Permit Information
Permit NumberBLD16-00710
StatusFinaled
Name PKC CONSTRUCTION
Site Address 5610 W GAGE ST Unit: B
Project NameDaVita Table Rock Dialysis
Customer Number 
ePlanReviewNo
Description
(DAVITA TABLE ROCK DIALYSIS CENTER)(SUITE B) Remodel to an existing 9,844 sq. ft. space for use as a dialysis clinic per approved plans. This building was constructed under BLD96-01237. Work to include new exterior exit door, removing 1 restroom, remodel of 1 existing restroom, changes to traffic flow from lobby through tenant space. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/4/20168/5/20168/5/2016APASS
DetailsJim Sly
Ed Phone #: ###-####
Talked to Troy....Fire Alarm Permit and inspection passed. Not attached to this permit. OK for Perm Occ.
FIRE-Final Inspection8/5/20168/5/20168/5/2016PPASS
DetailsTroy Cobbley
life safety passed
BLD-Final7/4/20167/5/20167/5/2016PPART
DetailsMike Jordan
Tco fire, self preservation waiver onsite until sprinkler review Phone #: ###-#### Inspection requested via web by Ed Woods. Ok for temp occ. Needs to install ADA signage at restroom, lower sink to 34 inches, install mirror and grab bars, install glass at reception counter.
FIRE-Final Inspection7/4/20167/5/20167/5/2016APART
DetailsTroy Cobbley
A30 day temporary occupancy, for fire, is being given with scott's permission until the fire alarm modifications have been addressed.
BLD-Conference7/1/20167/1/20167/1/2016PCANC
DetailsJim Sly
Matt Phone #: ###-####
Need all fire finals.......
FIRE-Final Inspection7/1/20167/1/20167/1/2016PFAIL
DetailsTroy Cobbley
Finish installing ceiling tiles, mount fire extinguishers, finish installing hardware. The project related fire sprinkler (need tiles) and the fire alarm permit need addressed. Also as discussed a letter stating the facilities plan for "self preservation" needs to be provided prior to a 30 day temporary as discussed.
BLD-Ceiling Grid Inspection6/30/20167/1/20167/1/2016APASS
DetailsJim Sly
Matt Phone #: ###-####
BLD-Framing/Rough-in6/22/20166/23/20166/23/2016PPART
DetailsJim Sly
Rough. Frame, Rough Plm, Rough ele partial Phone #: ###-#### Inspection requested via web by Ed Woods
Treatment floor Framing OK......OK to one side select walls pending trade approvals.