BLD-Final | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
Jim Sly
|
|
|
Andy-please call with an approx meet time Phone #: ###-####
|
DOC - Permit Finaled | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Conference | 9/5/2018 | 9/6/2018 | 9/6/2018 | A | DONE |
Jim Sly
|
|
|
Requests phone call prior to access - Andrew Phone #: ###-#### WIP
|
BLD-Conference | 4/9/2018 | 4/10/2018 | 4/10/2018 | A | DONE |
Jim Sly
|
|
|
Andy Phone #: ###-#### Andy is working on Exterior......Slow progress...WIP
|
BLD-Conference | 9/7/2017 | 9/7/2017 | 9/7/2017 | P | DONE |
Jim Sly
|
|
|
Andy Phone #: ###-#### WIP
|
BLD - Request for Extension | 4/6/2017 | 4/7/2017 | 4/7/2017 | A | DONE |
Jim Sly
|
|
|
Andrew Phone #: ###-#### WIP
|
BLD-Conference | 9/8/2016 | 9/8/2016 | 9/8/2016 | P | DONE |
Jim Sly
|
|
|
Andy Phone #: ###-#### WIP
|
BLD-Final | 3/9/2016 | 4/29/2016 | 4/29/2016 | A | NR |
Jim Sly
|
|
|
WIP
|
BLD-Final | 4/6/2016 | 4/6/2016 | 4/6/2016 | P | NR |
Jim Sly
|
|
|
Andy ###-#### Need Driveway Completed.
|
BLD-Final | 4/5/2016 | 4/6/2016 | 4/6/2016 | A | CANC |
Jim Sly
|
|
|
Andy Phone #: ###-####
|
BLD-Aging Inspection | 3/10/2016 | 3/10/2016 | 3/16/2016 | | CANC |
Jim Sly
|
|
|
|
BLD-Aging Inspection | 3/9/2016 | 3/9/2016 | 3/9/2016 | | CANC |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 10/26/2015 | 10/27/2015 | 10/27/2015 | A | PASS |
Jim Sly
|
|
|
Andy Phone #: ###-####
|
BLD-Framing/Rough-in | 10/26/2015 | 10/26/2015 | 10/27/2015 | P | PASS |
Jim Sly
|
|
|
Andy Phone #: ###-####
|
BLD-Conference | 8/31/2015 | 9/1/2015 | 9/1/2015 | A | DONE |
Jim Sly
|
|
|
Andy ###-#### About Wall bracing. Plans show no Brace panels ........will have to add some to interior.
|
BLD-Foundation | 8/31/2015 | 8/31/2015 | 8/31/2015 | P | PASS |
Jim Sly
|
|
|
Andy Phone #: ###-####
|
BLD-Footing | 8/10/2015 | 8/11/2015 | 8/11/2015 | P | PASS |
Jim Sly
|
|
|
Andy Phone #: ###-####
|