Permit Information
Permit NumberBLD15-01125
StatusFinaled
Name BACH LAND AND DEVELOPMENT LLC
Site Address 7458 W SAXTON DR
Project NameThe Kensington Apartments H
Customer NumberBLD15-01118 - BLD15-01137
ePlanReview 
Description
(THE KENSINGTON APARTMENTS - BUILDING H) The drawings are filed under BLD15-01118 in ePlanReview. The NFPA 13-R fire sprinkler system is used for occupancy and for story increase. To construct a 19,484 square foot four story apartment building (5,189 sq. ft. 1st story with four 2.a units, 5,189 sq. ft. 2nd story with four 2.a units, 5,189 sq. ft. 3rd story with four 2.a units, 3,917 sq. ft. 4th story with four 1.b units). All ground floor units are required to comply as Type B dwelling units. No elevator is provided in this building. Work is to include concrete footings, concrete foundations, concrete slabs on grade, wood stud bearing walls, wood stud shear walls, fiberglass shingles, fiber-cement board siding, manufactured stone veneer, 1-hr dwelling unit separations, .5-hr minimum fire-resistance-rated corridors with 20 minute smoke- and draft-control doors, exterior exit stairways fire rated like the corridor, steel stairways with concrete treads, interior nonbearing walls, millwork, and finishes. Special Inspection is required for soils and for concrete. The roof truss design is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13-R and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection11/9/201711/9/201711/9/2017 PASS
DetailsTony Young
BLD-Aging Inspection11/8/201711/8/201711/9/2017 PASS
DetailsTony Young
BLD-Final6/26/20176/27/20176/27/2017APASS
DetailsTony Young
Ed Phone #: ###-####
BLD-Final6/26/20176/26/20176/27/2017PDEFR
DetailsTony Young
Ed Phone #: ###-####
BLD-Final6/22/20176/23/20176/23/2017PCANC
DetailsJim Storey
Ed Phone #: ###-####
FIRE-Final Inspection6/22/20176/23/20176/23/2017APASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, building has knox box installed. Final life fire safey inspection passed/complete.
BLD-Wall cover4/14/20174/17/20174/16/2017APART
DetailsTony Young
1st floor - Ed Phone #: ###-####,, ok pending mech
BLD-Framing/Rough-in4/13/20174/14/20174/14/2017APART
DetailsTony Young
1st floor - Ed Phone #: ###-####,, energy ok,, just needs to get mech passed,, also firecaulking finished inside door on the 2 east units
BLD-Framing/Rough-in4/11/20174/12/20174/12/2017APART
DetailsTony Young
Ed-2 nd floor Phone #: ###-####,, ok pending trades
BLD-Framing/Rough-in4/10/20174/10/20174/11/2017PPASS
DetailsTony Young
3rd floor; Ed Phone #: ###-####
BLD-Energy code compliance4/7/20174/10/20174/10/2017APART
DetailsTony Young
Floors 1-3 // Ed Phone #: ###-####,, ok pending trades
BLD-Other3/29/20173/30/20173/30/2017PPASS
DetailsTony Young
Ed-fire caulking-1st floor Phone #: ###-####
BLD-Other3/29/20173/30/20173/29/2017APASS
DetailsJim Sly
Ed-fire caulking-2nd floor Phone #: ###-####
BLD-Other3/28/20173/29/20173/29/2017APASS
DetailsTony Young
2nd floor Fire Caulking // Ed Phone #: ###-####
BLD-Other3/27/20173/28/20173/28/2017APASS
DetailsJim Sly
3rd Floor - Fire Caulking; Ed Phone #: ###-####
BLD-Energy code compliance3/27/20173/27/20173/28/2017PPART
DetailsTony Young
Ed-4th floor Phone #: ###-####,, 4th ok
BLD-Other3/24/20173/24/20173/24/2017PPART
DetailsTony Young
4th floor fire caulking; Ed Phone #: ###-####,, 4th floor plate fire caulking ok
BLD-Framing/Rough-in3/22/20173/23/20173/23/2017PPART
DetailsTony Young
4th floor; Ed Phone #: ###-####,, all floors pre-rock areas ok,, pending trades,, firecaulking
BLD-Wall Bracing2/3/20172/6/20172/6/2017APART
DetailsTony Young
Interior sheathing, hold downs - Ed Phone #: ###-####,, interior plumbing walls,,( interior shear and insulation ok)
BLD-Wall Bracing12/22/201612/23/201612/23/2016APART
DetailsTony Young
Shear // Ed Phone #: ###-####,, exterior shear ok after minor fixes and removing shiner nails
BLD-Concrete8/31/20169/1/20169/1/2016PPASS
DetailsPhil Shearer
Ken Phone #: ###-####
BLD-Footing7/28/20167/29/20167/29/2016APASS
DetailsMike Jordan
Ed Phone #: ###-####