BLD-Final | 11/16/2016 | 11/16/2016 | 11/16/2016 | A | PASS |
Dave Hannah
|
|
|
Ok for permanent occupancy once bond posted
|
FIRE-Final Inspection | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PASS |
Jim Page
|
|
|
|
BLD-Aging Inspection | 10/3/2016 | 10/3/2016 | 10/3/2016 | | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 8/2/2016 | 8/3/2016 | 8/3/2016 | A | PART |
Jim Page
|
|
|
Partial life fire safety inspection passed/complete. Fire alarm inspections for levels 2 and 3 complete, fire sprinkler inspections for levels 2 and 3 complete, pre-action fire sprinkler inspection for server room on level 3 complete, clean agent fire suppression system for server room on level 3 complete, fire extinguishers are in place with current inspection tags on levels 2 and 3. Final life fire safety inspection for levels 2 and 3 complete.
|
BLD-Ceiling Grid Inspection | 7/28/2016 | 7/28/2016 | 7/29/2016 | P | PASS |
Dave Hannah
|
|
|
ok to cover 2nd and 3rd floors
|
BLD-Ceiling Grid Inspection | 7/22/2016 | 7/22/2016 | 7/27/2016 | P | PART |
Dave Hannah
|
|
|
floors 6and 7
|
BLD-Wall cover | 3/14/2016 | 3/14/2016 | 3/16/2016 | P | PEND |
Dave Hannah
|
|
|
BSU TI, confirm fire assemblies at interior columns, working toward TI 2 side cover. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 3/4/2016 | 3/4/2016 | 3/7/2016 | P | PART |
Dave Hannah
|
|
|
BSU TI, Ongoing Framing inspection, Documentation update to Permit Binder. Week inspection follow up. Concurrent with Shell and Core walks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson int wall ok to cover see singoff sheets in office
|