BLD-Final | 4/29/2015 | 4/29/2015 | 4/29/2015 | P | PASS |
Mike Jordan
|
|
|
Ok for perm occ.
|
BLD-Final | 4/21/2015 | 4/21/2015 | 4/21/2015 | P | PART |
Mike Jordan
|
|
|
Greg Phone #: ###-####. Ok for temp occ. Will be ok for perm occ. once zoning signs perm.
|
BLD-Final | 4/20/2015 | 4/20/2015 | 4/20/2015 | P | NR |
Mike Jordan
|
|
|
Greg Phone #: ###-####. Work in progress.
|
BLD-Final | 4/17/2015 | 4/17/2015 | 4/17/2015 | P | FAIL |
Mike Jordan
|
|
|
Craig Phone #: ###-####. Provide additional handrail at ramp, provide handrail extensions at stairs, provide handrail at east exit.
|
FIRE-Final Inspection | 4/13/2015 | 4/14/2015 | 4/14/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 4/9/2015 | 4/10/2015 | 4/10/2015 | P | NR |
Mike Jordan
|
|
|
Greg Phone #: ###-####. Fire/life/safety failed.
|
FIRE-Final Inspection | 4/9/2015 | 4/10/2015 | 4/10/2015 | A | FAIL |
Troy Cobbley
|
|
|
Provide ADA compliant single action hardware on all doors. Remove dead bolts. Provide signage on Electrical Room door. Provide exit sign/emergency light at the bottom of the stairs. Fire dept. access is acceptable per Scott.
|
BLD-Framing/Rough-in | 3/4/2015 | 3/4/2015 | 3/4/2015 | P | PASS |
Dave Hannah
|
|
|
Greg-would like as early as possible Phone #: ###-####
|
BLD-Framing/Rough-in | 2/26/2015 | 2/26/2015 | 2/26/2015 | P | NR |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Needs electrical rough in inspection.
|