DOC - Permit Finaled | | | 6/23/2016 | | DONE |
|
|
|
|
BLD-Final | 6/21/2016 | 6/22/2016 | 6/22/2016 | P | PASS |
Dave Hannah
|
|
|
Keith// please call 30 min. prior Phone #: ###-####
|
FIRE-Final Inspection | 6/14/2016 | 6/14/2016 | 6/14/2016 | P | PASS |
Katie Marron
|
|
|
Inspection for phase II, permit final life safety pass.
|
BLD-Final | 6/2/2016 | 6/6/2016 | 6/6/2016 | A | PEND |
Dave Hannah
|
|
|
Keith-partial final on 3rd floor to get temp c of o-please call 30 minutes prior Phone #: ###-#### ok to occ phase one
|
FIRE-Final Inspection | 6/2/2016 | 6/6/2016 | 6/6/2016 | A | PART |
Jim Page
|
|
|
Per conversation with point of contact Keith, phone ###-####, project is being completed in two phases, area considered phase one for area of work is the west side, no fire sprinkler modifications, no fire alarm modifications, fire extinguisher located by the elevator with a current inspection tag, final life fire safety inspection passed/complete for phase one. Phase two for this area or work is the east side of space, this area to be completed at later date.
|
BLD-Wall Bracing | 5/16/2016 | 5/16/2016 | 5/16/2016 | P | PASS |
Dave Hannah
|
|
|
Wall bracing at interior center wall that was removed and east wall where closets were.
|
BLD-Framing/Rough-in | 4/25/2016 | 4/27/2016 | 4/27/2016 | A | PASS |
Bob Archibald
|
|
|
Adan Phone #: ###-#### office walls ok to cover
|