BLD-Final | 11/16/2016 | 11/16/2016 | 11/16/2016 | A | PASS |
Dave Hannah
|
|
|
Ok for permanent occupancy once bond is posted.
|
FIRE-Final Inspection | 11/14/2016 | 11/14/2016 | 11/14/2016 | P | PASS |
Jim Page
|
|
|
Final inspection complete
|
BLD-Final | 10/10/2016 | 10/10/2016 | 10/11/2016 | P | PART |
Dave Hannah
|
|
|
On track for temp C of O for VRT TI. Call Adam when on site. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for tco
|
FIRE-Final Inspection | 10/10/2016 | 10/10/2016 | 10/10/2016 | P | PART |
Jim Page
|
|
|
Partial final for life fire safety inspection complete, final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Partial final inspection for VRT complete, permit will not be finaled until core and shell for city center plaza is completed. VRT can be finaled for life fire safety pending core and shell permit completion.
|
BLD-Final | 10/7/2016 | 10/7/2016 | 10/10/2016 | P | PEND |
Dave Hannah
|
|
|
Mechanical final will be performed in the am, seeking C of O allowing tenat to set up for occupancy. Call adam when on site. Thanks akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
FIRE-Final Inspection | 10/7/2016 | 10/7/2016 | 10/7/2016 | P | CANC |
Jim Page
|
|
|
Inspection request is going to be rescheduled per conversation with point of contact, Adam phone number ###-####
|
BLD-Final | 9/29/2016 | 9/29/2016 | 9/30/2016 | P | PART |
Dave Hannah
|
|
|
Per recap from yesterdays walk thru, review and sign card for approval on temp use for testing and training. Call Adam when on site. Thanks AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson ok for training
|
FIRE-Final Inspection | 9/29/2016 | 9/29/2016 | 9/29/2016 | P | PART |
Jim Page
|
|
|
Partial final life fire safety inspection complete, fire sprinklers are complete with exception to various escutcheons, fire alarm inspection is complete, fire extinguishers are in place with current inspection tags.
|
BLD-Final | 9/27/2016 | 9/28/2016 | 9/29/2016 | P | CANC |
Dave Hannah
|
|
|
Requesting inspection to review VRT TI space. Call Adam when on site. ###-####. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
|
FIRE-Conference | 9/28/2016 | 9/28/2016 | 9/28/2016 | P | DONE |
Jim Page
|
|
|
Fire conference complete, items needed for life fire safety inspection reviewed.
|
FIRE-Final Inspection | 9/27/2016 | 9/28/2016 | 9/28/2016 | P | CANC |
Jim Page
|
|
|
Inspection request was for a fire conference, project is not ready for life fire safety final.
|
BLD-Ceiling Grid Inspection | 9/12/2016 | 9/12/2016 | 9/13/2016 | P | PASS |
Dave Hannah
|
|
|
Begin inspections of OH ceilings, west side, north drive isle, and stair vestibule and ticket areas. Please call Adam when heading to site. Thanks AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Conference | 9/9/2016 | 9/9/2016 | 9/12/2016 | P | PEND |
Dave Hannah
|
|
|
Adam Phone #: ###-####
|
BLD-Framing/Rough-in | 8/22/2016 | 8/22/2016 | 8/22/2016 | A | PASS |
Dave Hannah
|
|
|
Restroom. Hard lid framing approve for cover. Call Adam when on site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PART |
Dave Hannah
|
|
|
Interior VRT TI Wall Rough ins complete, electrical signed off. Ready for framing inspection. akj 7/20/16 AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson ok to cover walls
|