BLD-Final | 9/9/2015 | 9/10/2015 | 9/10/2015 | A | PASS |
Mike Jordan
|
|
|
Karen Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 9/3/2015 | 9/9/2015 | 9/9/2015 | P | NR |
Jim Sly
|
|
|
Karen Phone #: ###-#### Need Verification that CDHD is OK for Occ. I verified that Plumbing is OK ......Note....Electr. at this point is a Part .....but OK to Occupy interior.
|
FIRE-Final Inspection | 9/4/2015 | 9/9/2015 | 9/9/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Previously listed items corrected
|
BLD-Conference | 9/3/2015 | 9/4/2015 | 9/4/2015 | P | DONE |
Mike Jordan
|
|
|
Spoke with owner regaurding what finals they have left to get occupancy.
|
FIRE-Final Inspection | 9/3/2015 | 9/4/2015 | 9/4/2015 | A | PART |
Jim Page
|
|
|
Life fire safety partially complete, interior emergency egress lighting installed but the discharge landings do not have egress lighting, another inspection will be scheduled when exterior egress lighting installed. All other life fire safety items inspected, passed/complete.
|
BLD-Conference | 8/6/2015 | 8/6/2015 | 8/6/2015 | P | FAIL |
Mike Jordan
|
|
|
Randy Phone #: ###-####. A correction noticw was issued to provide code compliant ramps and ladings in acordance with the approved plans.
|
FIRE-Final Inspection | 7/6/2015 | 7/9/2015 | 7/9/2015 | A | CANC |
Troy Cobbley
|
|
|
I left voice messafe for Lance Phone #: ###-#### letting him know that I need to have the project related fire alarm permits finaled prior to a fire life safety inspection/sign off. I noted that door hardware was incorrect/missing, doors missing and fire extinguishers missing. I also spoke to his wife briefly on site about the same issues.
|
BLD-Framing/Rough-in | 6/4/2015 | 6/5/2015 | 6/5/2015 | P | PART |
Mike Jordan
|
|
|
Lance Phone #: ###-####. ok pending elec. rough in inspection.
|