Information based on query as of Wednesday, June 19, 2024.
Permit Information
Permit NumberBLD15-01585
StatusFinaled
Name EVERYTHING UNDER THE ROOF CONSTRUCT
Site Address 2470 W BOISE AVE
Project NameBoise Hare Krishna Temple &...
Customer Number 
ePlanReviewYes
Description
(BOISE HARE KRISHNA TEMPLE AND VEDIC CULTURAL CENTER) Permit is to construct a 3,876 square foot religious assembly building. PLAN MODIFICATION - Modification approved to add additional plumbing / reverse direction of a ramp / clarify doors needing panic hardware / other minor changes. 2-19-16 **TLW** This building is constructed as a wood frame building and a concrete footing. Work includes: new foundation, new exterior walls, new mechanical, new plumbing, site work, new wood frame exterior walls, new manufactured wood truss roof system, new electrical, new accessible doors / hardware, new employee kitchen (refer to owners explanation of use letter), and interior finishes in accordance with Chapter 8 of the 2012 IBC. This building is not fire sprinklered. NOTE: additional energy code package of Lighting was selected and compliance was demonstrated. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/7/201611/8/201611/8/2016APASS
DetailsJim Storey
Nate ###-####-
BLD-Aging Inspection9/12/20169/12/20169/12/2016 PASS
DetailsJim Storey
BLD-Aging Inspection7/13/20167/13/20167/13/2016 PASS
DetailsJim Storey
BLD-Final5/13/20165/13/20165/13/2016PPART
DetailsJim Storey
Nate Phone #: ###-####temp
FIRE-Final Inspection5/12/20165/13/20165/13/2016APASS
DetailsJim Page
Previously noted items addressed/repaired. No fire sprinklers, smoke detectors are stand alone and not associated with an FIR permit, fire extinguishers are in place with current inspections tags, verified with mechanical inspector that the commercial hood in kitchen area is a Type 2 hood, does not require hood suppression. Final life fire safety inspection passed/complete.
BLD-Final5/12/20165/13/20165/13/2016ANR
DetailsJim Sly
Nate Phone #: ###-####
NR.....Verify ACHD signed off. Need Public works and Zoning finals.
FIRE-Final Inspection5/9/20165/10/20165/10/2016AFAIL
DetailsJim Page
Small documentation was not attached to the city approved drawings, fire plan review small documentation needs to be with city approved drawings before next inspection. No knox box installed, knox box needs to ordered/installed before final inspection. No exit discharge emergency egress lighting installed at time of inspection, exit discharge emergency egress lighting will need to be installed before final inspection. Addressing needs to be installed on the exterior of building.
BLD-Wall cover3/1/20163/2/20163/2/2016APASS
DetailsJim Storey
ceilling
BLD-Energy code compliance3/1/20163/1/20163/1/2016APASS
DetailsJim Storey
BLD-Energy code compliance2/29/20163/1/20163/1/2016ADONE
DetailsJim Storey
Nate Phone #: ###-####
BLD-Framing/Rough-in2/23/20162/23/20162/23/2016PPART
DetailsJim Storey
Brian Phone #: ###-#### pic of gyp on soffit
BLD-Framing/Rough-in2/17/20162/18/20162/18/2016APART
DetailsJim Storey
Brian Phone #: ###-####
BLD-Framing/Rough-in2/17/20162/17/20162/17/2016PFAIL
DetailsJim Storey
Brian Phone #: ###-#### arch to address soffit prorection changed w/o review/need fan protection/canlight protection. need plm insp ok to insulate upon aproval from plm
BLD-Wall Bracing1/6/20161/7/20161/7/2016PPASS
DetailsPhil Shearer
Brian Phone #: ###-####. Exterior only OK to wrap.
BLD-Foundation10/26/201510/26/201510/26/2015PPASS
DetailsJim Storey
early as possible//Rebar insp. Phone #: ###-####
BLD-Footing10/13/201510/13/201510/13/2015PPASS
DetailsJim Storey
Nate Phone #: ###-####