BLD-Final | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | PASS |
Mike Jordan
|
|
|
as per Jim Wylie all flood plain conditions have been met
|
DOC - Permit Finaled | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 1/4/2016 | 1/4/2016 | 1/4/2016 | P | PASS |
Mike Jordan
|
|
|
Taff Phone #: ###-####
|
BLD-Energy code compliance | 1/4/2016 | 1/4/2016 | 1/4/2016 | P | PASS |
Mike Jordan
|
|
|
Taff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/30/2015 | 12/30/2015 | 12/30/2015 | P | FAIL |
Jim Storey
|
|
|
Pat Phone #: ###-#### n2 hr wall/ holes in roof 4 ft of wall// gyp instaled to roof deck at overbuildes
|
BLD-Framing/Rough-in | 12/24/2015 | 12/28/2015 | 12/28/2015 | P | FAIL |
Mike Jordan
|
|
|
Framer will leave the truss engineering with plans at the fireplace. If you find any truss engineering needing fixed, the framer is two doors down framing on the next townhome. Please let them know as I will be out of town. Thx. Phone #: ###-#### Inspection requested via web by Scott Zierler. INstall missing sheetrock on 2hr. wall. 2hr. fire wall to be continous to upper roof deck in garage.
|
BLD-Framing/Rough-in | 12/22/2015 | 12/24/2015 | 12/24/2015 | A | FAIL |
Dave Hannah
|
|
|
Plans will be above the fireplace. Thanks Mike! Scott Phone #: ###-#### Inspection requested via web by Scott Zierler c/n on site needs truss engin on site and fireplace rough in
|
BLD-Wall Bracing | 11/12/2015 | 11/12/2015 | 11/12/2015 | P | PASS |
Mike Jordan
|
|
|
Scott Phone #: ###-####
|
BLD-Other | 10/15/2015 | 10/16/2015 | 10/16/2015 | P | PASS |
Mike Jordan
|
|
|
Fire wall // Scott Phone #: ###-####
|
BLD-Footing | 6/9/2015 | 6/9/2015 | 6/9/2015 | P | PART |
Mike Jordan
|
|
|
Heron Phone #: ###-####
|