Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD14-02003
StatusFinaled
Name ESI
Site Address 12336 W OVERLAND RD
Project NamePROJECT OVERDALE N&T HOLDINGS
Customer Number 
ePlanReviewYes
Description
Overdale N & T Holdings (Shell) - To construct a new 19,150 square foot, one story shell building and related site improvements. This building is constructed of masonry exterior walls, steel roof joists and metal roof deck. This is a shell permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. This building will fully fire sprinklered. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/21/20155/22/20155/22/2015PPASS
DetailsJim Sly
Curtis Phone #: ###-####
FIRE-Final Inspection5/22/20155/22/20155/22/2015PPASS
DetailsTroy Cobbley
life safety passed
BLD-Framing/Rough-in4/23/20154/23/20154/23/2015PPASS
DetailsMike Jordan
Curtis Phone #: ###-####. Went over masonry wall infill details with masonry contractor and general contractor.
BLD-Footing1/7/20151/8/20151/8/2015PPASS
DetailsDave Hannah
Masonary wall rebar/grout-Top out- MTI scheduled to be on site,Grout scheduled for 12pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation1/5/20151/6/20151/6/2015APASS
DetailsDave Hannah
Partial Masonary wall grout,MTI scheduled to be onsie 10 am grout time Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/29/201412/30/201412/30/2014ACANC
DetailsDave Hannah
Partial Masonary wall rebar and grout.MTI scheduled to be on site Grout planned for 10 am Phone #: ###-#### >> Inspection requested via web by Murph Naughtin Inspection cancelled from web by: Murph Naughtin
BLD-Foundation12/23/201412/24/201412/24/2014APEND
DetailsDave Hannah
Partial Masonary wall grout/rebar,MTI scheduled to be onside 11am grout Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/23/201412/23/201412/24/2014PPART
DetailsDave Hannah
Partial Masonary grout/rebar MTI to be onsite, Grout scheduled for 2:30 pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/22/201412/22/201412/22/2014PPART
DetailsDave Hannah
Partial Masonary wall grout/rebar.MTI scheduled to be on site 2PM grout Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/19/201412/19/201412/20/2014PPEND
DetailsDave Hannah
Partial masonary wall rebar;grout,MTI to be on site, grout at 2 pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/17/201412/17/201412/18/2014PPASS
DetailsDave Hannah
Partial masonary wall rebar/grout MTI scheduled to be on site, grout at 2pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/16/201412/16/201412/16/2014PPASS
DetailsPhil Shearer
Partial Masonary wall rebar/grout MTI to be onsite, grout scheduled for 2pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/15/201412/15/201412/15/2014PCANC
DetailsPhil Shearer
Partial Masonary wall rebar&grout,MTI tobe onsite,grout scheduled for 2 pm Phone #: ###-#### >> Inspection requested via web by Murph Naughtin Inspection cancelled from web by: Murph Naughtin
BLD-Foundation12/11/201412/12/201412/12/2014APART
DetailsJim Sly
Masonary wall rebar and grout insp. MTI to be on site,grout scheduled for 11am Phone #: ###-#### Inspection requested via web by Murph Naughtin
OK Pending MTI special insp, tests and approvals.
BLD-Foundation12/9/201412/9/201412/9/2014PPASS
DetailsPhil Shearer
Masonary wall rebar and grout,MTI to be on site as special insp. Grouting at 2 pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/8/201412/8/201412/8/2014PPASS
DetailsPhil Shearer
Masonary wall bar ; grout,MTI to be onsite, grout scheduled for 2pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/5/201412/5/201412/6/2014PPASS
DetailsDave Hannah
Masonary wall rebar/grout MTI to be onsite, grout scheduled for 1pm Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/3/201412/4/201412/6/2014PPASS
DetailsDave Hannah
Masonary wall rebar-Rear wall, Grout scheduled for 2pm, MTI to be on site Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Foundation12/1/201412/2/201412/2/2014ADEFR
DetailsMike Jordan
masonry wall reinforcement, special inspector to be on site(MTI) Phone #: ###-#### Inspection requested via web by Murph Naughtin
BLD-Other12/1/201412/2/201412/2/2014ACANC
DetailsDave Hannah
Masonry rebar and grout Phone #: ###-#### >> Inspection requested via web by Murph Naughtin
BLD-Foundation10/17/201410/20/201410/20/2014APART
DetailsJim Sly
First thing please. Concrete at 9:30 Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
Last of foundation........ North and West found wall .....and interior footing matts OK pending MTI special inspections, tests and approvals.
BLD-Foundation10/15/201410/16/201410/16/2014APART
DetailsDave Hannah
Early as possible please. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt crew still setting forms mti will finish inspection
BLD-Footing10/10/201410/10/201410/10/2014PPART
DetailsJim Sly
1/2 Bldg. South and East wall footings and piers OK pending MTI special inspection, tests and approvals.
BLD-Foundation10/8/201410/10/201410/10/2014PCANC
DetailsJim Sly
12:00 PM inspection please. concrete scheduled for 1:00 PM. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
BLD-Footing10/7/201410/8/201410/8/2014APART
DetailsMike Jordan
Concrete is scheduled for 12 PM. Would prefer around 10 AM Phone #: ###-#### Inspection requested via web by Kevin Honeycutt. Work in progress, will hace special inspection.