Permit Information
Permit NumberBLD15-02346
StatusIssued
Name ESI
Site Address 1111 W JEFFERSON ST Unit: 500
Project NamePerkins Coie
Customer Number 
ePlanReviewYes
Description
(PERKINS COIE)(SUITE 500) PLAN MODIFICATION FOR RFI#0051, DOOR TO TENANTS SPACE FROM ATRUIM, DOOR MUST FUNCTION AS INDICATED ON EXISTING UPGRADE DATED 1/31/06. **AJS**This building is fire sprinklered to meet high rise provisions. Permit to renovate an existing tenant space located to the south of the 5th floor. Scope of work to include; relocation of tenant separation walls, lighting fixture upgrades, plumbing fixture modifications, and furnishings replacement. See engineering structural calculations for new partition wall on existing structural column. Construction of nonbearing interior walls to create new office lay out with accessory multipurpose room of 1,056 sq ft. The upgrade to the fire spinkler system was completed in 2011. The 2 hour exit enclosures will not be altered as part of this permit. Access to the two exit enclosures shown within tenant area shall be available at all times to the entire floor. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection1/18/20171/18/20171/20/2017 PASS
DetailsTony Young
BLD-Aging Inspection9/2/20169/2/20169/6/2016 PASS
DetailsTony Young
BLD-Final4/21/20164/21/20164/21/2016PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Mike Beeson
FIRE-Final Inspection4/20/20164/21/20164/21/2016PPASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
BLD-Ceiling Grid Inspection3/24/20163/25/20163/25/2016PPEND
DetailsTony Young
Call James Prewett once you get onsite to meet on 5th floor. @ ###-#### Phone #: ###-#### Inspection requested via web by Mike Beeson,, ceiling grid in the storage area ok pending trades
BLD-Framing/Rough-in3/22/20163/22/20163/22/2016PPART
DetailsTony Young
Mike Phone #: ###-####,, 3 walls ok to cover,, phase 3
BLD-Final3/21/20163/22/20163/22/2016PPART
DetailsTony Young
Mike Phone #: ###-####,, ok to use kitchen area in phase 2,, also break room
BLD-Framing/Rough-in3/21/20163/22/20163/22/2016ACANC
DetailsDave Hannah
Mike Phone #: ###-####
BLD-Conference3/21/20163/21/20163/21/2016PDEFR
DetailsTony Young
Mike- phase 2 Phone #: ###-####
FIRE-Final Inspection3/21/20163/21/20163/21/2016PPART
DetailsJim Page
FIre sprinkler inspection complete for phase 2, fire alarm inspection complete for phase 2, fire extinguishers for phase two are in place with current inspection tages. Life fire safety complete for phase 2, area of work will be complete when phase 3 is finshed, life fire safety will be completed at that time.
FIRE-Final Inspection3/17/20163/18/20163/18/2016ACANC
DetailsJim Page
Inspection request cancelled per conversation with Mike, phone number ###-####, will reschedule inspection request for later date.
BLD-Conference3/17/20163/17/20163/17/2016PPART
DetailsTony Young
Mike Phone #: ###-####,, ?s
BLD-Conference3/10/20163/10/20163/10/2016PPASS
DetailsJim Storey
Ceiling grid inspection request. Mechanical, electrical and fire inspections are set up for the morning of 3/10. looking to drop ceiling tiles tomorrow Phone #: ###-#### Inspection requested via web by Mike Beeson ceilling ok to cover pending ele.
BLD-Wall cover2/23/20162/24/20162/24/2016APART
DetailsTony Young
Please call 45 min prior to visit, as we start our shift at 5pm and i will need 45 min heads up to meet the inspector if before 4:30pm. Also, we are just looking at the soffit framing. Electrical and fire have been approved and HVAC is set for inspection tomorrow morning. Phone #: ###-#### Inspection requested via web by Mike Beeson,,// soffits ok
BLD-Framing/Rough-in2/22/20162/23/20162/23/2016PPART
DetailsTony Young
Please call 45 min prior to visit, as we start our shift at 5pm and i will need 45 min heads up to meet the inspector if before 4:30pm. Also, we are just looking at the soffit framing. Electrical and fire have been approved and HVAC is set for inspection tomorrow morning. Phone #: ###-#### Inspection requested via web by Mike Beeson,, soffits ok pending trades
BLD-Framing/Rough-in2/15/20162/16/20162/16/2016PPART
DetailsTony Young
Please contact Mike 45mins to 1hr prior to arrival of at all possible to ensure site access. ###-####
Thank you. Phone #: ###-#### Inspection requested via web by Chris Palmer,, walls ok
BLD-Final1/22/20161/25/20161/25/2016AFAIL
DetailsDave Hannah
Phase I bldg. final inspection. Please contact Mike Beeson for access to the site. Thank you. Phone #: ###-#### Inspection requested via web by Chris Palmer locking door hardwear not to code
BLD-Conference1/20/20161/21/20161/21/2016APASS
DetailsTony Young
Please contact Mike Beeson 30min to 1 hour prior to arrival if at all possible to ensure someone will be onsite to meet.

Thank you! Phone #: ###-#### Inspection requested via web by Chris Palmer,, ?s on final
FIRE-Final Inspection1/18/20161/19/20161/19/2016APART
DetailsJim Page
Project being worked in phases, phase 1 fire alarm inspection complete, phase 1 fire sprinkler inspection complete. Life fire safety passed/complete for phase 1, notated city approved drawings with red ink inspected, made note next to Area 1 Box for life fire safety.
BLD-Ceiling Grid Inspection12/22/201512/23/201512/23/2015APART
DetailsTony Young
Ceiling grid inspection for phase I area. Will have Superintendent Mike Beeson onsite to walk between 7:00am and 11:30am. Please call Mike at ###-#### for access into the space.
Thanks! Phone #: ###-#### Inspection requested via web by Chris Palmer,, phase 1,, ok pending trades
BLD-Framing/Rough-in11/17/201511/17/201511/17/2015PPART
DetailsTony Young
This project is operating during the night hours, if at all possible, please make it last stop of the day. I can be onsite between 4:00 and 4:30pm. If able to call an hour in advance, I can be sure to be onsite to walk with you.
Thank You! Phone #: ###-#### Inspection requested via web by Chris Palmer,, ceilings ok pending other trades
BLD-Framing/Rough-in10/29/201510/29/201510/30/2015PPASS
DetailsDave Hannah
Balance of the wall framing inspection for the pipe penetrations through the floor in the walls. Material spec information is onsite. Access to the site is provided through the Perkins-Coie reception desk. Please call me when onsite.
Thanks! Phone #: ###-#### Inspection requested via web by Chris Palmer
BLD-Framing/Rough-in10/26/201510/27/201510/28/2015PPART
DetailsDave Hannah
This project is operating during the night hours. If at all possible, a late in the day inspection is preferable. Please contact me an hour prior to inspection if at all possible so that I may meet onsite for access and inspection.
Thank you, Chris Palmer. Phone #: ###-#### Inspection requested via web by Chris Palmer phase one ok to one side needs to fire holes in floor