BLD-Final | 5/16/2016 | 5/17/2016 | 5/17/2016 | A | PASS |
Jim Sly
|
|
|
Call for any questions - brandon Phone #: ###-#### Inspection requested via web by Brandon Juarez OK for Perm Occ.
|
FIRE-Final Inspection | 5/12/2016 | 5/13/2016 | 5/13/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 5/11/2016 | 5/12/2016 | 5/12/2016 | A | FAIL |
Troy Cobbley
|
|
|
I performed a quick inspection with contractor but he did not have the city approved plans on site. I rescheduled for tomorrow morning to give him time
|
FIRE-Final Inspection | 5/11/2016 | 5/11/2016 | 5/11/2016 | P | CANC |
Troy Cobbley
|
|
|
Inspection requested via web by Brandon Juarez
|
BLD-Aging Inspection | 12/25/2015 | 12/25/2015 | 12/29/2015 | | CANC |
Jim Sly
|
|
|
|
BLD-Final | 12/28/2015 | 12/28/2015 | 12/29/2015 | P | NR |
Jim Sly
|
|
|
WIP
|
BLD-Other | 11/13/2015 | 11/13/2015 | 11/13/2015 | P | DONE |
Jim Sly
|
|
|
Need occupancy review for phase 2.1,2.2,2.3.
Phone #: ###-#### Inspection requested via web by Brandon Juarez
|
BLD-Framing/Rough-in | 8/13/2015 | 8/13/2015 | 8/13/2015 | A | PART |
Jim Sly
|
|
|
Phase 2.1 framing rough in. Need ok to cover. Phone #: ###-#### Inspection requested via web by Brandon Juarez
|
BLD-Other | 5/30/2015 | 6/1/2015 | 6/1/2015 | A | PASS |
Jim Sly
|
|
|
Phase 1 final walk through. please call me to meet on site. thank you Brandon Phone #: ###-#### Inspection requested via web by Brandon Juarez Troy signed off phase 1 phase 1 OK to occupy as shown on plans.
|
FIRE-Final Inspection | 5/29/2015 | 5/29/2015 | 5/29/2015 | P | PART |
Troy Cobbley
|
|
|
Phase 1 life safety passed. See the city approved plans for location.
|
FIRE-Conference | 5/19/2015 | 5/20/2015 | 5/21/2015 | A | PASS |
Troy Cobbley
|
|
|
Discussed fire life safety items with contractor.
|
BLD-Conference | 3/12/2015 | 3/12/2015 | 3/12/2015 | P | PART |
Jim Sly
|
|
|
Framing inspection prior to cover. Enter through rear door (lockbox code 8059) Phone #: ###-#### Inspection requested via web by Brandon Juarez North 3rd of phased project .........framing OK.
|