BLD-Final | 6/29/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Mike Jordan
|
|
|
Rich Phone #: ###-####
|
FIRE-Final Inspection | 6/29/2015 | 6/29/2015 | 6/29/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide occupant load sign prior to a building sign off.
|
BLD-Ceiling Grid Inspection | 6/18/2015 | 6/19/2015 | 6/19/2015 | A | PART |
Mike Jordan
|
|
|
Early as possible // Rich Phone #: ###-####. Pending electrical rough in inspection.
|
BLD-Framing/Rough-in | 6/5/2015 | 6/8/2015 | 6/8/2015 | A | PASS |
Mike Jordan
|
|
|
Shawn Phone #: ###-####. Remainder of parapet ok to cover. Inertior wood framed walls for janitors closet.
|
BLD-Framing/Rough-in | 6/2/2015 | 6/5/2015 | 6/5/2015 | A | PASS |
Mike Jordan
|
|
|
Rich Phone #: ###-####. Reviewed RFI and reinspected SW exterior facade wall. Ok to insulate. Also inspected reinstallation of existing insulation at parapet. Work in progress on west parapet.
|
BLD-Framing/Rough-in | 6/2/2015 | 6/4/2015 | 6/4/2015 | A | PART |
Mike Jordan
|
|
|
Rich Phone #: ###-####. South West exterior wall facade will require RFI from engineer
|
BLD-Framing/Rough-in | 6/2/2015 | 6/3/2015 | 6/3/2015 | A | PASS |
Mike Jordan
|
|
|
Rich Phone #: ###-####. North and south mansard construction. Work in progress.
|