BLD-Final | 3/22/2017 | 3/23/2017 | 3/23/2017 | P | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####
|
FIRE-Final Inspection | 3/22/2017 | 3/23/2017 | 3/23/2017 | A | PASS |
Jim Page
|
|
|
Final life fire safety inspection passed/complete
|
BLD-Aging Inspection | 1/31/2017 | 1/31/2017 | 2/1/2017 | | PASS |
Tony Young
|
|
|
|
BLD-Final | 9/23/2016 | 9/26/2016 | 9/26/2016 | A | PART |
Tony Young
|
|
|
ok pending others?
|
FIRE-Final Inspection | 9/26/2016 | 9/26/2016 | 9/26/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are in place, some have current inspection tags, others will be getting tagged by a licensed contractor (will verify current inspection tag during follow up inspection on other builings at jobsite) Knox box is in place, knox caps for FDC/Standpipe are on order and will be installed after received. Final life fire safety inspection for building T passed/complete.
|
BLD-Final | 9/22/2016 | 9/23/2016 | 9/23/2016 | P | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### needs fire life saftey needs elec and change locks ada unit
|
BLD-Footing | 8/29/2016 | 8/30/2016 | 8/30/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,,, tree root footing,, centerpiece,, pend spec insp
|
BLD-Energy code compliance | 6/30/2016 | 7/1/2016 | 7/1/2016 | A | PASS |
Phil Shearer
|
|
|
Ed Phone #: ###-####. 2nd and 3rd floor OK for cover
|
BLD-Energy code compliance | 6/29/2016 | 6/30/2016 | 6/30/2016 | A | PASS |
Jim Sly
|
|
|
Ed// 1st floor Phone #: ###-####
|
BLD-Framing/Rough-in | 6/28/2016 | 6/29/2016 | 6/29/2016 | A | PART |
Tony Young
|
|
|
Ed/// inspection for the 3rd floor Phone #: ###-####,, 3rd floor ok to rock lids and insulate
|
BLD-Framing/Rough-in | 6/27/2016 | 6/28/2016 | 6/28/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, 1st and 2nd floor ceilings ok to cover,, also ok to insulate walls on same
|
BLD-Energy code compliance | 5/27/2016 | 6/1/2016 | 6/1/2016 | A | PART |
Tony Young
|
|
|
Ed// 1st floor Phone #: ###-####,, 1st floor ok
|
BLD-Energy code compliance | 5/26/2016 | 5/27/2016 | 5/27/2016 | A | PEND |
Tony Young
|
|
|
Ed// 4th floor Phone #: ###-####,, pending fire sprinkler pass
|
BLD-Energy code compliance | 5/25/2016 | 5/26/2016 | 5/26/2016 | A | PART |
Tony Young
|
|
|
Ed// 4th floor Phone #: ###-####,, seal pack ok,, frame ok,, need sprinkler full sign off
|
BLD-Framing/Rough-in | 5/20/2016 | 5/23/2016 | 5/23/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,, interior fur outs for trades ok to insulate
|
BLD-Framing/Rough-in | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | DEFR |
Tony Young
|
|
|
Ed Phone #: ###-####,, out of time
|
BLD-Wall Bracing | 4/6/2016 | 4/6/2016 | 4/6/2016 | P | PART |
Jim Sly
|
|
|
Ed Phone #: ###-#### Exterior Nailing and strapping.....OK.
|
BLD-Energy code compliance | 3/31/2016 | 4/1/2016 | 4/1/2016 | A | PART |
Jim Sly
|
|
|
Ed Phone #: ###-#### Plumbing Walls OK 1st floor.
|
BLD-Wall cover | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | PART |
Jim Sly
|
|
|
Shear // Ed Phone #: ###-#### OSB shear nailing at E. to W. Center wall ( Plumbing wall)....Main floor OK.
|
BLD-Other | 3/15/2016 | 3/16/2016 | 3/16/2016 | A | PART |
Tony Young
|
|
|
Nail // Adam Phone #: ###-####,, contractor to verify roof nailing
|
BLD-Footing | 1/28/2016 | 1/29/2016 | 1/29/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Footing | 1/26/2016 | 1/27/2016 | 1/27/2016 | A | PART |
Tony Young
|
|
|
Ed Phone #: ###-####,,, special inspection on site
|