BLD-Final | 10/26/2015 | 10/27/2015 | 10/27/2015 | A | PASS |
Jim Sly
|
|
|
Tyler Phone #: ###-#### OK for perm ok occ.
|
BLD-Final | 10/19/2015 | 10/19/2015 | 10/19/2015 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand OK for Temp Occ. OK for Perm when Zoning signs off........Bond.
|
FIRE-Final Inspection | 10/19/2015 | 10/19/2015 | 10/19/2015 | P | PASS |
Troy Cobbley
|
|
|
Life Safety Passed
|
FIRE-Final Inspection | 10/15/2015 | 10/16/2015 | 10/16/2015 | A | FAIL |
Troy Cobbley
|
|
|
Missing sprinkler canopy (shipping cap still in place) in the upstairs ADA bathroom
|
BLD-Final | 10/15/2015 | 10/16/2015 | 10/16/2015 | P | NR |
Mike Jordan
|
|
|
Tyler Phone #: ###-####
|
BLD-Energy code compliance | 8/26/2015 | 8/27/2015 | 8/27/2015 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
|
BLD-Framing/Rough-in | 8/25/2015 | 8/26/2015 | 8/26/2015 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
|
BLD-Wall Bracing | 8/4/2015 | 8/4/2015 | 8/4/2015 | P | PASS |
Jim Sly
|
|
|
ext shear Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
|
BLD-Wall Bracing | 7/13/2015 | 7/13/2015 | 7/15/2015 | P | PASS |
Jim Sly
|
|
|
2nd floor int shear Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
|
BLD-Wall Bracing | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | PART |
Jim Sly
|
|
|
first floor interior shear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
|
BLD-Energy code compliance | 6/8/2015 | 6/8/2015 | 6/8/2015 | P | PASS |
Jim Storey
|
|
|
Rob Phone #: ###-#### foam at stem wall.
|
BLD-Foundation | 6/4/2015 | 6/5/2015 | 6/5/2015 | A | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 6/4/2015 | 6/4/2015 | 6/4/2015 | P | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|