BLD-Final | 12/18/2014 | 12/18/2014 | 12/18/2014 | P | PASS |
Mike Jordan
|
|
|
Jake Phone #: ###-####
|
DOC - Permit Finaled | 12/18/2014 | 12/18/2014 | 12/18/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 10/23/2014 | 10/24/2014 | 10/24/2014 | P | PART |
Mike Jordan
|
|
|
Jake Phone #: ###-####. ok to open, per frank with CDHD, an inspection is not required due to kitchen was not remodeled. Still needs zonong sign off, inspection is on monday per contractor. All other trades are finaled off, all life/safety is passed. Ok to open this weekend. Contractor will need to follow up for cert. of completion once zoning has finaled.
|
FIRE-Final Inspection | 10/24/2014 | 10/24/2014 | 10/24/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 10/23/2014 | 10/24/2014 | 10/24/2014 | A | FAIL |
Troy Cobbley
|
|
|
Provide correct occupant load signs and exit discharge lighting as per the approval note number 3. All other items appear ok.
|
BLD-Framing/Rough-in | 10/15/2014 | 10/15/2014 | 10/15/2014 | P | PART |
Mike Jordan
|
|
|
Jake Phone #: ###-####.
|
BLD-Framing/Rough-in | 10/8/2014 | 10/9/2014 | 10/9/2014 | A | PART |
Jim Sly
|
|
|
Jake Phone #: ###-#### Exterior and Window infill.....OK.
|