Permit Information
Permit NumberBLD15-04191
StatusFinaled
Name HC COMPANY INC
Site Address 400 S BROADWAY AVE
Project NameSt Luke's in MK Plaza I
Customer Number 
ePlanReviewYes
Description
(ST. LUKE'S)(MK PLAZA I - ENTIRE BUILDING) PLAN MOD 1ST FLOOR OFFICE AND CONFRENCE ROOM LAYOUT WITH IN EXISTING SMOKE CONTROL AREAS AS SHOWN ON APPROVED PLANS. **4-13-16 AJS**PLAN MODIFICATION TO BREAK ROOM DOORS AS NOTED ON REVISED FLOOR PLAN. NO CHANGE TO SMOKE CONTROL ZONES. 3-17-16 AJS*** Special Inspection form attached to drawings. Remodel to entire high-rise building including basement and all 6 floors for new office tenant with some assembly uses per approved plans. Work to include demolition of existing tenant spaces on all floors and build back of new spaces on all floors to include new interior walls, doors, interior finish, new suspended ceilings, electrical work, mechanical work, plumbing work and fire protection equipment. Occupant load request for classrooms on 5th floor approved and attached to case. NOTE: This building is fully fire sprinklered for high-rise and atrium provisions. A smoke management system exists for the atrium. The smoke control system is not being altered under this permit. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/24/20166/27/20166/27/2016PPASS
DetailsDave Hannah
Garry Phone #: ###-####
FIRE-Final Inspection6/24/20166/27/20166/27/2016APASS
DetailsJim Page
Final fire sprinkler inspections complete, final fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
BLD-Final6/22/20166/23/20166/27/2016APART
DetailsDave Hannah
Darin Phone #: ###-####
FIRE-Final Inspection6/23/20166/23/20166/23/2016PPART
DetailsJim Page
Level 1 fire sprinklers complete, level 1 fire alarms complete, level 1 fire extinguishers are in place with current inspection tags. Life fire safety complete for level 1 excluding smoke evacuation system and elevator smoke curtains, when smoke evac and curtians have been inspected/passed then life fire safety can be finaled.
FIRE-Final Inspection6/17/20166/20/20166/20/2016APART
DetailsJim Page
Level 2 fire sprinklers complete, level 2 fire alarms complete, fire extinguishers are in place with cuurent inspection tags for level 2, final life fire safety inspection for level 2 passed/complete.
FIRE-Final Inspection6/16/20166/17/20166/17/2016PCANC
DetailsJim Page
Inspection request will be rescheduled 20June2016 due to medical emergency with the inspector.
BLD-Ceiling Grid Inspection6/15/20166/16/20166/17/2016PPASS
DetailsDave Hannah
Darren Phone #: ###-#### first floor
BLD-Final6/14/20166/15/20166/15/2016APART
DetailsDave Hannah
Please call ahead for access - Darren Phone #: ###-#### walked 3rd and 4th floors ok for occ also 5th and 6th are ok in basement need to change door swing on hallway doors out of class rooms area olso double exit doors out of auditorium need to met ansi 97.1 saftey glassind standerds.
FIRE-Final Inspection6/9/20166/10/20166/10/2016APART
DetailsJim Page
Fire sprinkler inspection complete for basement level, fire alarm inspection complete for basement level, fire extinguishers are in place with current inspection tags for basement level, will verify loading dock mag lock integration to fire alarm system at later date. Final life fire safety inspection for basement level complete excluding mag lock operation and elevator smoke curtians operation.
BLD-Ceiling Grid Inspection6/2/20166/3/20166/3/2016PPASS
DetailsDave Hannah
Garren Phone #: ###-#### second floor
FIRE-Final Inspection6/1/20166/2/20166/2/2016APART
DetailsJim Page
Fire sprinklers complete for level 4, fire alarm complete for level 4, final life fire safety for level 4 complete. Level 3 will be reinspected at later date for fire extinguishers and egress lighting on south side of floor (remaining egress lighting for level 3 tested and passed) Fire sprinklers complete for level 3, alarms will be retested for A/V devices that were disconnected during this inspection.
BLD-Conference6/1/20166/1/20166/1/2016PDONE
DetailsDave Hannah
Darren Phone #: ###-####
BLD-Ceiling Grid Inspection5/24/20165/25/20165/26/2016PPART
DetailsDave Hannah
Darren Phone #: ###-#### basement rooms ok to cover ceilings
FIRE-Final Inspection5/19/20165/20/20165/20/2016APART
DetailsJim Page
Project being worked in phases, fire sprinkler inspections complete for 5th floor and 6th floor, fire alarm inspections complete for 5th floor and 6th floor, fire extinguishers are in place with current inspections tags for 5th and 6th floors. Final life fire safety inspection for 5th and 6th floors passed/complete. Contractor will schedule life fire safety inspections for remaining floors when ready.
BLD-Ceiling Grid Inspection5/9/20165/9/20165/10/2016PPART
DetailsDave Hannah
Darin Phone #: ###-#### hard lids 1st floor ok to cover
BLD-Framing/Rough-in5/4/20165/4/20165/5/2016PPART
DetailsDave Hannah
Darren Phone #: ###-#### 3rd floor ceiling grid ok and restrooms in basement ok to cover
BLD-Ceiling Grid Inspection5/2/20165/2/20165/2/2016PFAIL
DetailsDave Hannah
Darin Phone #: ###-#### needs safty wires on lights
BLD-Ceiling Grid Inspection4/28/20164/28/20164/28/2016PNR
DetailsDave Hannah
Darin Phone #: ###-####
BLD-Framing/Rough-in4/20/20164/20/20164/21/2016PPART
DetailsDave Hannah
Darren Phone #: ###-#### basement walls ok all but for bathrooms
BLD-Ceiling Grid Inspection4/18/20164/19/20164/19/2016APART
DetailsDave Hannah
Daren Phone #: ###-#### ok after other trades sign off
BLD-Framing/Rough-in4/13/20164/13/20164/14/2016PPASS
DetailsDave Hannah
Tucker Phone #: ###-#### first floor wall framing ok
BLD-Framing/Rough-in4/11/20164/12/20164/13/2016PNR
DetailsDave Hannah
Darren Phone #: ###-####
BLD-Ceiling Grid Inspection4/5/20164/5/20164/6/2016APART
DetailsDave Hannah
Darren ###-####- inspection has nothing to do with plan mod 5th floor ok to cover
BLD-Framing/Rough-in4/4/20164/4/20164/5/2016PPART
DetailsDave Hannah
Darin Phone #: ###-#### second fllor hallways hardlids ok
FIRE-Conference3/30/20163/31/20163/31/2016ADONE
DetailsJim Page
Fire conference complete
BLD-Framing/Rough-in3/25/20163/28/20163/29/2016PPART
DetailsDave Hannah
Darren Phone #: ###-#### second floor walls ok to cover
BLD-Framing/Rough-in3/24/20163/25/20163/25/2016APART
DetailsMike Jordan
Darin Phone #: ###-####. 6th floor ceiling grid ok, pending electrical rough in inspection.
BLD-Ceiling Grid Inspection3/18/20163/21/20163/21/2016APART
DetailsDave Hannah
Tucker Phone #: ###-#### hard lid on 3rd floor ok to cover
BLD-Framing/Rough-in3/11/20163/11/20163/14/2016PPART
DetailsDave Hannah
Darren-2 nd & 3rd Phone #: ###-#### 3rd floor ok to cover walls
BLD-Framing/Rough-in3/7/20163/8/20163/8/2016APART
DetailsDave Hannah
Darren Phone #: ###-#### haed lid framing on 4th floor ok also the 3rd floor floor plans need to be resubmitted
BLD-Framing/Rough-in3/2/20163/3/20163/4/2016APART
DetailsDave Hannah
Darren Phone #: ###-#### walls on 4th floor ok to cover
BLD-Framing/Rough-in2/25/20162/26/20162/26/2016APART
DetailsDave Hannah
Darren-please call 30 minutes prior to meet Phone #: ###-#### 5th floor walls and hard lids in hallways ok to cover
BLD-Framing/Rough-in2/16/20162/16/20162/16/2016PPART
DetailsDave Hannah
Darren Phone #: ###-#### ok to cover hardlid ceiling in hallways on 6th floor
BLD-Framing/Rough-in2/4/20162/5/20162/5/2016APART
DetailsDave Hannah
Darren Phone #: ###-#### 6th floor ok to cover walls
BLD-Conference2/3/20162/3/20162/3/2016PDONE
DetailsDave Hannah
Call half hour before // Darin Phone #: ###-####