BLD-Final | 10/28/2015 | 10/28/2015 | 10/28/2015 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 10/28/2015 | 10/28/2015 | 10/28/2015 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 10/27/2015 | 10/28/2015 | 10/28/2015 | A | FAIL |
Mike Jordan
|
|
|
Robert Phone #: ###-####. Provide the blower dorr test result or the 3rd party airseal inspection report and post. Correction notice issued.
|
BLD-Energy code compliance | 9/15/2015 | 9/15/2015 | 9/15/2015 | P | PASS |
Mike Jordan
|
|
|
Robert Phone #: ###-####
|
BLD-Framing/Rough-in | 9/11/2015 | 9/11/2015 | 9/11/2015 | P | PASS |
Mike Jordan
|
|
|
Robert Phone #: ###-####
|
BLD-Wall Bracing | 8/31/2015 | 9/1/2015 | 9/1/2015 | P | PASS |
Mike Jordan
|
|
|
Robert Phone #: ###-####. Wall bracing on detached garage ok.
|
BLD-Conference | 8/27/2015 | 8/28/2015 | 8/28/2015 | A | CANC |
Mike Jordan
|
|
|
Robert Phone #: ###-####
|
BLD-Wall Bracing | 8/28/2015 | 8/28/2015 | 8/28/2015 | A | PASS |
Mike Jordan
|
|
|
Robert Phone #: ###-####
|
BLD-Foundation | 7/31/2015 | 7/31/2015 | 7/31/2015 | P | PART |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. Work in progress.
|
BLD-Conference | 7/29/2015 | 7/29/2015 | 7/30/2015 | P | PASS |
Mike Jordan
|
|
|
Received soils test report. Structural fill has been tested and passed. Ok for concrete.
|
BLD-Footing | 7/29/2015 | 7/29/2015 | 7/29/2015 | A | PART |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. Footings ok. Noted that approx. 1ft. of sandy gravel was placed and compacted. Will be ok for concrete once the fill has been tested and passed and report emailed showing passing results.
|
BLD-Footing | 7/28/2015 | 7/28/2015 | 7/28/2015 | P | NR |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. No one on site, no forms erected.
|