
|
|
|
Partial Masonary wall grout/rebar.MTI scheduled to be on site 2PM grout Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/19/2014 | 12/19/2014 | 12/20/2014 | P | PEND |
Dave Hannah
|
|
|
Partial masonary wall rebar;grout,MTI to be on site, grout at 2 pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/17/2014 | 12/17/2014 | 12/18/2014 | P | PASS |
Dave Hannah
|
|
|
Partial masonary wall rebar/grout MTI scheduled to be on site, grout at 2pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/16/2014 | 12/16/2014 | 12/16/2014 | P | PASS |
Phil Shearer
|
|
|
Partial Masonary wall rebar/grout MTI to be onsite, grout scheduled for 2pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/15/2014 | 12/15/2014 | 12/15/2014 | P | CANC |
Phil Shearer
|
|
|
Partial Masonary wall rebar&grout,MTI tobe onsite,grout scheduled for 2 pm Phone #: ###-#### >> Inspection requested via web by Murph Naughtin Inspection cancelled from web by: Murph Naughtin
|
BLD-Foundation | 12/11/2014 | 12/12/2014 | 12/12/2014 | A | PART |
Jim Sly
|
|
|
Masonary wall rebar and grout insp. MTI to be on site,grout scheduled for 11am Phone #: ###-#### Inspection requested via web by Murph Naughtin OK Pending MTI special insp, tests and approvals.
|
BLD-Foundation | 12/9/2014 | 12/9/2014 | 12/9/2014 | P | PASS |
Phil Shearer
|
|
|
Masonary wall rebar and grout,MTI to be on site as special insp. Grouting at 2 pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/8/2014 | 12/8/2014 | 12/8/2014 | P | PASS |
Phil Shearer
|
|
|
Masonary wall bar ; grout,MTI to be onsite, grout scheduled for 2pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/5/2014 | 12/5/2014 | 12/6/2014 | P | PASS |
Dave Hannah
|
|
|
Masonary wall rebar/grout MTI to be onsite, grout scheduled for 1pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/3/2014 | 12/4/2014 | 12/6/2014 | P | PASS |
Dave Hannah
|
|
|
Masonary wall rebar-Rear wall, Grout scheduled for 2pm, MTI to be on site Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | DEFR |
Mike Jordan
|
|
|
masonry wall reinforcement, special inspector to be on site(MTI) Phone #: ###-#### Inspection requested via web by Murph Naughtin
|
BLD-Other | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | CANC |
Dave Hannah
|
|
|
Masonry rebar and grout Phone #: ###-#### >> Inspection requested via web by Murph Naughtin
|
BLD-Foundation | 10/17/2014 | 10/20/2014 | 10/20/2014 | A | PART |
Jim Sly
|
|
|
First thing please. Concrete at 9:30 Phone #: ###-#### Inspection requested via web by Kevin Honeycutt Last of foundation........ North and West found wall .....and interior footing matts OK pending MTI special inspections, tests and approvals.
|
BLD-Foundation | 10/15/2014 | 10/16/2014 | 10/16/2014 | A | PART |
Dave Hannah
|
|
|
Early as possible please. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt crew still setting forms mti will finish inspection
|
BLD-Footing | 10/10/2014 | 10/10/2014 | 10/10/2014 | P | PART |
Jim Sly
|
|
|
1/2 Bldg. South and East wall footings and piers OK pending MTI special inspection, tests and approvals.
|
BLD-Foundation | 10/8/2014 | 10/10/2014 | 10/10/2014 | P | CANC |
Jim Sly
|
|
|
12:00 PM inspection please. concrete scheduled for 1:00 PM. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
|
BLD-Footing | 10/7/2014 | 10/8/2014 | 10/8/2014 | A | PART |
Mike Jordan
|
|
|
Concrete is scheduled for 12 PM. Would prefer around 10 AM Phone #: ###-#### Inspection requested via web by Kevin Honeycutt. Work in progress, will hace special inspection.
|