BLD-Conference | 2/19/2016 | 2/19/2016 | 2/19/2016 | P | DONE |
Jim Sly
|
|
|
|
BLD-Aging Inspection | 2/12/2016 | 2/12/2016 | 2/19/2016 | | CANC |
Jim Sly
|
|
|
|
BLD-Final | 2/17/2016 | 2/17/2016 | 2/17/2016 | P | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 2/17/2016 | 2/17/2016 | 2/17/2016 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 9/30/2015 | 9/30/2015 | 9/30/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Framing/Rough-in | 6/15/2015 | 6/16/2015 | 6/16/2015 | A | PASS |
Jim Sly
|
|
|
Dave Phone #: ###-#### Minor Changes on Exterior Canopys addressed and approved by Structural Engineer of record per letter of approval.......archived with plan.
|
BLD-Conference | 3/24/2015 | 3/30/2015 | 3/30/2015 | A | DONE |
Jim Sly
|
|
|
Bill- 11am please Phone #: ###-#### Met with Engineer tyo check out heavy timber exterior canopys.
|
BLD-Framing/Rough-in | 1/28/2015 | 1/30/2015 | 1/30/2015 | P | PART |
Jim Sly
|
|
|
Dave Phone #: ###-####-meet time 1:00 Appears OK .........but waiting for special inspection.
|
BLD-Foundation | 12/2/2014 | 12/3/2014 | 12/3/2014 | P | PART |
Jim Sly
|
|
|
rebar//dave Phone #: ###-#### Part to all of the slab OK pending MTI special insp, tests and approvals.
|
BLD-Footing | 10/9/2014 | 10/9/2014 | 10/10/2014 | P | PASS |
Jim Sly
|
|
|
Dave Phone #: ###-#### should be Found. insp. Found. OK pending MTI special insp, tests and approvals.
|
BLD-Footing | 10/1/2014 | 10/2/2014 | 10/2/2014 | A | PASS |
Jim Sly
|
|
|
Bill// pour time around 10am Phone #: ###-#### OK pending MTI special insp, tests and approvals.
|
BLD-Footing | 9/30/2014 | 10/1/2014 | 10/1/2014 | P | CANC |
Jim Sly
|
|
|
Bill//pour time is two Phone #: ###-####
|